4547 1/2 E HUNTINGTON DR NORT 90032

Certificate Information: 4547 1/2 E HUNTINGTON DR NORT 90032

Application / Permit
21010-10000-05551
Plan Check / Job No.
B21LA19946
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT EXISTING GARAGE TO A DETACHED ACCESSORY DWELLING UNIT PER STATE LAW (1-STORY)
Permit Issued
Issued on 10/30/2023
Issuing Office
Current Status
CofO Issued on 12/12/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/4/2021 APPLICANT
Assigned to Plan Check Engineer 11/8/2021 CARLOS MONTES
Corrections Issued 11/8/2021 CARLOS MONTES
Applicant returned to address corrections 12/17/2021 CARLOS MONTES
Applicant returned to address corrections 2/3/2022 CARLOS MONTES
Applicant returned to address corrections 10/19/2023 CARLOS MONTES
Plan Check Approved 10/24/2023 CARLOS MONTES
Issued 10/30/2023 APPLICANT
CofO in Progress 12/11/2025 LILIANA PORTILLO
Permit Finaled 12/12/2025 DEROLD HAUFF
CofO Issued 12/12/2025 DEROLD HAUFF
Permit Finaled 12/12/2025 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 2/28/2022 LAURINDA MEADE
Address approval Cleared 7/15/2023 MSTAFA AL-MSARI
BHO/Hillside ordinance Cleared 7/15/2023 MSTAFA AL-MSARI
BHO/Hillside ordinance Cleared 7/15/2023 MSTAFA AL-MSARI
BHO/Hillside ordinance Cleared 7/15/2023 MSTAFA AL-MSARI
BHO/Hillside ordinance Cleared 7/15/2023 MSTAFA AL-MSARI
BHO/Hillside ordinance Cleared 7/15/2023 MSTAFA AL-MSARI
Highway dedication Cleared 7/15/2023 MSTAFA AL-MSARI
Eng Process Fee Ord 176,300 Cleared 9/27/2023 MSTAFA AL-MSARI
Sewer availability Cleared 9/27/2023 MSTAFA AL-MSARI
Grading Pre-Inspection Cleared 10/17/2023 ALEXANDER HELFER
Tenant Habitability Plan Cleared 10/18/2023 RICARDO BOHORQUEZ

Contact Information

Contractor Owner-Builder       ,

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 4/16/2024 Corrections Issued LILIANA PORTILLO
Deputy Drilled-In Anchors 8/28/2024 No Access for Inspection LILIANA PORTILLO
Deputy Drilled-In Anchors 8/29/2024 Conditional Approval FREDDIE RIVERA
Footing/Foundation/Slab 3/6/2025 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/18/2025 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/20/2025 Corrections Issued LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 4/23/2025 Approved NICHOLAS LOPEZ
Underground Mechanical 4/23/2025 Corrections Issued NICHOLAS LOPEZ
Rough-Elec/Plmb/HVAC 4/30/2025 Corrections Issued LILIANA PORTILLO
BUILDING-Rough-Frame 5/7/2025 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Rough 5/7/2025 Approved LILIANA PORTILLO
HVAC-Rough 5/7/2025 Approved LILIANA PORTILLO
PLUMBING-Rough 5/7/2025 Approved LILIANA PORTILLO
Insulation 5/9/2025 Partial Approval REGINA MENDEZ
Interior/Exterior Lathing 5/9/2025 Approved REGINA MENDEZ
Drywall Nailing 5/15/2025 Partial Approval REGINA MENDEZ
ELECTRICAL-Final 9/9/2025 Not Ready for Inspection LILIANA PORTILLO
Final 9/9/2025 Corrections Issued LILIANA PORTILLO
HVAC-Final 9/9/2025 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Final 9/9/2025 Not Ready for Inspection LILIANA PORTILLO
ELECTRICAL-Final 9/18/2025 Approved LILIANA PORTILLO
Final 9/18/2025 Not Ready for Inspection LILIANA PORTILLO
HVAC-Final 9/18/2025 Approved LILIANA PORTILLO
PLUMBING-Final 9/18/2025 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 12/10/2025 Approved LILIANA PORTILLO
ELECTRICAL-Final 12/10/2025 Approved LILIANA PORTILLO
Final 12/10/2025 OK to Issue CofO LILIANA PORTILLO
Green Building Final 12/10/2025 Approved LILIANA PORTILLO
Green Building Rough 12/10/2025 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 12/10/2025 SGSOV No Gas LILIANA PORTILLO
Service/Power Release 12/10/2025 Approved LILIANA PORTILLO
Smoke Detectors 12/10/2025 Approved LILIANA PORTILLO