3624 S 9TH AVE 90018
Certificate Information: 3624 S 9TH AVE 90018
- Application / Permit
- 21010-10000-05600
- Plan Check / Job No.
- B21LA20140
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED ADU AT REAR OF LOT PER LAMC 12.22 A.33(c)-(d) ALL WORK DONE PER WFPP. SEE COMMENT.
- Permit Issued
- Issued on 4/1/2022
- Issuing Office
- Current Status
- CofO Issued on 9/29/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/29/2021 | TSE MING HUANG |
| Corrections Issued | 10/31/2021 | TSE MING HUANG |
| Applicant returned to address corrections | 1/4/2022 | SINA KHOSRAVI |
| Applicant returned to address corrections | 2/18/2022 | TSE MING HUANG |
| Applicant returned to address corrections | 3/4/2022 | TSE MING HUANG |
| Plan Check Approved | 3/8/2022 | TSE MING HUANG |
| Issued | 4/1/2022 | APPLICANT |
| Building Plans Picked Up | 4/1/2022 | APPLICANT |
| CofO in Progress | 9/14/2022 | STUART CHAPMAN |
| Permit Finaled | 9/29/2022 | DEROLD HAUFF |
| CofO Issued | 9/29/2022 | DEROLD HAUFF |
| Permit Finaled | 9/29/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/8/2021 | ABEL CASILLAS |
| Eng Process Fee Ord 176,300 | Cleared | 11/9/2021 | ABEL CASILLAS |
| Sewer availability | Cleared | 11/9/2021 | ABEL CASILLAS |
| Low Impact Development | Cleared | 12/10/2021 | TA ANH |
| Roof/Waste drainage to street | Cleared | 12/13/2021 | ABEL CASILLAS |
| Hydrant and Access approval | Cleared | 2/7/2022 | DWAYNE LAURENT |
Contact Information
| Contractor | Daniel Pascuale; Lic. No.: 573067-B | 18729 CLARK DALE AVE #C ARTESIA, CA 90701 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/5/2022 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 4/5/2022 | Corrections Issued | STUART CHAPMAN |
| Underground Mechanical | 4/5/2022 | Approved | STUART CHAPMAN |
| Excavation/Setback/Form/Re-Bar | 4/14/2022 | Approved | STUART CHAPMAN |
| Footing/Foundation/Slab | 4/14/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/24/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 5/24/2022 | Not Ready for Inspection | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 5/24/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 5/24/2022 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 5/24/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 5/24/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 5/26/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2022 | Corrections Issued | STUART CHAPMAN |
| HVAC-Rough | 5/26/2022 | Corrections Issued | STUART CHAPMAN |
| PLUMBING-Rough | 5/26/2022 | Approved | STUART CHAPMAN |
| Sewer | 5/26/2022 | Approved | STUART CHAPMAN |
| Underground Mechanical | 5/26/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 6/2/2022 | Partial Approval | STUART CHAPMAN |
| Insulation | 6/7/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 6/9/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Rough | 6/9/2022 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 6/17/2022 | Approved | STUART CHAPMAN |
| Drywall Nailing | 6/17/2022 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 6/17/2022 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 6/17/2022 | Approved | STUART CHAPMAN |
| Final | 8/23/2022 | Corrections Issued | STUART CHAPMAN |
| Green Building Final | 8/23/2022 | Approved | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 8/23/2022 | SGSOV Not Ready | STUART CHAPMAN |
| Service/Power Release | 8/23/2022 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 8/23/2022 | Approved | STUART CHAPMAN |
| Final | 8/30/2022 | Corrections Issued | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 8/30/2022 | SGSOV Approved | STUART CHAPMAN |
| Service/Power Release | 8/30/2022 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Final | 9/8/2022 | Approved | STUART CHAPMAN |
| Final | 9/8/2022 | Conditional Approval | STUART CHAPMAN |
| HVAC-Final | 9/8/2022 | Approved | STUART CHAPMAN |
| PLUMBING-Final | 9/8/2022 | Approved | STUART CHAPMAN |
| Service/Power Release | 9/8/2022 | Approved | STUART CHAPMAN |
| Final | 9/12/2022 | Corrections Issued | STUART CHAPMAN |
| Final | 9/14/2022 | OK to Issue CofO | STUART CHAPMAN |