3236 W 59TH PL 90043
Certificate Information: 3236 W 59TH PL 90043
- Application / Permit
- 21010-10000-05505
- Plan Check / Job No.
- B21LA19789
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ePLAN. NEW DETACHED ACCESSORY DWELLING UNIT AT REAR PER CA Govt. Code 65852.2(e)(1)(B) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g)
- Permit Issued
- Issued on 2/4/2025
- Issuing Office
- Current Status
- Issued on 2/4/2025
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 11/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/28/2021 | KEVIN MORALES |
| Corrections Issued | 11/29/2021 | KEVIN MORALES |
| Quality Review Completed | 12/1/2021 | EUGENE BARBEAU |
| Applicant returned to address corrections | 3/28/2024 | KEVIN MORALES |
| Applicant returned to address corrections | 1/14/2025 | KEVIN MORALES |
| Plan Check Approved | 1/27/2025 | KEVIN MORALES |
| Issued | 2/4/2025 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/31/2022 | CINDY QI |
| Historic Resource Verification | Cleared | 4/8/2022 | GRACIELA ACOSTA |
| Redevelopment Project Area | Cleared | 4/8/2022 | GRACIELA ACOSTA |
| Eng Process Fee Ord 176,300 | Cleared | 4/28/2022 | CINDY QI |
| Sewer availability | Cleared | 4/28/2022 | CINDY QI |
| Low Impact Development | Cleared | 2/5/2024 | LUIS CRUZ |
| Roof/Waste drainage to street | Cleared | 3/26/2024 | TREVOR QUAN |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| SALVADOR MARTINEZ, (213) 202-3479 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 8/13/2025 | Approved | WAYNE REGESTER |
| Excavation/Setback/Form/Re-Bar | 8/18/2025 | Approved | WAYNE REGESTER |
| BUILDING-Rough-Frame | 9/26/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| ELECTRICAL-Rough | 9/26/2025 | Not Ready for Inspection | SALVADOR MARTINEZ |
| HVAC-Rough | 9/26/2025 | Corrections Issued | SALVADOR MARTINEZ |
| PLUMBING-Rough | 9/26/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 9/30/2025 | No Access for Inspection | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/3/2025 | Partial Approval | BARRY HACHE |
| Floor/Roof Diaphrgm/Shear Wall | 10/6/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Floor/Roof Diaphrgm/Shear Wall | 10/24/2025 | Approved | SALVADOR MARTINEZ |
| PLUMBING-Rough | 10/24/2025 | Approved | SALVADOR MARTINEZ |
| Sewer | 12/11/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 12/11/2025 | Corrections Issued | SALVADOR MARTINEZ |
| Underground Mechanical | 12/15/2025 | Partial Approval | SALVADOR MARTINEZ |
| Interior/Exterior Lathing | 12/17/2025 | Approved | MICHAEL LEWIS |
| Sewer | 12/17/2025 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 12/26/2025 | Corrections Issued | SABAS ALONSO |
| HVAC-Rough | 12/26/2025 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 12/29/2025 | Approved | SALVADOR MARTINEZ |
| BUILDING-Rough-Frame | 1/2/2026 | Approved | WILLIAM SIERRA |
| Green Building Rough | 1/2/2026 | Approved | WILLIAM SIERRA |
| Verify Sprinkler Sign Off | 1/2/2026 | Approved | WILLIAM SIERRA |
| Wood Frame | 1/2/2026 | Approved | WILLIAM SIERRA |
| Insulation | 1/16/2026 | Approved | SCOTT FINNILA |
| Drywall Nailing | 1/22/2026 | Approved | GEM DE OCAMPO |
| Final | 5/29/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Footing/Foundation/Slab | 5/29/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Green Building Final | 5/29/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| SGSOV-Seismic Gas S/O Valve | 5/29/2026 | SGSOV Not Ready | SALVADOR MARTINEZ |
| Service/Power Release | 5/29/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |
| Smoke Detectors | 5/29/2026 | Not Ready for Inspection | SALVADOR MARTINEZ |