2367 N EDGEWATER TER 90039
Certificate Information: 2367 N EDGEWATER TER 90039
- Application / Permit
- 21010-10000-05608
- Plan Check / Job No.
- B21LA20160
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. NEW 2-STORY DETACHED ACCESSORY DWELLING UNIT PER STANDARD PLAN PER LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 4/7/2022
- Issuing Office
- Current Status
- CofO Issued on 5/2/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2021 | KEVIN MORALES |
| Corrections Issued | 11/1/2021 | KEVIN MORALES |
| Applicant returned to address corrections | 11/25/2021 | KEVIN MORALES |
| Plan Check Approved | 2/10/2022 | KEVIN MORALES |
| Issued | 4/7/2022 | APPLICANT |
| CofO in Progress | 4/30/2024 | JOSEPH MCGARRY |
| Permit Finaled | 5/2/2024 | DEROLD HAUFF |
| CofO Issued | 5/2/2024 | DEROLD HAUFF |
| Permit Finaled | 5/2/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/9/2021 | CINDY QI |
| Certificate of Compliance | Cleared | 11/9/2021 | ANACANY HURTADO |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2021 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 11/9/2021 | CINDY QI |
| Sewer availability | Cleared | 11/9/2021 | CINDY QI |
| Tract Map conditions | Cleared | 11/9/2021 | ANACANY HURTADO |
| Tract Map conditions | Cleared | 11/9/2021 | ANACANY HURTADO |
| Grading Pre-Inspection | Cleared | 12/1/2021 | ROBERT HUGHES |
| Hydrant and Access approval | Cleared | 2/4/2022 | MATTHEW CRAIG |
Contact Information
| Architect | Taalman,, Linda Evelyn; Lic. No.: NA30187 | , |
| Contractor | Mota Builders Inc; Lic. No.: 1070384-B | 15364 WYANDOTTE ST VAN NUYS, CA 91406 |
Inspector Information
| ENRIQUE MIRELES, (213) 202-3438 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/24/2022 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 6/10/2022 | Partial Approval | JOSEPH MCGARRY |
| Rough-Elec/Plmb/HVAC | 8/3/2022 | Partial Approval | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 8/25/2022 | Conditional Approval | JOSEPH MCGARRY |
| Underground Mechanical | 12/8/2022 | Approved | JOSEPH MCGARRY |
| Deputy Drilled-In Anchors | 12/15/2022 | Partial Approval | JEFFREY MEAD |
| ELECTRICAL-Rough | 2/28/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| HVAC-Rough | 2/28/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 2/28/2023 | Partial Approval | JOSEPH MCGARRY |
| Light Gage Steel Frame | 2/28/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| PLUMBING-Rough | 2/28/2023 | Not Ready for Inspection | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 3/13/2023 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 3/13/2023 | Conditional Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/13/2023 | Approved | JOSEPH MCGARRY |
| Structural Steel Frame | 3/13/2023 | Conditional Approval | JOSEPH MCGARRY |
| ELECTRICAL-Rough | 3/15/2023 | Approved | JOSEPH MCGARRY |
| HVAC-Rough | 3/15/2023 | Conditional Approval | JOSEPH MCGARRY |
| PLUMBING-Rough | 3/15/2023 | Approved | JOSEPH MCGARRY |
| Drywall Nailing | 6/26/2023 | Approved | JOSEPH MCGARRY |
| Green Building Rough | 6/26/2023 | Approved | JOSEPH MCGARRY |
| Interior/Exterior Lathing | 6/26/2023 | Approved | JOSEPH MCGARRY |
| BUILDING-Rough-Frame | 1/26/2024 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 1/26/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Final | 1/26/2024 | Corrections Issued | LILIANA PORTILLO |
| Footing/Foundation/Slab | 1/26/2024 | Approved | LILIANA PORTILLO |
| Green Building Final | 1/26/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| HVAC-Final | 1/26/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Insulation | 1/26/2024 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 1/26/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 1/26/2024 | SGSOV Not Required | LILIANA PORTILLO |
| Service/Power Release | 1/26/2024 | Not Ready for Inspection | LILIANA PORTILLO |
| Smoke Detectors | 1/26/2024 | Approved | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 1/26/2024 | Approved | LILIANA PORTILLO |
| Final | 4/25/2024 | OK to Issue CofO | JOSEPH MCGARRY |
| Green Building Final | 4/25/2024 | Approved | JOSEPH MCGARRY |
| Service/Power Release | 4/25/2024 | Not Required | JOSEPH MCGARRY |