4325 S MAIN ST 90037

Certificate Information: 4325 S MAIN ST 90037

Application / Permit
21010-10000-05431
Plan Check / Job No.
B21LA19409
Group
Building
Type
Bldg-New
Sub-Type
Apartment
Primary Use
(5) Apartment
Work Description
NEW 4 STORY TYPE VA 31 UNITS 100% AFFORDABLE HOUSING APARTMENT, TIER 3 TOC BASE INCENTIVE
Permit Issued
Issued on 3/15/2023
Issuing Office
Current Status
CofO Issued on 11/22/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Plan Check Approved 3/15/2023 MANUEL MONTUFAR
Issued 3/15/2023 SUYA LY
Issued 3/15/2023 SHANNON HAAS
TCO Issued (Expire Date: 04-15-2025) 10/17/2024 ERNESTO CORRAL
CofO in Progress 11/21/2024 JAMES POWERS
Permit Finaled 11/22/2024 ERNESTO CORRAL
CofO Issued 11/22/2024 ERNESTO CORRAL
Permit Finaled 11/22/2024 ERNESTO CORRAL

Permit Application Clearance Information

Address approval Cleared 1/14/2022 WALLIE JONG
Community Plan Implem. Overlay Cleared 1/14/2022 WALLIE JONG
Historic Resource Verification Cleared 1/18/2022 MAX LODER
Eng Process Fee Ord 176,300 Cleared 1/26/2022 WALLIE JONG
Miscellaneous Cleared 1/28/2022 MAXFIELD VERMY
Community Plan Implem. Overlay Cleared 2/1/2022 WALTER RAMIREZ
Redevelopment Project Area Cleared 2/4/2022 GRACIELA ACOSTA
Highway dedication Cleared 2/10/2022 WALLIE JONG
Construction near power lines Cleared 2/16/2022 WALTER RAMIREZ
Community Plan Implem. Overlay Cleared 3/3/2022 EILEEN HUNT
Driveway location Cleared 3/3/2022 EILEEN HUNT
Building over 36-ft Cleared 3/7/2022 CALOSHA APPROVED
Trees in Parkway Cleared 3/8/2022 ADALBERTO VERA
Community Plan Implem. Overlay Cleared 3/9/2022 ADALBERTO VERA
Hydrant and Access approval Cleared 3/17/2022 KURT CORRAL
DAS Clearance Cleared 4/19/2022 MANUEL MONTUFAR
Green Code Cleared 6/19/2022 MANUEL MONTUFAR
Fire Marshal Fire Life Safety Cleared 6/22/2022 WILLIAM JOHNS
Low Impact Development Cleared 7/6/2022 SARAH YOUSSEF
Roof/Waste drainage to street Cleared 7/11/2022 JEANIE LAM
Community Plan Implem. Overlay Cleared 10/11/2022 HELEN JADALI
Frnt yard landscape/Water mgmt Cleared 10/28/2022 MAXFIELD VERMY
Opn space landscape/Water mgmt Cleared 11/22/2022 MAXFIELD VERMY
Permit Cleared 3/10/2023 WALLIE JONG
Sewer availability Cleared 3/10/2023 WALLIE JONG
Density Bonus 12.22.A.31 Cleared 3/14/2023 JAMES MCCARTHY
Work Adjacent to Public Way Cleared 3/14/2023 KHOUNG LE

Contact Information

Architect Garcia,, Maria Celina; Lic. No.: C32852 1983 W. 190TH STREET #200      TORRANCE, CA 90504
Contractor Jones Randy; Lic. No.: 473449-B 18823 STATE STREET      CORONA, CA 92881
Engineer Abantao,, Marlo Christoph Macaraeg; Lic. No.: C93225 230 W 47TH ST      LONG BEACH, CA 90805
Engineer Cai,, Luo; Lic. No.: C80352 9428 ETAON AVE M      CHATSWORTH, CA 91311
Engineer Lee,, David Chong; Lic. No.: S5881 124 S GUADALUPE AVE, UNIT B      RANCHO PALOS VERDES, CA 90277
Geologist Tsao,, Tze-Tzong; Lic. No.: EG1783 9428 ETON AVENUE #M      CHATSWORTH, CA 91311
Landscape Architect Gagne,, Paul Elliott; Lic. No.: LA6223 6620 MURIETTA AVE      VAN NUYS, CA 91405

