4325 S MAIN ST 90037
Certificate Information: 4325 S MAIN ST 90037
- Application / Permit
- 21010-10000-05431
- Plan Check / Job No.
- B21LA19409
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- Apartment
- Primary Use
- (5) Apartment
- Work Description
- NEW 4 STORY TYPE VA 31 UNITS 100% AFFORDABLE HOUSING APARTMENT, TIER 3 TOC BASE INCENTIVE
- Permit Issued
- Issued on 3/15/2023
- Issuing Office
- Current Status
- CofO Issued on 11/22/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Plan Check Approved | 3/15/2023 | MANUEL MONTUFAR |
| Issued | 3/15/2023 | SUYA LY |
| Issued | 3/15/2023 | SHANNON HAAS |
| TCO Issued (Expire Date: 04-15-2025) | 10/17/2024 | ERNESTO CORRAL |
| CofO in Progress | 11/21/2024 | JAMES POWERS |
| Permit Finaled | 11/22/2024 | ERNESTO CORRAL |
| CofO Issued | 11/22/2024 | ERNESTO CORRAL |
| Permit Finaled | 11/22/2024 | ERNESTO CORRAL |
Permit Application Clearance Information
| Address approval | Cleared | 1/14/2022 | WALLIE JONG |
| Community Plan Implem. Overlay | Cleared | 1/14/2022 | WALLIE JONG |
| Historic Resource Verification | Cleared | 1/18/2022 | MAX LODER |
| Eng Process Fee Ord 176,300 | Cleared | 1/26/2022 | WALLIE JONG |
| Miscellaneous | Cleared | 1/28/2022 | MAXFIELD VERMY |
| Community Plan Implem. Overlay | Cleared | 2/1/2022 | WALTER RAMIREZ |
| Redevelopment Project Area | Cleared | 2/4/2022 | GRACIELA ACOSTA |
| Highway dedication | Cleared | 2/10/2022 | WALLIE JONG |
| Construction near power lines | Cleared | 2/16/2022 | WALTER RAMIREZ |
| Community Plan Implem. Overlay | Cleared | 3/3/2022 | EILEEN HUNT |
| Driveway location | Cleared | 3/3/2022 | EILEEN HUNT |
| Building over 36-ft | Cleared | 3/7/2022 | CALOSHA APPROVED |
| Trees in Parkway | Cleared | 3/8/2022 | ADALBERTO VERA |
| Community Plan Implem. Overlay | Cleared | 3/9/2022 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 3/17/2022 | KURT CORRAL |
| DAS Clearance | Cleared | 4/19/2022 | MANUEL MONTUFAR |
| Green Code | Cleared | 6/19/2022 | MANUEL MONTUFAR |
| Fire Marshal Fire Life Safety | Cleared | 6/22/2022 | WILLIAM JOHNS |
| Low Impact Development | Cleared | 7/6/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 7/11/2022 | JEANIE LAM |
| Community Plan Implem. Overlay | Cleared | 10/11/2022 | HELEN JADALI |
| Frnt yard landscape/Water mgmt | Cleared | 10/28/2022 | MAXFIELD VERMY |
| Opn space landscape/Water mgmt | Cleared | 11/22/2022 | MAXFIELD VERMY |
| Permit | Cleared | 3/10/2023 | WALLIE JONG |
| Sewer availability | Cleared | 3/10/2023 | WALLIE JONG |
| Density Bonus 12.22.A.31 | Cleared | 3/14/2023 | JAMES MCCARTHY |
| Work Adjacent to Public Way | Cleared | 3/14/2023 | KHOUNG LE |
Contact Information
| Architect | Garcia,, Maria Celina; Lic. No.: C32852 | 1983 W. 190TH STREET #200 TORRANCE, CA 90504 |
| Contractor | Jones Randy; Lic. No.: 473449-B | 18823 STATE STREET CORONA, CA 92881 |
| Engineer | Abantao,, Marlo Christoph Macaraeg; Lic. No.: C93225 | 230 W 47TH ST LONG BEACH, CA 90805 |
| Engineer | Cai,, Luo; Lic. No.: C80352 | 9428 ETAON AVE M CHATSWORTH, CA 91311 |
| Engineer | Lee,, David Chong; Lic. No.: S5881 | 124 S GUADALUPE AVE, UNIT B RANCHO PALOS VERDES, CA 90277 |
| Geologist | Tsao,, Tze-Tzong; Lic. No.: EG1783 | 9428 ETON AVENUE #M CHATSWORTH, CA 91311 |
| Landscape Architect | Gagne,, Paul Elliott; Lic. No.: LA6223 | 6620 MURIETTA AVE VAN NUYS, CA 91405 |
Inspector Information
| ALFREDO LOPEZ, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
| JAMES POWERS, (213) 482-0361 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Deputy Reinf. Concrete | 6/13/2023 | Conditional Approval | MICHAEL ROSENBERG |
| Excavation/Setback/Form/Re-Bar | 7/12/2023 | Partial Approval | ALAN MORELOS |
| Footing/Foundation/Slab | 7/12/2023 | Not Ready for Inspection | ALAN MORELOS |
| METHANE-Barrier | 7/12/2023 | Approved | ALAN MORELOS |
| METHANE-Subgrade | 7/12/2023 | Approved | ALAN MORELOS |
| Footing/Foundation/Slab | 7/25/2023 | Not Ready for Inspection | JAMES POWERS |
| Excavation/Setback/Form/Re-Bar | 7/26/2023 | Partial Approval | ALAN MORELOS |
