4995-4997 W 23RD ST 90016
Certificate Information: 4995-4997 W 23RD ST 90016
- Application / Permit
- 21010-10000-05539
- Plan Check / Job No.
- B21LA19918
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- NEW 3-STORY DUPLEX AND ATTACHED 4-CAR GARAGE AT REAR OF LOT.
- Permit Issued
- Issued on 3/28/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 4/16/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2021 | VIVIAN LAO |
| Corrections Issued | 11/17/2021 | VIVIAN LAO |
| Quality Review Completed | 11/29/2021 | KEN GILL |
| Building Plans Picked Up | 12/2/2021 | APPLICANT |
| Applicant returned to address corrections | 3/16/2023 | VIVIAN LAO |
| Plan Check Approved | 3/22/2023 | VIVIAN LAO |
| Issued | 3/28/2023 | APPLICANT |
| CofO in Progress | 4/16/2024 | JUSTIN HAWLEY |
| Permit Finaled | 4/16/2024 | DEROLD HAUFF |
| CofO Issued | 4/16/2024 | DEROLD HAUFF |
| Permit Finaled | 4/16/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/8/2021 | CINDY QI |
| Highway dedication | Cleared | 12/8/2021 | CINDY QI |
| Permit | Cleared | 12/8/2021 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2021 | CINDY QI |
| Sewer availability | Cleared | 12/10/2021 | CINDY QI |
| Frnt yard landscape/Water mgmt | Cleared | 12/21/2021 | RICHARD REASER |
| Hydrant and Access approval | Cleared | 3/5/2022 | GILBERT URREA |
| Low Impact Development | Cleared | 2/13/2023 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 2/14/2023 | CINDY QI |
Contact Information
| Contractor | Riviera Building & Design Inc; Lic. No.: 878203-B | 31103 RANCHO VIEJO RD SUITE D2039 SAN JUAN CAPISTRANO, CA 92675 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| JUSTIN HAWLEY, (213) 202-3432 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/25/2023 | Corrections Issued | CALEB MEISTER |
| PLUMBING-Rough | 6/1/2023 | Partial Approval | CALEB MEISTER |
| Footing/Foundation/Slab | 6/12/2023 | Approved | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 7/10/2023 | Approved | RUBEN SALAS |
| Floor/Roof Diaphrgm/Shear Wall | 8/3/2023 | Partial Approval | CALEB MEISTER |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2023 | Partial Approval | STUART CHAPMAN |
| HVAC-Rough | 10/4/2023 | Approved | STUART CHAPMAN |
| Deputy Wood Construction | 10/10/2023 | Conditional Approval | FREDDIE RIVERA |
| ELECTRICAL-Rough | 10/11/2023 | Approved | CALEB MEISTER |
| BUILDING-Rough-Frame | 10/25/2023 | Not Ready for Inspection | CALEB MEISTER |
| Gas Test | 10/25/2023 | Approved | CALEB MEISTER |
| Green Building Rough | 10/25/2023 | Not Ready for Inspection | CALEB MEISTER |
| MERV13>=Rough | 10/25/2023 | Not Ready for Inspection | CALEB MEISTER |
| PLUMBING-Rough | 10/25/2023 | Approved | CALEB MEISTER |
| Verify Sprinkler Sign Off | 10/25/2023 | Not Ready for Inspection | CALEB MEISTER |
| Insulation | 11/6/2023 | Not Ready for Inspection | CALEB MEISTER |
| Insulation | 11/8/2023 | Corrections Issued | FREDDIE RIVERA |
| Insulation | 11/14/2023 | Approved | STUART CHAPMAN |
| Interior/Exterior Lathing | 11/14/2023 | Approved | STUART CHAPMAN |
| BUILDING-Rough-Frame | 11/16/2023 | Approved | CALEB MEISTER |
| Green Building Rough | 11/16/2023 | Approved | CALEB MEISTER |
| MERV13>=Rough | 11/16/2023 | Approved | CALEB MEISTER |
| Verify Sprinkler Sign Off | 11/16/2023 | Approved | CALEB MEISTER |
| Drywall Nailing | 11/29/2023 | Approved | JUSTIN HAWLEY |
| Interior/Exterior Lathing | 11/29/2023 | Approved | JUSTIN HAWLEY |
| Gas Test | 1/10/2024 | Approved | BRENDAN MORELLI |
| Sewer | 1/10/2024 | Approved | BRENDAN MORELLI |
| Underground Mechanical | 1/10/2024 | Partial Approval | BRENDAN MORELLI |
| ELECTRICAL-Final | 3/26/2024 | Approved | JUSTIN HAWLEY |
| Final | 3/26/2024 | Corrections Issued | JUSTIN HAWLEY |
| Green Building Final | 3/26/2024 | Approved | JUSTIN HAWLEY |
| HVAC-Final | 3/26/2024 | Approved | JUSTIN HAWLEY |
| PLUMBING-Final | 3/26/2024 | Approved | JUSTIN HAWLEY |
| SGSOV-Seismic Gas S/O Valve | 3/26/2024 | SGSOV Approved | JUSTIN HAWLEY |
| Service/Power Release | 3/26/2024 | Not Ready for Inspection | JUSTIN HAWLEY |
| Smoke Detectors | 3/26/2024 | Approved | JUSTIN HAWLEY |
| Final | 4/16/2024 | OK to Issue CofO | JUSTIN HAWLEY |
| MERV13>=Final | 4/16/2024 | Approved | JUSTIN HAWLEY |
| Service/Power Release | 4/16/2024 | Approved | JUSTIN HAWLEY |