5044 1/2 N HARTWICK ST 90041

Certificate Information: 5044 1/2 N HARTWICK ST 90041

Application / Permit
21010-10000-05574
Plan Check / Job No.
B21LA20030
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 1-STORY A.D.U. PER STATE LAW AT REAR OF LOT.
Permit Issued
Issued on 5/20/2022
Issuing Office
Metro
Current Status
CofO Issued on 8/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/28/2021 APPLICANT
Assigned to Plan Check Engineer 11/1/2021 LAWRENCE QUIRANTE
Corrections Issued 11/2/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 4/21/2022 LAWRENCE QUIRANTE
Building Plans Picked Up 4/25/2022 APPLICANT
Plan Check Approved 5/12/2022 LAWRENCE QUIRANTE
Issued 5/20/2022 APPLICANT
CofO in Progress 8/1/2023 SCOTT FINNILA
Permit Finaled 8/13/2023 DEROLD HAUFF
CofO Issued 8/13/2023 DEROLD HAUFF
Permit Finaled 8/13/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 1/21/2022 JEANETTE VONG
Roof/Waste drainage to street Cleared 1/21/2022 JEANETTE VONG
Eng Process Fee Ord 176,300 Cleared 1/26/2022 JEANETTE VONG
Sewer availability Cleared 1/26/2022 JEANETTE VONG
Grading Pre-Inspection Cleared 1/27/2022 ROBERT HUGHES
Low Impact Development Cleared 3/21/2022 TA ANH
GPI Written Notices Cleared 5/12/2022 LAWRENCE QUIRANTE

Contact Information

Contractor Owner-Builder       ,
Engineer Li,, Dacheng David; Lic. No.: C58075 1400 N KRAEMER BLVD #712      PLACENTIA, CA 92781

Inspector Information

RONNIE MEDINA, (213) 469-5852 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/30/2022 Approved CRAIG VAUGHAN
Footing/Foundation/Slab 11/16/2022 Partial Inspection SCOTT FINNILA
Underground Mechanical 11/16/2022 Corrections Issued SCOTT FINNILA
Footing/Foundation/Slab 11/17/2022 Approved SCOTT FINNILA
Underground Mechanical 11/17/2022 Partial Approval SCOTT FINNILA
Deputy Drilled-In Anchors 12/16/2022 Conditional Approval CRAIG VAUGHAN
BUILDING-Rough-Frame 12/20/2022 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 12/20/2022 Approved BRIAN SULLIVAN
Green Building Rough 12/20/2022 Not Ready for Inspection BRIAN SULLIVAN
Verify Sprinkler Sign Off 12/20/2022 Not Ready for Inspection BRIAN SULLIVAN
BUILDING-Rough-Frame 12/30/2022 Conditional Approval AMY COLIN
ELECTRICAL-Rough 12/30/2022 Corrections Issued AMY COLIN
PLUMBING-Rough 12/30/2022 Corrections Issued AMY COLIN
BUILDING-Rough-Frame 2/1/2023 Approved CRAIG VAUGHAN
Green Building Rough 2/1/2023 Approved CRAIG VAUGHAN
HVAC-Rough 2/1/2023 Corrections Issued CRAIG VAUGHAN
Verify Sprinkler Sign Off 2/1/2023 Approved CRAIG VAUGHAN
HVAC-Rough 2/3/2023 Corrections Issued CRAIG VAUGHAN
Insulation 2/3/2023 Approved CRAIG VAUGHAN
Drywall Nailing 2/13/2023 Approved CRAIG VAUGHAN
Underground Mechanical 3/29/2023 Partial Approval SCOTT FINNILA
Final 5/3/2023 Corrections Issued CRAIG VAUGHAN
Green Building Final 5/3/2023 Approved CRAIG VAUGHAN
SGSOV-Seismic Gas S/O Valve 5/3/2023 SGSOV Not Ready CRAIG VAUGHAN
Service/Power Release 5/3/2023 Corrections Issued CRAIG VAUGHAN
Smoke Detectors 5/3/2023 Not Ready for Inspection CRAIG VAUGHAN
Final 6/26/2023 Corrections Issued BRIAN SULLIVAN
SGSOV-Seismic Gas S/O Valve 6/26/2023 SGSOV Approved BRIAN SULLIVAN
Service/Power Release 6/26/2023 Approved BRIAN SULLIVAN
Smoke Detectors 6/26/2023 Approved BRIAN SULLIVAN
Final 7/31/2023 OK to Issue CofO SCOTT FINNILA