2217 S GLYNDON AVE 90291
Certificate Information: 2217 S GLYNDON AVE 90291
- Application / Permit
- 21010-10000-05625
- Plan Check / Job No.
- B21LA20206
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 2-STORY ACCESSORY DWELLING UNIT PER LAMC 12.22.A.33.(c)-(d)
- Permit Issued
- Issued on 8/7/2023
- Issuing Office
- Current Status
- CofO Issued on 6/2/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | STARR CHEN |
| Corrections Issued | 11/26/2021 | STARR CHEN |
| Quality Review Completed | 12/2/2021 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 12/7/2021 | APPLICANT |
| Applicant returned to address corrections | 1/11/2023 | STARR CHEN |
| Plan Check Approved | 3/29/2023 | DANIEL YIP |
| Issued | 8/7/2023 | APPLICANT |
| CofO in Progress | 6/2/2026 | RUBEN RIVAS |
| Permit Finaled | 6/2/2026 | RICHARD STEINBACH |
| CofO Issued | 6/2/2026 | RICHARD STEINBACH |
| Permit Finaled | 6/2/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Address approval | Cleared | 12/20/2021 | DENNIS BRAGIN |
| Roof/Waste drainage to street | Cleared | 12/20/2021 | DENNIS BRAGIN |
| Specific Plan | Cleared | 3/3/2022 | PEDRO AYALA |
| Construction near power lines | Cleared | 11/29/2022 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 2/14/2023 | SAUL GARCIA |
| Sewer availability | Cleared | 2/14/2023 | SAUL GARCIA |
Contact Information
| Contractor | Pacific Coast Environments; Lic. No.: 616213-B | 5425 E MEZZANINE WAY LONG BEACH, CA 90808 |
Inspector Information
| RUBEN RIVAS, (310) 914-3981 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 1/16/2024 | Approved | TEMISTOCLES CAAL |
| Excavation/Setback/Form/Re-Bar | 1/19/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 3/6/2024 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 3/6/2024 | Approved | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 3/26/2024 | Partial Approval | HERBERT GIRON |
| Underground Mechanical | 3/26/2024 | Partial Approval | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 5/3/2024 | Corrections Issued | TEMISTOCLES CAAL |
| Floor/Roof Diaphrgm/Shear Wall | 5/7/2024 | Corrections Issued | TEMISTOCLES CAAL |
| ELECTRICAL-Rough | 5/10/2024 | Corrections Issued | HERBERT GIRON |
| Floor/Roof Diaphrgm/Shear Wall | 5/10/2024 | Approved | HERBERT GIRON |
| PLUMBING-Rough | 5/10/2024 | Approved | HERBERT GIRON |
| Sewer | 5/10/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Rough | 6/14/2024 | Approved | HERBERT GIRON |
| HVAC-Rough | 6/14/2024 | Corrections Issued | HERBERT GIRON |
| BUILDING-Rough-Frame | 8/5/2024 | Corrections Issued | HERBERT GIRON |
| Green Building Rough | 8/5/2024 | Approved | HERBERT GIRON |
| HVAC-Rough | 8/5/2024 | Approved | HERBERT GIRON |
| Interior/Exterior Lathing | 8/5/2024 | Partial Approval | HERBERT GIRON |
| Verify Sprinkler Sign Off | 8/5/2024 | Corrections Issued | HERBERT GIRON |
| Shower Pan | 8/7/2024 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 8/21/2024 | Conditional Approval | HERBERT GIRON |
| Insulation | 8/21/2024 | Approved | HERBERT GIRON |
| Drywall Nailing | 8/27/2024 | Approved | ARAM AVEDISIAN |
| ELECTRICAL-Final | 9/16/2024 | Corrections Issued | HERBERT GIRON |
| Interior/Exterior Lathing | 9/16/2024 | Approved | HERBERT GIRON |
| ELECTRICAL-Final | 6/16/2025 | Corrections Issued | JESUS RODRIGUEZ |
| HVAC-Final | 6/16/2025 | Corrections Issued | JESUS RODRIGUEZ |
| PLUMBING-Final | 6/16/2025 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 6/16/2025 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 1/27/2026 | Approved | RUBEN RIVAS |
| Final | 1/27/2026 | Corrections Issued | RUBEN RIVAS |
| Green Building Final | 1/27/2026 | Approved | RUBEN RIVAS |
| SGSOV-Seismic Gas S/O Valve | 1/27/2026 | SGSOV Approved | RUBEN RIVAS |
| Service/Power Release | 1/27/2026 | Not Ready for Inspection | RUBEN RIVAS |
| Final | 5/27/2026 | OK to Issue CofO | RUBEN RIVAS |
| Service/Power Release | 5/27/2026 | Approved | RUBEN RIVAS |