629 N KINGSLEY DR 90004

Certificate Information: 629 N KINGSLEY DR 90004

Application / Permit
21010-10000-05568
Plan Check / Job No.
B21LA20010
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(FRONT OF LOT) (N) 3-STORY DUPLEX WITH ATTACHED ADU AND (N) GARAGE COMPLY WITH DEPARTMENT ORDER effective date 10/27/2021. PERMIT WILL EXPIRE 30 DAYS FROM ISSUANCE DATE
Permit Issued
Issued on 4/19/2022
Issuing Office
Current Status
CofO Corrected on 1/6/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2021 APPLICANT
Assigned to Plan Check Engineer 11/9/2021 CARLOS MONTES
Corrections Issued 11/15/2021 CARLOS MONTES
Quality Review Completed 11/18/2021 KEN GILL
Plan Check Approved 4/8/2022 CARLOS MONTES
Issued 4/19/2022 APPLICANT
Building Plans Picked Up 4/25/2022 APPLICANT
CofO in Progress 11/26/2024 JEFFREY MEAD
CofO Issued-Status Void 12/3/2024 DEROLD HAUFF
Permit Finaled-Status Void 12/3/2024 DEROLD HAUFF
Re-Activate Permit 5/7/2025 DEROLD HAUFF
No Progress 10/11/2025 DEROLD HAUFF
CofO in Progress 10/11/2025 DEROLD HAUFF
Permit Finaled 1/6/2026 DEROLD HAUFF
CofO Corrected 1/6/2026 DEROLD HAUFF
Permit Finaled 1/6/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/15/2021 CINDY QI
Eng Process Fee Ord 176,300 Cleared 12/20/2021 CINDY QI
Frnt yard landscape/Water mgmt Cleared 12/20/2021 KENTON TRINH
Low Impact Development Cleared 12/20/2021 CHRIS VONG
Sewer availability Cleared 12/20/2021 CINDY QI
Roof/Waste drainage to street Cleared 1/13/2022 CINDY QI
Highway dedication Cleared 2/14/2022 CINDY QI
Hydrant and Access approval Cleared 3/31/2022 RUEL COLE

Contact Information

Contractor Rios William A; Lic. No.: 866335-B P O BOX 1061      DOWNEY, CA 90240
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/29/2022 Approved SHAVONNE ESPINOZA
Footing/Foundation/Slab 5/17/2022 Approved SHAVONNE ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/11/2022 Partial Approval ADAM ESCOTO
Floor/Roof Diaphrgm/Shear Wall 7/1/2022 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 8/2/2022 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 8/15/2022 Approved JEFFREY MEAD
ELECTRICAL-Rough 11/2/2022 Partial Approval JEFFREY MEAD
HVAC-Rough 11/2/2022 Partial Approval JEFFREY MEAD
PLUMBING-Rough 11/2/2022 Approved JEFFREY MEAD
Wood Frame 11/9/2022 Partial Inspection JULIAN AMAYA
ELECTRICAL-Rough 11/22/2022 Approved JEFFREY MEAD
HVAC-Rough 11/22/2022 Approved JEFFREY MEAD
Wood Frame 11/22/2022 Partial Approval JEFFREY MEAD
Insulation 12/8/2022 Approved JEFFREY MEAD
Interior/Exterior Lathing 12/8/2022 Approved JEFFREY MEAD
Drywall Nailing 12/19/2022 Approved JEFFREY MEAD
Green Building Rough 12/19/2022 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 8/8/2024 SGSOV Approved JEFFREY MEAD
Smoke Detectors 8/8/2024 Not Ready for Inspection JEFFREY MEAD
Verify Sprinkler Sign Off 8/8/2024 Approved JEFFREY MEAD
BUILDING-Rough-Frame 10/2/2024 Corrections Issued JEFFREY MEAD
Final 10/2/2024 Not Ready for Inspection JEFFREY MEAD
Green Building Final 10/2/2024 Approved JEFFREY MEAD
Service/Power Release 10/2/2024 Not Ready for Inspection JEFFREY MEAD
Smoke Detectors 10/2/2024 Approved JEFFREY MEAD
BUILDING-Rough-Frame 10/29/2024 Not Ready for Inspection ENRIQUE MIRELES
Final 10/29/2024 Corrections Issued ENRIQUE MIRELES
PLUMBING-Final 10/29/2024 Not Ready for Inspection ENRIQUE MIRELES
Service/Power Release 10/29/2024 Not Ready for Inspection ENRIQUE MIRELES
BUILDING-Rough-Frame 11/25/2024 Approved JEFFREY MEAD
Final 11/25/2024 OK to Issue CofO JEFFREY MEAD
Service/Power Release 11/25/2024 Approved JEFFREY MEAD
Special/Order Compliance 5/7/2025 Corrections Issued RAUL BARAJAS
Special/Order Compliance 11/17/2025 Partial Inspection ALEX COLIN
Special/Order Compliance 11/25/2025 Conditional Approval JEFFREY MEAD
Special/Order Compliance 12/18/2025 Approved JEFFREY MEAD