Inspector Information

ALFREDO LOPEZ, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI
JAMES POWERS, (213) 482-0361 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Deputy Reinf. Concrete 6/13/2023 Conditional Approval MICHAEL ROSENBERG
Excavation/Setback/Form/Re-Bar 7/12/2023 Partial Approval ALAN MORELOS
Footing/Foundation/Slab 7/12/2023 Not Ready for Inspection ALAN MORELOS
METHANE-Barrier 7/12/2023 Approved ALAN MORELOS
METHANE-Subgrade 7/12/2023 Approved ALAN MORELOS
Footing/Foundation/Slab 7/25/2023 Not Ready for Inspection JAMES POWERS
Excavation/Setback/Form/Re-Bar 7/26/2023 Partial Approval ALAN MORELOS
Footing/Foundation/Slab 8/9/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 9/8/2023 Partial Approval JAMES POWERS
Deputy Wood Construction 9/21/2023 Conditional Approval LARRY ARNICK
Floor/Roof Diaphrgm/Shear Wall 9/21/2023 Partial Approval LARRY ARNICK
Deputy Wood Construction 10/3/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/4/2023 Partial Approval LARRY ARNICK
Deputy Wood Construction 10/18/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 10/19/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/14/2023 Partial Approval JAMES POWERS
Green Building Rough 11/14/2023 Not Ready for Inspection JAMES POWERS
METHANE-Rough 11/14/2023 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 11/14/2023 Not Ready for Inspection JAMES POWERS
Deputy Wood Construction 11/28/2023 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 11/29/2023 Partial Approval JAMES POWERS
Green Building Rough 12/12/2023 Not Ready for Inspection LARRY ARNICK
METHANE-Rough 12/12/2023 Not Ready for Inspection LARRY ARNICK
Verify Sprinkler Sign Off 12/12/2023 Not Ready for Inspection LARRY ARNICK
Wood Frame 12/12/2023 Partial Approval LARRY ARNICK
Pre-Inspection 12/18/2023 Not Ready for Inspection JAMES POWERS
Drywall Nailing 12/27/2023 Partial Approval JAMES POWERS
Insulation 1/3/2024 Conditional Approval DARRYL ARNOLD
Insulation 1/5/2024 Partial Approval JAMES POWERS
Insulation 1/9/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 1/16/2024 Partial Approval JAMES POWERS
Floor/Roof Diaphrgm/Shear Wall 1/17/2024 Partial Approval JAMES POWERS
Green Building Rough 1/17/2024 Partial Approval JAMES POWERS
METHANE-Rough 1/17/2024 Not Ready for Inspection JAMES POWERS
Verify Sprinkler Sign Off 1/17/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 1/17/2024 Not Ready for Inspection JAMES POWERS
Insulation 1/24/2024 Partial Approval JAMES POWERS
Insulation 1/26/2024 Partial Approval LARRY ARNICK
Interior/Exterior Lathing 1/31/2024 Approved JAMES POWERS
Drywall Nailing 2/6/2024 Partial Approval LARRY ARNICK
Insulation 2/6/2024 Partial Approval LARRY ARNICK
Reinforced Concrete Frame 2/6/2024 Not Ready for Inspection LARRY ARNICK
Drywall Nailing 2/20/2024 Not Ready for Inspection JAMES POWERS
Insulation 2/20/2024 Partial Approval JAMES POWERS
Drywall Nailing 2/26/2024 Partial Approval JAMES POWERS
Insulation 2/26/2024 Partial Approval JAMES POWERS
Drywall Nailing 3/12/2024 Partial Approval JAMES POWERS
Light Gage Steel Frame 3/21/2024 Partial Approval JAMES POWERS
Masonry Wall/Backfill 6/18/2024 Partial Approval JAMES POWERS
Special/Order Compliance 7/1/2024 Partial Approval JAMES POWERS
Final 9/23/2024 Not Ready for Inspection JAMES POWERS
Footing/Foundation/Slab 9/23/2024 Approved JAMES POWERS
Green Building Final 9/23/2024 Approved JAMES POWERS
Green Building Rough 9/23/2024 Approved JAMES POWERS
METHANE-Final 9/23/2024 Approved JAMES POWERS
METHANE-Rough 9/23/2024 Approved JAMES POWERS
SGSOV-Seismic Gas S/O Valve 9/23/2024 SGSOV Approved JAMES POWERS
Smoke Detectors 9/23/2024 Approved JAMES POWERS
Verify Sprinkler Sign Off 9/23/2024 Not Ready for Inspection JAMES POWERS
Wood Frame 9/23/2024 Partial Approval JAMES POWERS
Deputy Drilled-In Anchors 9/27/2024 Partial Approval JAMES POWERS
Deputy Reinf. Concrete 9/27/2024 Partial Approval JAMES POWERS
Deputy Steel/Welding 9/27/2024 Partial Approval JAMES POWERS
Deputy Wood Construction 9/27/2024 Partial Approval JAMES POWERS
Final 10/17/2024 OK for TCO JAMES POWERS
Verify Sprinkler Sign Off 10/17/2024 Approved JAMES POWERS
Wood Frame 10/17/2024 Approved JAMES POWERS
Final 11/20/2024 OK to Issue CofO JAMES POWERS