2602 E LANCASTER AVE 90033

Certificate Information: 2602 E LANCASTER AVE 90033

Application / Permit
21010-10000-05611
Plan Check / Job No.
B21LA20178
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 1-STORY ADU PER ORDINANCE AT REAR OF LOT.
Permit Issued
Issued on 4/18/2024
Issuing Office
Metro
Current Status
CofO Issued on 5/3/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 3/11/2022 APPLICANT
Assigned to Plan Check Engineer 3/16/2022 LAWRENCE QUIRANTE
Corrections Issued 3/16/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 4/13/2022 APPLICANT
Applicant returned to address corrections 1/23/2024 ADAM HEGAZI
Plan Check Approved 3/20/2024 ADAM HEGAZI
Issued 4/18/2024 APPLICANT
CofO in Progress 5/2/2025 ALIZAH MAYAGOITIA
Permit Finaled 5/3/2025 DEROLD HAUFF
CofO Issued 5/3/2025 DEROLD HAUFF
Permit Finaled 5/3/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 10/14/2022 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 10/19/2022 CHRISTOPHER ROCHA
Sewer availability Cleared 10/19/2022 CHRISTOPHER ROCHA
Low Impact Development Cleared 2/21/2023 CHRIS VONG
Grading Pre-Inspection Cleared 1/23/2024 LAWRENCE QUIRANTE
GPI Written Notices Cleared 3/20/2024 LAWRENCE QUIRANTE
Roof/Waste drainage to street Cleared 3/20/2024 TERRY PHAN

Contact Information

Contractor Viera Design & Construction; Lic. No.: 972064-B 17646 E BENBOW ST      COVINA, CA 91722
Engineer Alson,, Ken; Lic. No.: C41697 9744 MAPLE ST 201      BELLFLOWER, CA 90706

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 5/31/2024 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 5/31/2024 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 6/12/2024 Approved OSVALDO PARAMO
Footing/Foundation/Slab 6/12/2024 Approved OSVALDO PARAMO
PLUMBING-Rough 7/1/2024 Corrections Issued LILIANA PORTILLO
PLUMBING-Rough 7/2/2024 Partial Approval ALIZAH MAYAGOITIA
Wood Frame 7/2/2024 Partial Approval ALIZAH MAYAGOITIA
Insulation 7/5/2024 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 7/8/2024 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 7/22/2024 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 7/29/2024 Partial Approval ALIZAH MAYAGOITIA
ELECTRICAL-Rough 8/15/2024 Approved ALIZAH MAYAGOITIA
HVAC-Rough 8/15/2024 Approved ALIZAH MAYAGOITIA
PLUMBING-Rough 8/15/2024 Corrections Issued ALIZAH MAYAGOITIA
PLUMBING-Rough 8/23/2024 Approved OSVALDO PARAMO
Underground Mechanical 8/23/2024 Partial Inspection OSVALDO PARAMO
ELECTRICAL-Rough 8/27/2024 Approved LUIS CASTRO
Gas Test 8/29/2024 Partial Inspection OSVALDO PARAMO
Underground Mechanical 8/29/2024 Partial Inspection OSVALDO PARAMO
Interior/Exterior Lathing 9/4/2024 Not Ready for Inspection LUIS CASTRO
Underground Mechanical 9/4/2024 Partial Approval LUIS CASTRO
BUILDING-Rough-Frame 9/11/2024 Not Ready for Inspection OSVALDO PARAMO
Green Building Rough 9/11/2024 Not Ready for Inspection OSVALDO PARAMO
Interior/Exterior Lathing 9/11/2024 Not Ready for Inspection OSVALDO PARAMO
MERV13>=Rough 9/11/2024 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Rough 9/11/2024 Not Ready for Inspection OSVALDO PARAMO
Verify Sprinkler Sign Off 9/11/2024 Not Ready for Inspection OSVALDO PARAMO
Interior/Exterior Lathing 9/16/2024 Approved LUIS CASTRO
Underground Mechanical 9/16/2024 Approved LUIS CASTRO
Shower Pan 10/8/2024 Approved JOHN QUINTANILLA
Wood Frame 10/8/2024 Approved JOHN QUINTANILLA
BUILDING-Rough-Frame 10/16/2024 Approved OSVALDO PARAMO
Green Building Rough 10/16/2024 Approved OSVALDO PARAMO
MERV13>=Rough 10/16/2024 Approved OSVALDO PARAMO
Verify Sprinkler Sign Off 10/16/2024 Approved OSVALDO PARAMO
Drywall Nailing 11/5/2024 Approved ALIZAH MAYAGOITIA
Sewer 12/17/2024 Partial Approval ANTHONY RAMOS
Underground Mechanical 12/17/2024 Partial Approval ANTHONY RAMOS
Final 2/26/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 2/26/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
MERV13>=Final 2/26/2025 Approved ALIZAH MAYAGOITIA
SGSOV-Seismic Gas S/O Valve 2/26/2025 SGSOV Approved ALIZAH MAYAGOITIA
Service/Power Release 2/26/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Smoke Detectors 2/26/2025 Approved ALIZAH MAYAGOITIA
Final 3/5/2025 Corrections Issued ALIZAH MAYAGOITIA
Green Building Final 3/5/2025 Approved ALIZAH MAYAGOITIA
Service/Power Release 3/5/2025 Not Ready for Inspection ALIZAH MAYAGOITIA
Final 4/30/2025 Conditional Approval ALIZAH MAYAGOITIA
Service/Power Release 4/30/2025 Approved ALIZAH MAYAGOITIA
Final 5/2/2025 OK to Issue CofO ALIZAH MAYAGOITIA