2050 S PARNELL AVE 90025
Certificate Information: 2050 S PARNELL AVE 90025
- Application / Permit
- 21010-10000-05624
- Plan Check / Job No.
- B21LA20213
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) 2-STORY SINGLE FAMILY DWELLING WITH BASEMENT AND 2-CAR GARAGE.
- Permit Issued
- Issued on 6/9/2022
- Issuing Office
- Current Status
- CofO Issued on 10/31/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 12/2/2021 | DANIEL YIP |
| Corrections Issued | 12/7/2021 | DANIEL YIP |
| Quality Review Completed | 12/15/2021 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 12/28/2021 | APPLICANT |
| Applicant returned to address corrections | 4/21/2022 | DANIEL YIP |
| Plan Check Approved | 4/25/2022 | DANIEL YIP |
| No Progress | 5/18/2022 | DANIEL YIP |
| Plan Check Approved | 5/18/2022 | DANIEL YIP |
| Issued | 6/9/2022 | APPLICANT |
| CofO in Progress | 10/30/2023 | STEPHANIE SWANSON |
| Permit Finaled | 10/31/2023 | DANIEL ORRANTE |
| CofO Issued | 10/31/2023 | DANIEL ORRANTE |
| Permit Finaled | 10/31/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 1/25/2022 | JOSE HERNANDEZ |
| Permit | Cleared | 1/25/2022 | JOSE HERNANDEZ |
| Eng Process Fee Ord 176,300 | Cleared | 1/29/2022 | JOSE HERNANDEZ |
| Sewer availability | Cleared | 1/29/2022 | JOSE HERNANDEZ |
| Hydrant and Access approval | Cleared | 3/5/2022 | CINDY JOSSELYN |
| Specific Plan | Cleared | 3/7/2022 | VALERIA CEJA |
| Trees in Parkway | Cleared | 3/30/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 4/13/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 4/20/2022 | JOSE HERNANDEZ |
| Excavation more than 5-ft deep | Cleared | 4/21/2022 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 4/21/2022 | DANIEL YIP |
| Grading Pre-Inspection | Cleared | 4/21/2022 | DANIEL YIP |
Contact Information
| Architect | Rezvani,, Farbod; Lic. No.: C32315 | 9055 ALCOTT STREET #1 LOS ANGELES, CA 90035 |
| Contractor | Di Nalli Construction; Lic. No.: 942979-B | 9055 ALCOTT STREET #1 LOS ANGELES, CA 90035 |
| Engineer | Askarian,, Soroosh; Lic. No.: C83413 | 22287 MULHOLLAND HWY 163 CALABASAS, CA 91302 |
Inspector Information
| DAVID SCANTLIN, (310) 914-3863 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 7/5/2022 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Reinf. Concrete | 7/11/2022 | Conditional Approval | MICHAEL PELHAM |
| METHANE-Subgrade | 8/17/2022 | Corrections Issued | ANDREW NAVE |
| Underground Mechanical | 8/17/2022 | Corrections Issued | ANDREW NAVE |
| METHANE-Rough | 8/19/2022 | Approved | ANDREW NAVE |
| Underground Mechanical | 8/19/2022 | Partial Approval | ANDREW NAVE |
| Deputy Methane Barrier | 8/23/2022 | Approved | MICHAEL PELHAM |
| Deputy Methane Barrier | 8/24/2022 | Approved | MICHAEL PELHAM |
| Footing/Foundation/Slab | 8/25/2022 | Conditional Approval | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Barrier | 8/25/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| METHANE-Subgrade | 8/25/2022 | Approved | GERMAN RODRIGUEZ MENDOZA |
| Reinforced Concrete Frame | 9/2/2022 | Approved | STEPHANIE SWANSON |
| Deputy Shotcrete | 9/7/2022 | Conditional Approval | STEPHANIE SWANSON |
| Deputy Methane Barrier | 10/24/2022 | Conditional Approval | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 10/25/2022 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 10/26/2022 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/10/2022 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2022 | Partial Approval | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2022 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 11/28/2022 | Conditional Approval | RICHARD STEINBACH |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2022 | Partial Approval | CHRISTOPHER WILSON |
| Deputy Wood Construction | 1/19/2023 | Conditional Approval | MICHAEL PELHAM |
| BUILDING-Rough-Frame | 1/23/2023 | Corrections Issued | STEPHANIE SWANSON |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2023 | Corrections Issued | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 2/2/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 2/15/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Rough | 2/15/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Rough | 2/17/2023 | Approved | STEPHANIE SWANSON |
| HVAC-Rough | 2/17/2023 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 2/27/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 2/27/2023 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 3/8/2023 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Rough | 3/8/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Rough | 3/8/2023 | Partial Approval | STEPHANIE SWANSON |
| METHANE-Rough | 3/8/2023 | Corrections Issued | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 3/29/2023 | Partial Approval | STEPHANIE SWANSON |
| Green Building Rough | 3/29/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| HVAC-Rough | 3/29/2023 | Approved | STEPHANIE SWANSON |
| METHANE-Rough | 3/29/2023 | Approved | STEPHANIE SWANSON |
| Verify Sprinkler Sign Off | 3/29/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/3/2023 | Conditional Approval | STEPHANIE SWANSON |
| Green Building Rough | 4/3/2023 | Approved | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 4/7/2023 | Approved | STEPHANIE SWANSON |
| Insulation | 4/7/2023 | Approved | STEPHANIE SWANSON |
| Drywall Nailing | 4/12/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Drywall Nailing | 4/14/2023 | Approved | STEPHANIE SWANSON |
| Interior/Exterior Lathing | 4/24/2023 | Approved | STEPHANIE SWANSON |
| Shower Pan | 4/24/2023 | Approved | STEPHANIE SWANSON |
| Final | 8/24/2023 | Corrections Issued | STEPHANIE SWANSON |
| HVAC-Final | 8/24/2023 | Corrections Issued | STEPHANIE SWANSON |
| PLUMBING-Final | 8/24/2023 | Corrections Issued | STEPHANIE SWANSON |
| Gas Test | 9/12/2023 | Approved | BRENDAN LOONEY |
| HVAC-Final | 9/12/2023 | Corrections Issued | BRENDAN LOONEY |
| PLUMBING-Final | 9/12/2023 | Not Ready for Inspection | BRENDAN LOONEY |
| Footing/Foundation/Slab | 9/21/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 9/28/2023 | Corrections Issued | STEPHANIE SWANSON |
| Final | 9/28/2023 | Corrections Issued | STEPHANIE SWANSON |
| Green Building Final | 9/28/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 9/28/2023 | Corrections Issued | STEPHANIE SWANSON |
| SGSOV-Seismic Gas S/O Valve | 9/28/2023 | SGSOV Approved | STEPHANIE SWANSON |
| Smoke Detectors | 9/28/2023 | Approved | STEPHANIE SWANSON |
| ELECTRICAL-Final | 10/27/2023 | Approved | STEPHANIE SWANSON |
| Final | 10/27/2023 | Conditional Approval | STEPHANIE SWANSON |
| HVAC-Final | 10/27/2023 | Approved | STEPHANIE SWANSON |
| PLUMBING-Final | 10/27/2023 | Approved | STEPHANIE SWANSON |
| Service/Power Release | 10/27/2023 | Approved | STEPHANIE SWANSON |
| Final | 10/30/2023 | OK to Issue CofO | STEPHANIE SWANSON |