| Footing/Foundation/Slab | 8/9/2023 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 9/8/2023 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 9/21/2023 | Conditional Approval | LARRY ARNICK |
| Floor/Roof Diaphrgm/Shear Wall | 9/21/2023 | Partial Approval | LARRY ARNICK |
| Deputy Wood Construction | 10/3/2023 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2023 | Partial Approval | LARRY ARNICK |
| Deputy Wood Construction | 10/18/2023 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2023 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/14/2023 | Partial Approval | JAMES POWERS |
| Green Building Rough | 11/14/2023 | Not Ready for Inspection | JAMES POWERS |
| METHANE-Rough | 11/14/2023 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 11/14/2023 | Not Ready for Inspection | JAMES POWERS |
| Deputy Wood Construction | 11/28/2023 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2023 | Partial Approval | JAMES POWERS |
| Green Building Rough | 12/12/2023 | Not Ready for Inspection | LARRY ARNICK |
| METHANE-Rough | 12/12/2023 | Not Ready for Inspection | LARRY ARNICK |
| Verify Sprinkler Sign Off | 12/12/2023 | Not Ready for Inspection | LARRY ARNICK |
| Wood Frame | 12/12/2023 | Partial Approval | LARRY ARNICK |
| Pre-Inspection | 12/18/2023 | Not Ready for Inspection | JAMES POWERS |
| Drywall Nailing | 12/27/2023 | Partial Approval | JAMES POWERS |
| Insulation | 1/3/2024 | Conditional Approval | DARRYL ARNOLD |
| Insulation | 1/5/2024 | Partial Approval | JAMES POWERS |
| Insulation | 1/9/2024 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 1/16/2024 | Partial Approval | JAMES POWERS |
| Floor/Roof Diaphrgm/Shear Wall | 1/17/2024 | Partial Approval | JAMES POWERS |
| Green Building Rough | 1/17/2024 | Partial Approval | JAMES POWERS |
| METHANE-Rough | 1/17/2024 | Not Ready for Inspection | JAMES POWERS |
| Verify Sprinkler Sign Off | 1/17/2024 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 1/17/2024 | Not Ready for Inspection | JAMES POWERS |
| Insulation | 1/24/2024 | Partial Approval | JAMES POWERS |
| Insulation | 1/26/2024 | Partial Approval | LARRY ARNICK |
| Interior/Exterior Lathing | 1/31/2024 | Approved | JAMES POWERS |
| Drywall Nailing | 2/6/2024 | Partial Approval | LARRY ARNICK |
| Insulation | 2/6/2024 | Partial Approval | LARRY ARNICK |
| Reinforced Concrete Frame | 2/6/2024 | Not Ready for Inspection | LARRY ARNICK |
| Drywall Nailing | 2/20/2024 | Not Ready for Inspection | JAMES POWERS |
| Insulation | 2/20/2024 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 2/26/2024 | Partial Approval | JAMES POWERS |
| Insulation | 2/26/2024 | Partial Approval | JAMES POWERS |
| Drywall Nailing | 3/12/2024 | Partial Approval | JAMES POWERS |
| Light Gage Steel Frame | 3/21/2024 | Partial Approval | JAMES POWERS |
| Masonry Wall/Backfill | 6/18/2024 | Partial Approval | JAMES POWERS |
| Special/Order Compliance | 7/1/2024 | Partial Approval | JAMES POWERS |
| Final | 9/23/2024 | Not Ready for Inspection | JAMES POWERS |
| Footing/Foundation/Slab | 9/23/2024 | Approved | JAMES POWERS |
| Green Building Final | 9/23/2024 | Approved | JAMES POWERS |
| Green Building Rough | 9/23/2024 | Approved | JAMES POWERS |
| METHANE-Final | 9/23/2024 | Approved | JAMES POWERS |
| METHANE-Rough | 9/23/2024 | Approved | JAMES POWERS |
| SGSOV-Seismic Gas S/O Valve | 9/23/2024 | SGSOV Approved | JAMES POWERS |
| Smoke Detectors | 9/23/2024 | Approved | JAMES POWERS |
| Verify Sprinkler Sign Off | 9/23/2024 | Not Ready for Inspection | JAMES POWERS |
| Wood Frame | 9/23/2024 | Partial Approval | JAMES POWERS |
| Deputy Drilled-In Anchors | 9/27/2024 | Partial Approval | JAMES POWERS |
| Deputy Reinf. Concrete | 9/27/2024 | Partial Approval | JAMES POWERS |
| Deputy Steel/Welding | 9/27/2024 | Partial Approval | JAMES POWERS |
| Deputy Wood Construction | 9/27/2024 | Partial Approval | JAMES POWERS |
| Final | 10/17/2024 | OK for TCO | JAMES POWERS |
| Verify Sprinkler Sign Off | 10/17/2024 | Approved | JAMES POWERS |
| Wood Frame | 10/17/2024 | Approved | JAMES POWERS |
| Final | 11/20/2024 | OK to Issue CofO | JAMES POWERS |