3802 S DUBLIN AVE 90008
Certificate Information: 3802 S DUBLIN AVE 90008
- Application / Permit
- 21010-10000-05493
- Plan Check / Job No.
- B21LA19767
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW 1-STORY ADU PER LAMC 12.22 A.33. The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the finaling of the permit.
- Permit Issued
- Issued on 4/28/2023
- Issuing Office
- Metro
- Current Status
- Issued on 4/28/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | SAMUEL GONZALEZ |
| Corrections Issued | 11/6/2021 | SAMUEL GONZALEZ |
| Building Plans Picked Up | 11/10/2021 | APPLICANT |
| Applicant returned to address corrections | 6/22/2022 | STANLEY RAAP |
| Plan Check Approved | 3/31/2023 | SAMUEL GONZALEZ |
| Issued | 4/28/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 3/9/2022 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 5/13/2022 | STEVE MELGAR |
| Sewer availability | Cleared | 5/13/2022 | STEVE MELGAR |
| Construction near power lines | Cleared | 11/22/2022 | NADER ISKANDER |
| Roof/Waste drainage to street | Cleared | 3/2/2023 | CELINA MORENO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| LUIS CASTRO, (213) 202-3436 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 5/16/2023 | Corrections Issued | ANTHONY EGSON |
| Underground Mechanical | 5/30/2023 | Approved | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 6/16/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 6/22/2023 | Corrections Issued | ANTHONY EGSON |
| Excavation/Setback/Form/Re-Bar | 6/26/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Footing/Foundation/Slab | 8/11/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/3/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/3/2023 | Corrections Issued | ANTHONY EGSON |
| Green Building Rough | 10/3/2023 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 10/3/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 10/3/2023 | Corrections Issued | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 10/3/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/16/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/16/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/16/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 10/16/2023 | Not Ready for Inspection | ANTHONY EGSON |
| HVAC-Rough | 10/16/2023 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Rough | 10/16/2023 | Corrections Issued | ANTHONY EGSON |
| ELECTRICAL-Rough | 10/18/2023 | Approved | ANTHONY EGSON |
| HVAC-Rough | 10/18/2023 | Approved | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2023 | No Access for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/23/2023 | Corrections Issued | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 10/25/2023 | Approved | ANTHONY EGSON |
| BUILDING-Rough-Frame | 10/30/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Green Building Rough | 10/30/2023 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 11/3/2023 | Approved | ANTHONY EGSON |
| Green Building Rough | 11/3/2023 | Approved | ANTHONY EGSON |
| Interior/Exterior Lathing | 11/13/2023 | Corrections Issued | ANTHONY EGSON |
| Insulation | 11/15/2023 | Approved | ANTHONY EGSON |
| Shower Pan | 11/15/2023 | Approved | ANTHONY EGSON |
| Drywall Nailing | 11/20/2023 | Approved | ANTHONY EGSON |
| Sewer | 11/20/2023 | Corrections Issued | ANTHONY EGSON |
| Interior/Exterior Lathing | 11/27/2023 | Approved | ANTHONY EGSON |
| Sewer | 11/27/2023 | Partial Approval | ANTHONY EGSON |
| Underground Mechanical | 12/11/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Underground Mechanical | 3/6/2024 | Partial Approval | ANTHONY EGSON |
| Underground Mechanical | 3/13/2024 | Approved | ANTHONY EGSON |
| Pre-Inspection | 1/2/2025 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Final | 1/7/2025 | Corrections Issued | LUIS CASTRO |
| Final | 1/7/2025 | Corrections Issued | LUIS CASTRO |
| HVAC-Final | 1/7/2025 | Corrections Issued | LUIS CASTRO |
| PLUMBING-Final | 1/7/2025 | Corrections Issued | LUIS CASTRO |
| Service/Power Release | 1/7/2025 | Corrections Issued | LUIS CASTRO |
| Final | 2/14/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 2/14/2025 | Partial Approval | LUIS CASTRO |
| HVAC-Final | 2/14/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 2/14/2025 | Approved | LUIS CASTRO |
| SGSOV-Seismic Gas S/O Valve | 2/14/2025 | SGSOV Approved | LUIS CASTRO |
| Service/Power Release | 2/14/2025 | Corrections Issued | LUIS CASTRO |
| Smoke Detectors | 2/14/2025 | Approved | LUIS CASTRO |
| ELECTRICAL-Final | 4/10/2025 | Corrections Issued | LUIS CASTRO |
| Final | 4/10/2025 | Corrections Issued | LUIS CASTRO |
| Green Building Final | 4/10/2025 | Approved | LUIS CASTRO |
| HVAC-Final | 4/10/2025 | Approved | LUIS CASTRO |
| PLUMBING-Final | 4/10/2025 | Approved | LUIS CASTRO |
| Service/Power Release | 4/10/2025 | Corrections Issued | LUIS CASTRO |
| ELECTRICAL-Final | 4/16/2025 | Corrections Issued | LUIS CASTRO |
| Final | 4/16/2025 | Not Ready for Inspection | LUIS CASTRO |
| Service/Power Release | 4/16/2025 | Not Ready for Inspection | LUIS CASTRO |
| ELECTRICAL-Final | 4/24/2025 | Approved | LUIS CASTRO |
| Final | 4/24/2025 | Corrections Issued | LUIS CASTRO |
| Service/Power Release | 4/24/2025 | Approved | LUIS CASTRO |