3236 W 59TH PL 90043

Certificate Information: 3236 W 59TH PL 90043

Application / Permit
21010-10000-05505
Plan Check / Job No.
B21LA19789
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. NEW DETACHED ACCESSORY DWELLING UNIT AT REAR PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
Permit Issued
Issued on 2/4/2025
Issuing Office
Current Status
Issued on 2/4/2025
Certificate of Occupancy
Pending More Information

Permit Application Status History

Submitted 11/9/2021 APPLICANT
Assigned to Plan Check Engineer 11/28/2021 KEVIN MORALES
Corrections Issued 11/29/2021 KEVIN MORALES
Quality Review Completed 12/1/2021 EUGENE BARBEAU
Applicant returned to address corrections 3/28/2024 KEVIN MORALES
Applicant returned to address corrections 1/14/2025 KEVIN MORALES
Plan Check Approved 1/27/2025 KEVIN MORALES
Issued 2/4/2025 APPLICANT

Permit Application Clearance Information

Address approval Cleared 3/31/2022 CINDY QI
Historic Resource Verification Cleared 4/8/2022 GRACIELA ACOSTA
Redevelopment Project Area Cleared 4/8/2022 GRACIELA ACOSTA
Eng Process Fee Ord 176,300 Cleared 4/28/2022 CINDY QI
Sewer availability Cleared 4/28/2022 CINDY QI
Low Impact Development Cleared 2/5/2024 LUIS CRUZ
Roof/Waste drainage to street Cleared 3/26/2024 TREVOR QUAN

Contact Information

Contractor Owner-Builder       ,

Inspector Information

SALVADOR MARTINEZ, (213) 202-3479 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 8/13/2025 Approved WAYNE REGESTER
Excavation/Setback/Form/Re-Bar 8/18/2025 Approved WAYNE REGESTER
BUILDING-Rough-Frame 9/26/2025 Not Ready for Inspection SALVADOR MARTINEZ
ELECTRICAL-Rough 9/26/2025 Not Ready for Inspection SALVADOR MARTINEZ
HVAC-Rough 9/26/2025 Corrections Issued SALVADOR MARTINEZ
PLUMBING-Rough 9/26/2025 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 9/30/2025 No Access for Inspection SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 10/3/2025 Partial Approval BARRY HACHE
Floor/Roof Diaphrgm/Shear Wall 10/6/2025 Corrections Issued SALVADOR MARTINEZ
Floor/Roof Diaphrgm/Shear Wall 10/24/2025 Approved SALVADOR MARTINEZ
PLUMBING-Rough 10/24/2025 Approved SALVADOR MARTINEZ
Sewer 12/11/2025 Corrections Issued SALVADOR MARTINEZ
Underground Mechanical 12/11/2025 Corrections Issued SALVADOR MARTINEZ
Underground Mechanical 12/15/2025 Partial Approval SALVADOR MARTINEZ
Interior/Exterior Lathing 12/17/2025 Approved MICHAEL LEWIS
Sewer 12/17/2025 Approved MICHAEL LEWIS
ELECTRICAL-Rough 12/26/2025 Corrections Issued SABAS ALONSO
HVAC-Rough 12/26/2025 Approved SABAS ALONSO
ELECTRICAL-Rough 12/29/2025 Approved SALVADOR MARTINEZ
BUILDING-Rough-Frame 1/2/2026 Approved WILLIAM SIERRA
Green Building Rough 1/2/2026 Approved WILLIAM SIERRA
Verify Sprinkler Sign Off 1/2/2026 Approved WILLIAM SIERRA
Wood Frame 1/2/2026 Approved WILLIAM SIERRA
Insulation 1/16/2026 Approved SCOTT FINNILA
Drywall Nailing 1/22/2026 Approved GEM DE OCAMPO
Final 5/29/2026 Not Ready for Inspection SALVADOR MARTINEZ
Footing/Foundation/Slab 5/29/2026 Not Ready for Inspection SALVADOR MARTINEZ
Green Building Final 5/29/2026 Not Ready for Inspection SALVADOR MARTINEZ
SGSOV-Seismic Gas S/O Valve 5/29/2026 SGSOV Not Ready SALVADOR MARTINEZ
Service/Power Release 5/29/2026 Not Ready for Inspection SALVADOR MARTINEZ
Smoke Detectors 5/29/2026 Not Ready for Inspection SALVADOR MARTINEZ