4453 1/2 N COLLIS AVE 90032
Certificate Information: 4453 1/2 N COLLIS AVE 90032
- Application / Permit
- 21010-10000-05550
- Plan Check / Job No.
- B21LA19945
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY DETACHED ACCESSORY DWELLING UNIT INCLUDING MECHANICAL, SOLAR POWER, WALLS AND OPENINGS, ROOF, REWORK OF EXISTING PLUMBING AND ELECTRICAL
- Permit Issued
- Issued on 9/26/2022
- Issuing Office
- Current Status
- CofO Issued on 4/10/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/2/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/23/2021 | JOE VO |
| Corrections Issued | 11/30/2021 | JOE VO |
| Quality Review Completed | 12/5/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 4/9/2022 | JOE VO |
| Plan Check Approved | 9/26/2022 | JOE VO |
| Issued | 9/26/2022 | APPLICANT |
| CofO in Progress | 4/3/2024 | BRENDAN MORELLI |
| Permit Finaled | 4/10/2024 | DEROLD HAUFF |
| CofO Issued | 4/10/2024 | DEROLD HAUFF |
| Permit Finaled | 4/10/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 3/22/2022 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 3/22/2022 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 3/22/2022 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 3/22/2022 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 3/22/2022 | TREVOR QUAN |
| BHO/Hillside ordinance | Cleared | 3/22/2022 | TREVOR QUAN |
| Street Frontage | Cleared | 3/22/2022 | TREVOR QUAN |
| Street width determination | Cleared | 3/22/2022 | TREVOR QUAN |
| Eng Process Fee Ord 176,300 | Cleared | 3/24/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 3/24/2022 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 4/29/2022 | MICHAEL GILLISSIE |
| "D" conditions | Cleared | 7/20/2022 | DANIEL CORONADO |
| Low Impact Development | Cleared | 8/5/2022 | ROGELIO CORTES |
| "Q" conditions | Cleared | 8/12/2022 | DANIEL CORONADO |
| Grading Pre-Inspection | Cleared | 9/13/2022 | JOE VO |
| Roof/Waste drainage to street | Cleared | 9/14/2022 | WALLIE JONG |
Contact Information
| Architect | Tan,, Karmen; Lic. No.: C37719 | 15735 CAMINITO ATICO SAN DIEGO, CA 92128 |
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Steve; Lic. No.: C88484 | 7003 VINING STREET CHINO, CA 91710 |
Inspector Information
| No Data Available. |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 1/27/2023 | Partial Approval | AMY COLIN |
| PLUMBING-Rough | 2/3/2023 | Partial Approval | AMY COLIN |
| Underground Mechanical | 2/3/2023 | Partial Approval | AMY COLIN |
| Footing/Foundation/Slab | 2/8/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 2/14/2023 | Approved | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 3/9/2023 | Approved | AMY COLIN |
| Rough-Elec/Plmb/HVAC | 3/28/2023 | Corrections Issued | OSVALDO PARAMO |
| Sewer | 3/28/2023 | Approved | OSVALDO PARAMO |
| Wood Frame | 3/28/2023 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 4/10/2023 | Approved | AMY COLIN |
| ELECTRICAL-Rough | 4/10/2023 | Approved | AMY COLIN |
| Floor/Roof Diaphrgm/Shear Wall | 4/10/2023 | Approved | AMY COLIN |
| HVAC-Rough | 4/10/2023 | Approved | AMY COLIN |
| PLUMBING-Rough | 4/10/2023 | Approved | AMY COLIN |
| Verify Sprinkler Sign Off | 4/10/2023 | Approved | AMY COLIN |
| Insulation | 5/3/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 5/3/2023 | Partial Approval | AMY COLIN |
| Drywall Nailing | 5/12/2023 | Approved | AMY COLIN |
| Interior/Exterior Lathing | 6/14/2023 | Approved | AMY COLIN |
| ELECTRICAL-Final | 8/16/2023 | Corrections Issued | AMY COLIN |
| HVAC-Final | 8/16/2023 | Corrections Issued | AMY COLIN |
| PLUMBING-Final | 8/16/2023 | Approved | AMY COLIN |
| HVAC-Final | 9/11/2023 | Approved | AMY COLIN |
| ELECTRICAL-Final | 9/12/2023 | Approved | AMY COLIN |
| HVAC-Final | 9/12/2023 | Approved | AMY COLIN |
| Final | 10/24/2023 | Corrections Issued | AMY COLIN |
| SGSOV-Seismic Gas S/O Valve | 10/24/2023 | SGSOV Approved | AMY COLIN |
| Service/Power Release | 10/24/2023 | Approved | AMY COLIN |
| Smoke Detectors | 10/24/2023 | Approved | AMY COLIN |
| Final | 3/4/2024 | OK to Issue CofO | BRENDAN MORELLI |