1856 S CRESCENT HEIGHTS BLVD 90035

Certificate Information: 1856 S CRESCENT HEIGHTS BLVD 90035

Application / Permit
21010-10000-05549
Plan Check / Job No.
B21LA19944
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
CONVERT DETACHED GARAGE TO DETACHED ADU PER STATE LAW (1-STORY)
Permit Issued
Issued on 1/12/2022
Issuing Office
Current Status
CofO Issued on 9/16/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/25/2021 APPLICANT
Assigned to Plan Check Engineer 10/29/2021 CARLOS MONTES
Corrections Issued 10/29/2021 CARLOS MONTES
Applicant returned to address corrections 12/14/2021 CARLOS MONTES
Plan Check Approved 1/5/2022 CARLOS MONTES
Issued 1/12/2022 APPLICANT
CofO in Progress 9/9/2022 JOSE AVILA
Permit Finaled 9/16/2022 DEROLD HAUFF
CofO Issued 9/16/2022 DEROLD HAUFF
Permit Finaled 9/16/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/8/2021 AMAAN MALIK
Sewer availability Cleared 11/8/2021 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 12/22/2021 AMAAN MALIK
Construction near power lines Cleared 1/3/2022 RIDWAN HARDY

Contact Information

Contractor S & S Construction And Remodeling Inc; Lic. No.: 989424-B 7650 TOPANGA CANYON BLVD #3      CANOGA PARK, CA 91304
Engineer Melchor,, Oscar Elias; Lic. No.: C76828 21243 VENTURA BLVD SUITE 119      WOODLAND HILLS, CA 91364
Engineer Melchor,, Oscar Elias; Lic. No.: NA76828       ,

Inspector Information

DAVID WILLIAMS, (213) 202-3126 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 2/17/2022 Corrections Issued JOSE AVILA
Sewer 2/17/2022 Approved JOSE AVILA
Excavation/Setback/Form/Re-Bar 2/25/2022 Not Ready for Inspection JOSE AVILA
PLUMBING-Rough 2/25/2022 Partial Approval JOSE AVILA
Footing/Foundation/Slab 3/4/2022 Approved JOSE AVILA
BUILDING-Rough-Frame 4/18/2022 Not Ready for Inspection JOSE AVILA
ELECTRICAL-Rough 4/18/2022 Approved JOSE AVILA
Green Building Rough 4/18/2022 Approved JOSE AVILA
HVAC-Rough 4/18/2022 Approved JOSE AVILA
PLUMBING-Rough 4/18/2022 Corrections Issued JOSE AVILA
ELECTRICAL-Rough 4/28/2022 Approved JOSE AVILA
PLUMBING-Rough 4/28/2022 Approved JOSE AVILA
Insulation 5/2/2022 Corrections Issued SHAVONNE ESPINOZA
BUILDING-Rough-Frame 5/6/2022 Approved JOSE AVILA
Interior/Exterior Lathing 5/6/2022 Approved JOSE AVILA
Drywall Nailing 5/11/2022 Approved JOSE AVILA
Special/Order Compliance 5/25/2022 Approved JOSE AVILA
Interior/Exterior Lathing 6/7/2022 Approved JOSE AVILA
Final 7/15/2022 Corrections Issued JOSE AVILA
Green Building Final 7/15/2022 Corrections Issued JOSE AVILA
SGSOV-Seismic Gas S/O Valve 7/15/2022 SGSOV Approved JOSE AVILA
Smoke Detectors 7/15/2022 Approved JOSE AVILA
Final 7/21/2022 Corrections Issued JOSE AVILA
Green Building Final 7/21/2022 Approved JOSE AVILA
Final 9/8/2022 OK to Issue CofO JOSE AVILA