2602 E LANCASTER AVE 90033
Certificate Information: 2602 E LANCASTER AVE 90033
- Application / Permit
- 21010-10000-05611
- Plan Check / Job No.
- B21LA20178
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 1-STORY ADU PER ORDINANCE AT REAR OF LOT.
- Permit Issued
- Issued on 4/18/2024
- Issuing Office
- Metro
- Current Status
- CofO Issued on 5/3/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 3/11/2022 | APPLICANT |
| Assigned to Plan Check Engineer | 3/16/2022 | LAWRENCE QUIRANTE |
| Corrections Issued | 3/16/2022 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 4/13/2022 | APPLICANT |
| Applicant returned to address corrections | 1/23/2024 | ADAM HEGAZI |
| Plan Check Approved | 3/20/2024 | ADAM HEGAZI |
| Issued | 4/18/2024 | APPLICANT |
| CofO in Progress | 5/2/2025 | ALIZAH MAYAGOITIA |
| Permit Finaled | 5/3/2025 | DEROLD HAUFF |
| CofO Issued | 5/3/2025 | DEROLD HAUFF |
| Permit Finaled | 5/3/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/14/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 10/19/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 10/19/2022 | CHRISTOPHER ROCHA |
| Low Impact Development | Cleared | 2/21/2023 | CHRIS VONG |
| Grading Pre-Inspection | Cleared | 1/23/2024 | LAWRENCE QUIRANTE |
| GPI Written Notices | Cleared | 3/20/2024 | LAWRENCE QUIRANTE |
| Roof/Waste drainage to street | Cleared | 3/20/2024 | TERRY PHAN |
Contact Information
| Contractor | Viera Design & Construction; Lic. No.: 972064-B | 17646 E BENBOW ST COVINA, CA 91722 |
| Engineer | Alson,, Ken; Lic. No.: C41697 | 9744 MAPLE ST 201 BELLFLOWER, CA 90706 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 5/31/2024 | Corrections Issued | OSVALDO PARAMO |
| Footing/Foundation/Slab | 5/31/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Excavation/Setback/Form/Re-Bar | 6/12/2024 | Approved | OSVALDO PARAMO |
| Footing/Foundation/Slab | 6/12/2024 | Approved | OSVALDO PARAMO |
| PLUMBING-Rough | 7/1/2024 | Corrections Issued | LILIANA PORTILLO |
| PLUMBING-Rough | 7/2/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Wood Frame | 7/2/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 7/5/2024 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 7/8/2024 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 7/22/2024 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 7/29/2024 | Partial Approval | ALIZAH MAYAGOITIA |
| ELECTRICAL-Rough | 8/15/2024 | Approved | ALIZAH MAYAGOITIA |
| HVAC-Rough | 8/15/2024 | Approved | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 8/15/2024 | Corrections Issued | ALIZAH MAYAGOITIA |
| PLUMBING-Rough | 8/23/2024 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 8/23/2024 | Partial Inspection | OSVALDO PARAMO |
| ELECTRICAL-Rough | 8/27/2024 | Approved | LUIS CASTRO |
| Gas Test | 8/29/2024 | Partial Inspection | OSVALDO PARAMO |
| Underground Mechanical | 8/29/2024 | Partial Inspection | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/4/2024 | Not Ready for Inspection | LUIS CASTRO |
| Underground Mechanical | 9/4/2024 | Partial Approval | LUIS CASTRO |
| BUILDING-Rough-Frame | 9/11/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Green Building Rough | 9/11/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/11/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| MERV13>=Rough | 9/11/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| PLUMBING-Rough | 9/11/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 9/11/2024 | Not Ready for Inspection | OSVALDO PARAMO |
| Interior/Exterior Lathing | 9/16/2024 | Approved | LUIS CASTRO |
| Underground Mechanical | 9/16/2024 | Approved | LUIS CASTRO |
| Shower Pan | 10/8/2024 | Approved | JOHN QUINTANILLA |
| Wood Frame | 10/8/2024 | Approved | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 10/16/2024 | Approved | OSVALDO PARAMO |
| Green Building Rough | 10/16/2024 | Approved | OSVALDO PARAMO |
| MERV13>=Rough | 10/16/2024 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 10/16/2024 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 11/5/2024 | Approved | ALIZAH MAYAGOITIA |
| Sewer | 12/17/2024 | Partial Approval | ANTHONY RAMOS |
| Underground Mechanical | 12/17/2024 | Partial Approval | ANTHONY RAMOS |
| Final | 2/26/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 2/26/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| MERV13>=Final | 2/26/2025 | Approved | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 2/26/2025 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 2/26/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 2/26/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 3/5/2025 | Corrections Issued | ALIZAH MAYAGOITIA |
| Green Building Final | 3/5/2025 | Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 3/5/2025 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 4/30/2025 | Conditional Approval | ALIZAH MAYAGOITIA |
| Service/Power Release | 4/30/2025 | Approved | ALIZAH MAYAGOITIA |
| Final | 5/2/2025 | OK to Issue CofO | ALIZAH MAYAGOITIA |