7628 N WILBUR AVE 91335

Certificate Information: 7628 N WILBUR AVE 91335

Application / Permit
21010-10000-05450
Plan Check / Job No.
B21LA19446
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
PROPOSED 1-STORY ADU WITH ATTACHED LATTICE ROOF PER LAMC 12.22 A.33(c)-(d) AT REAR OF LOT. The LID clearance has been deferred. Approval for LID requirements shall be obtained from LASAN prior to the issuance of the Certificate of Occupancy.
Permit Issued
Issued on 2/25/2022
Issuing Office
Current Status
CofO Issued on 5/29/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/15/2021 APPLICANT
Assigned to Plan Check Engineer 10/22/2021 LAWRENCE QUIRANTE
Corrections Issued 10/23/2021 LAWRENCE QUIRANTE
Applicant returned to address corrections 1/14/2022 ADAM HEGAZI
Plan Check Approved 1/24/2022 ADAM HEGAZI
Issued 2/25/2022 APPLICANT
Building Plans Picked Up 3/1/2022 APPLICANT
CofO in Progress 4/23/2024 JEFFREY BULL
Permit Finaled 5/29/2024 JOHN JANSON
CofO Issued 5/29/2024 JOHN JANSON
Permit Finaled 5/29/2024 JOHN JANSON

Permit Application Clearance Information

Address approval Cleared 12/8/2021 JOSE DUARTE-DIAZ
Sewer availability Cleared 12/13/2021 JOSE DUARTE-DIAZ
Eng Process Fee Ord 176,300 Cleared 12/21/2021 CHRISTINE KEUSHGUERIAN
Roof/Waste drainage to street Cleared 2/25/2022 JOSE DUARTE-DIAZ

Contact Information

Contractor Owner-Builder       ,
Engineer Askarian,, Soroosh; Lic. No.: C83413 22287 MULHOLLAND HWY 163      CALABASAS, CA 91302

Inspector Information

ARUTYUN MADATYAN, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI
JUAN ALVARADO, (818) 774-4307 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 3/21/2023 No Access for Inspection KRISTEN CAUSEY
PLUMBING-Rough 3/24/2023 No Access for Inspection VINCENT HANLEY
PLUMBING-Rough 4/3/2023 Partial Approval JEFFREY BULL
Pre-Inspection 4/10/2023 Approved DAVID SANDOVAL
Underground Mechanical 4/10/2023 Approved MORRIS JACKSON
ELECTRICAL-Rough 5/19/2023 Approved JEFFREY BULL
HVAC-Rough 5/19/2023 Approved JEFFREY BULL
PLUMBING-Rough 5/19/2023 Approved JEFFREY BULL
BUILDING-Rough-Frame 6/14/2023 Not Ready for Inspection JEFFREY BULL
Green Building Rough 6/14/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 6/14/2023 Partial Approval JEFFREY BULL
Floor/Roof Diaphrgm/Shear Wall 7/25/2023 Approved JEFFREY BULL
Interior/Exterior Lathing 7/25/2023 Partial Approval JEFFREY BULL
Insulation 7/28/2023 Approved JEFFREY BULL
Insulation 7/31/2023 Partial Inspection JOHN KIDWELL
Drywall Nailing 8/8/2023 Corrections Issued JUSTIN HAWLEY
BUILDING-Rough-Frame 8/10/2023 Approved JUSTIN HAWLEY
Drywall Nailing 8/10/2023 Approved JUSTIN HAWLEY
Verify Sprinkler Sign Off 8/10/2023 Approved JUSTIN HAWLEY
Shower Pan 8/30/2023 Approved JEFFREY BULL
Underground Mechanical 10/13/2023 Approved JEFFREY BULL
ELECTRICAL-Final 10/24/2023 Corrections Issued JEFFREY BULL
Final 10/24/2023 Corrections Issued JEFFREY BULL
Footing/Foundation/Slab 10/24/2023 Approved JEFFREY BULL
Green Building Final 10/24/2023 Not Ready for Inspection JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 10/24/2023 SGSOV Not Ready JEFFREY BULL
Service/Power Release 10/24/2023 Approved JEFFREY BULL
Smoke Detectors 10/24/2023 Approved JEFFREY BULL
Final 4/11/2024 OK to Issue CofO JEFFREY BULL
Green Building Final 4/11/2024 Approved JEFFREY BULL
SGSOV-Seismic Gas S/O Valve 4/11/2024 SGSOV Approved JEFFREY BULL