637 N KINGSLEY DR 90004

Certificate Information: 637 N KINGSLEY DR 90004

Application / Permit
21010-10000-05560
Plan Check / Job No.
B21LA19976
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 3-STORY DUPLEX WITH ATTACHED 2-CAR GARAGE AND ACCESSORY DWELLING UNIT PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 3/9/2022
Issuing Office
Current Status
CofO Corrected on 1/9/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2021 APPLICANT
Assigned to Plan Check Engineer 11/9/2021 DANIEL YIP
Corrections Issued 11/15/2021 DANIEL YIP
Quality Review Completed 11/23/2021 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 1/13/2022 APPLICANT
Applicant returned to address corrections 2/25/2022 DANIEL YIP
Plan Check Approved 3/1/2022 DANIEL YIP
Issued 3/9/2022 APPLICANT
CofO in Progress 8/9/2024 JEFFREY MEAD
CofO in Progress 11/6/2024 ENRIQUE MIRELES
CofO Issued-Status Void 11/10/2024 DEROLD HAUFF
Permit Finaled-Status Void 11/10/2024 DEROLD HAUFF
Re-Activate Permit 5/7/2025 DEROLD HAUFF
No Progress 10/11/2025 DEROLD HAUFF
CofO in Progress 10/11/2025 DEROLD HAUFF
Permit Finaled 1/9/2026 DEROLD HAUFF
CofO Corrected 1/9/2026 DEROLD HAUFF
Permit Finaled 1/9/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/22/2021 JEANIE LAM
Eng Process Fee Ord 176,300 Cleared 1/11/2022 JEANIE LAM
Sewer availability Cleared 1/11/2022 JEANIE LAM
Low Impact Development Cleared 1/13/2022 JONATAN VELASQUEZ
Frnt yard landscape/Water mgmt Cleared 1/25/2022 RICHARD REASER
Highway dedication Cleared 2/11/2022 JEANIE LAM
Hydrant and Access approval Cleared 2/11/2022 KURT CORRAL
Roof/Waste drainage to street Cleared 2/16/2022 JEANIE LAM

Contact Information

Contractor Rios William A; Lic. No.: 866335-B P O BOX 1061      DOWNEY, CA 90240

Inspector Information

JEFFREY MEAD, (213) 202-3240 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Service/Power Release 3/11/2022 Not Ready for Inspection JOSEPH MCGARRY
Sewer 3/11/2022 Not Ready for Inspection JOSEPH MCGARRY
PLUMBING-Rough 4/29/2022 Approved SHAVONNE ESPINOZA
Deputy Reinf. Concrete 5/12/2022 Corrections Issued SHAVONNE ESPINOZA
Footing/Foundation/Slab 5/17/2022 Approved SHAVONNE ESPINOZA
Floor/Roof Diaphrgm/Shear Wall 6/11/2022 Partial Approval ADAM ESCOTO
Floor/Roof Diaphrgm/Shear Wall 7/1/2022 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 8/2/2022 Approved JEFFREY MEAD
Floor/Roof Diaphrgm/Shear Wall 8/15/2022 Approved JEFFREY MEAD
ELECTRICAL-Rough 11/2/2022 Partial Approval JEFFREY MEAD
HVAC-Rough 11/2/2022 Partial Approval JEFFREY MEAD
PLUMBING-Rough 11/2/2022 Approved JEFFREY MEAD
Wood Frame 11/9/2022 Partial Inspection JULIAN AMAYA
Wood Frame 11/23/2022 Partial Approval JEFFREY MEAD
Insulation 12/8/2022 Approved JEFFREY MEAD
Interior/Exterior Lathing 12/8/2022 Approved JEFFREY MEAD
Drywall Nailing 12/19/2022 Approved JEFFREY MEAD
Green Building Rough 12/19/2022 Approved JEFFREY MEAD
BUILDING-Rough-Frame 7/1/2024 Approved JEFFREY MEAD
Final 7/1/2024 Corrections Issued JEFFREY MEAD
Green Building Final 7/1/2024 Approved JEFFREY MEAD
SGSOV-Seismic Gas S/O Valve 7/1/2024 SGSOV Approved JEFFREY MEAD
Service/Power Release 7/1/2024 Not Ready for Inspection JEFFREY MEAD
Smoke Detectors 7/1/2024 Approved JEFFREY MEAD
Verify Sprinkler Sign Off 7/1/2024 Approved JEFFREY MEAD
Final 8/8/2024 OK to Issue CofO JEFFREY MEAD
Service/Power Release 8/8/2024 Approved JEFFREY MEAD
ELECTRICAL-Final 8/12/2024 Partial Inspection LUIS CASTRO
Special/Order Compliance 8/12/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Final 10/29/2024 OK to Issue CofO ENRIQUE MIRELES
Service/Power Release 11/7/2024 Approved ENRIQUE MIRELES
Special/Order Compliance 5/7/2025 Corrections Issued RAUL BARAJAS
Special/Order Compliance 12/15/2025 Partial Inspection JEFFREY MEAD
Special/Order Compliance 12/15/2025 Partial Inspection RAUL BARAJAS
Special/Order Compliance 12/18/2025 Approved JEFFREY MEAD