5044 1/2 N HARTWICK ST 90041
Certificate Information: 5044 1/2 N HARTWICK ST 90041
- Application / Permit
- 21010-10000-05574
- Plan Check / Job No.
- B21LA20030
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 1-STORY A.D.U. PER STATE LAW AT REAR OF LOT.
- Permit Issued
- Issued on 5/20/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 8/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/1/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 11/2/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 4/21/2022 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 4/25/2022 | APPLICANT |
| Plan Check Approved | 5/12/2022 | LAWRENCE QUIRANTE |
| Issued | 5/20/2022 | APPLICANT |
| CofO in Progress | 8/1/2023 | SCOTT FINNILA |
| Permit Finaled | 8/13/2023 | DEROLD HAUFF |
| CofO Issued | 8/13/2023 | DEROLD HAUFF |
| Permit Finaled | 8/13/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/21/2022 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 1/21/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 1/26/2022 | JEANETTE VONG |
| Grading Pre-Inspection | Cleared | 1/27/2022 | ROBERT HUGHES |
| Low Impact Development | Cleared | 3/21/2022 | TA ANH |
| GPI Written Notices | Cleared | 5/12/2022 | LAWRENCE QUIRANTE |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Li,, Dacheng David; Lic. No.: C58075 | 1400 N KRAEMER BLVD #712 PLACENTIA, CA 92781 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 9/30/2022 | Approved | CRAIG VAUGHAN |
| Footing/Foundation/Slab | 11/16/2022 | Partial Inspection | SCOTT FINNILA |
| Underground Mechanical | 11/16/2022 | Corrections Issued | SCOTT FINNILA |
| Footing/Foundation/Slab | 11/17/2022 | Approved | SCOTT FINNILA |
| Underground Mechanical | 11/17/2022 | Partial Approval | SCOTT FINNILA |
| Deputy Drilled-In Anchors | 12/16/2022 | Conditional Approval | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 12/20/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/20/2022 | Approved | BRIAN SULLIVAN |
| Green Building Rough | 12/20/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Verify Sprinkler Sign Off | 12/20/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 12/30/2022 | Conditional Approval | AMY COLIN |
| ELECTRICAL-Rough | 12/30/2022 | Corrections Issued | AMY COLIN |
| PLUMBING-Rough | 12/30/2022 | Corrections Issued | AMY COLIN |
| BUILDING-Rough-Frame | 2/1/2023 | Approved | CRAIG VAUGHAN |
| Green Building Rough | 2/1/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 2/1/2023 | Corrections Issued | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 2/1/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 2/3/2023 | Corrections Issued | CRAIG VAUGHAN |
| Insulation | 2/3/2023 | Approved | CRAIG VAUGHAN |
| Drywall Nailing | 2/13/2023 | Approved | CRAIG VAUGHAN |
| Underground Mechanical | 3/29/2023 | Partial Approval | SCOTT FINNILA |
| Final | 5/3/2023 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 5/3/2023 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 5/3/2023 | SGSOV Not Ready | CRAIG VAUGHAN |
| Service/Power Release | 5/3/2023 | Corrections Issued | CRAIG VAUGHAN |
| Smoke Detectors | 5/3/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Final | 6/26/2023 | Corrections Issued | BRIAN SULLIVAN |
| SGSOV-Seismic Gas S/O Valve | 6/26/2023 | SGSOV Approved | BRIAN SULLIVAN |
| Service/Power Release | 6/26/2023 | Approved | BRIAN SULLIVAN |
| Smoke Detectors | 6/26/2023 | Approved | BRIAN SULLIVAN |
| Final | 7/31/2023 | OK to Issue CofO | SCOTT FINNILA |