1189 W 37TH PL 1-4 90007
Certificate Information: 1189 W 37TH PL 1-4 90007
- Application / Permit
- 21010-10000-05577
- Plan Check / Job No.
- B21LA20050
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 3 STORY 4-UNIT APARTMENT WITH ATTACHED RECREATION ROOM
- Permit Issued
- Issued on 9/13/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | ARMEN JIVALAGIAN |
| Disabled Access Plans Picked Up | 11/23/2021 | APPLICANT |
| Corrections Issued | 11/30/2021 | ARMEN JIVALAGIAN |
| Quality Review Completed | 11/30/2021 | PETER KIM |
| Building Plans Picked Up | 12/7/2021 | APPLICANT |
| Green Plans Picked Up | 1/24/2022 | APPLICANT |
| Applicant returned to address corrections | 2/1/2022 | ARMEN JIVALAGIAN |
| Plan Check Approved | 9/8/2022 | ARMEN JIVALAGIAN |
| Issued | 9/13/2022 | APPLICANT |
| CofO in Progress | 9/14/2023 | JAMES POWERS |
| CofO Issued | 9/21/2023 | ERNESTO CORRAL |
| Permit Finaled | 9/21/2023 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 12/28/2021 | CELINA MORENO |
| Permit | Cleared | 12/28/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 1/3/2022 | CHRISTOPHER ROCHA |
| Highway dedication | Cleared | 3/2/2022 | CHRISTOPHER ROCHA |
| Hydrant and Access approval | Cleared | 3/3/2022 | KURT CORRAL |
| Trees in Parkway | Cleared | 3/23/2022 | ARMEN JIVALAGIAN |
| DAS Clearance | Cleared | 5/5/2022 | SHINE LIN |
| Green Code | Cleared | 5/16/2022 | AARON COSTA |
| Green Code | Cleared | 5/16/2022 | AARON COSTA |
| Sewer availability | Cleared | 5/27/2022 | CHRISTOPHER ROCHA |
| Low Impact Development | Cleared | 6/8/2022 | LONDY ALVARADO |
| Frnt yard landscape/Water mgmt | Cleared | 6/9/2022 | MAYELA VILLA |
| Prkng lot landscape/Water mgmt | Cleared | 6/9/2022 | MAYELA VILLA |
| Roof/Waste drainage to street | Cleared | 6/9/2022 | CELINA MORENO |
| ZI | Cleared | 6/15/2022 | RAFAEL FONTES |
| Fire Marshal Fire Life Safety | Cleared | 7/13/2022 | DOMINIQUE MEDINA |
Contact Information
| Contractor | B & Sons Construction Inc; Lic. No.: 1066259-B | 4361 E MISSION BLVD #37 MONTCLAIR, CA 91763 |
| Engineer | Dejban,, Masoud; Lic. No.: S2521 | 17200 VENTURA BLVD STE 213A ENCINO, CA 91316 |
| Engineer | Lee,, Sang Wook; Lic. No.: C56699 | 4664 W MAPLEWOOD AVE #305 LOS ANGELES, CA 90004 |
| Engineer | Nazemi,, Hassan Steve; Lic. No.: C44100 | 275 CENTENNIAL WAY 205 TUSTIN, CA 92780 |
| Engineer | Smith,, Melvin Bruce; Lic. No.: GE2673 | 2165 N MARVEL AVE SIMI VALLEY, CA 93065 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/31/2022 | Partial Approval | JAMES POWERS |
| METHANE-Barrier | 10/31/2022 | Approved | JAMES POWERS |
| METHANE-Subgrade | 10/31/2022 | Approved | JAMES POWERS |
| Footing/Foundation/Slab | 11/4/2022 | Approved | GREGORY POMISH |
| Deputy Wood Construction | 11/16/2022 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/17/2022 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 11/23/2022 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/23/2022 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 12/7/2022 | Conditional Approval | MICHAEL ROSENBERG |
| Floor/Roof Diaphrgm/Shear Wall | 1/18/2023 | Partial Approval | JAMES POWERS |
| Green Building Rough | 1/18/2023 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Rough | 1/18/2023 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 1/18/2023 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 1/18/2023 | Not Ready for Inspection | JAMES POWERS |
| Green Building Rough | 2/17/2023 | Approved | JAMES POWERS |
| METHANE-Rough | 2/17/2023 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 2/17/2023 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 2/17/2023 | Partial Approval | JAMES POWERS |
| Insulation | 2/23/2023 | Approved | JAMES POWERS |
| Drywall Nailing | 3/2/2023 | Partial Approval | JAMES POWERS |
| Interior/Exterior Lathing | 3/2/2023 | Not Ready for Inspection | JAMES POWERS |
| Drywall Nailing | 3/23/2023 | Approved | JAMES POWERS |
| Insulation | 3/23/2023 | Approved | JAMES POWERS |
| Final | 7/26/2023 | OK for TCO | JAMES POWERS |
| Green Building Final | 7/26/2023 | Approved | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 7/26/2023 | SGSOV Approved | JAMES POWERS |
| Smoke Detectors | 7/26/2023 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 7/26/2023 | Approved | JAMES POWERS |
| Wood Frame | 7/26/2023 | Approved | JAMES POWERS |
| Final | 9/14/2023 | OK to Issue CofO | JAMES POWERS |