1634 S CREST DR 90035

Certificate Information: 1634 S CREST DR 90035

Application / Permit
21010-10000-05405
Plan Check / Job No.
B21LA19312
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) TWO-STORY SFD WITH ATTACHED TWO CAR GARAGE
Permit Issued
Issued on 3/8/2022
Issuing Office
Current Status
CofO Issued on 1/13/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/14/2021 APPLICANT
Assigned to Plan Check Engineer 10/28/2021 LARRY LEE
Corrections Issued 11/3/2021 LARRY LEE
Quality Review Completed 11/5/2021 SAI KHUM
Plan Check Approved 3/3/2022 LARRY LEE
Issued 3/8/2022 APPLICANT
Building Plans Picked Up 3/8/2022 APPLICANT
CofO in Progress 12/16/2022 MICHAEL PELHAM
Permit Finaled 1/13/2023 RONALD MYRICK
CofO Issued 1/13/2023 RONALD MYRICK
Permit Finaled 1/13/2023 RONALD MYRICK

Permit Application Clearance Information

Address approval Cleared 11/17/2021 CINDY QI
Eng Process Fee Ord 176,300 Cleared 11/17/2021 CINDY QI
Permit Cleared 11/17/2021 CINDY QI
Sewer availability Cleared 11/17/2021 CINDY QI
Trees in Parkway Cleared 12/29/2021 ADALBERTO VERA
Hydrant and Access approval Cleared 1/16/2022 JOHN CONNEALLY
Low Impact Development Cleared 2/9/2022 CHRIS VONG
Roof/Waste drainage to street Cleared 2/10/2022 CINDY QI
GPI Written Notices Cleared 2/28/2022 SAI KHUM

Contact Information

Architect Leishman,, Thomas Edward; Lic. No.: C15059 28100 RIDGEFERN COURT      RANCHO PALOS VERDES, CA 90275
Contractor Owner-Builder       ,
Engineer Yuzon,, Benigno Sari; Lic. No.: S3454 2511 PEACHWOOD PLACE      WESTLAKE VILLAGE, CA 91361
Geologist Minas,, Shant; Lic. No.: GEO8859 566 RIVERDALE DRIVE      GLENDALE, CA 91204

Inspector Information

WILBER ROSALES, (310) 914-3892 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

METHANE-Rough 3/15/2022 Not Ready for Inspection EVAN COOPER
Underground Mechanical 3/15/2022 Not Ready for Inspection EVAN COOPER
Excavation/Setback/Form/Re-Bar 3/18/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 3/18/2022 Corrections Issued KEVIN SARGSYAN
PLUMBING-Rough 3/19/2022 Partial Approval JUAN VALENZUELA
Underground Mechanical 3/19/2022 Partial Approval JUAN VALENZUELA
Excavation/Setback/Form/Re-Bar 3/21/2022 Approved JOHNNY MIRANDA
Deputy Reinf. Concrete 3/23/2022 Conditional Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 4/11/2022 Partial Approval RYAN SALAZAR
BUILDING-Rough-Frame 5/19/2022 Corrections Issued EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 5/19/2022 Partial Approval EVAN COOPER
Deputy Wood Construction 5/23/2022 Conditional Approval EVAN COOPER
PLUMBING-Rough 5/25/2022 Approved EVAN COOPER
ELECTRICAL-Rough 6/1/2022 Approved EVAN COOPER
HVAC-Rough 6/7/2022 Approved EVAN COOPER
Shower Pan 6/7/2022 Approved EVAN COOPER
Interior/Exterior Lathing 6/9/2022 Partial Approval STEPHANIE SWANSON
BUILDING-Rough-Frame 6/16/2022 Corrections Issued KEVIN SARGSYAN
Green Building Rough 6/16/2022 Not Ready for Inspection KEVIN SARGSYAN
METHANE-Rough 6/16/2022 Not Ready for Inspection KEVIN SARGSYAN
Verify Sprinkler Sign Off 6/16/2022 Approved KEVIN SARGSYAN
Wood Frame 6/24/2022 Approved EVAN COOPER
Insulation 6/29/2022 Approved EVAN COOPER
Insulation 6/30/2022 Approved EVAN COOPER
Interior/Exterior Lathing 6/30/2022 Approved EVAN COOPER
Drywall Nailing 7/7/2022 Approved EVAN COOPER
HVAC-Final 9/1/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
PLUMBING-Final 9/1/2022 Corrections Issued GERMAN RODRIGUEZ MENDOZA
ELECTRICAL-Final 9/6/2022 Partial Approval EVAN COOPER
HVAC-Final 9/6/2022 Approved EVAN COOPER
PLUMBING-Final 9/6/2022 Approved EVAN COOPER
Service/Power Release 9/6/2022 Not Ready for Inspection EVAN COOPER
Service/Power Release 10/25/2022 Not Ready for Inspection EVAN COOPER
BUILDING-Rough-Frame 11/21/2022 No Access for Inspection OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 11/21/2022 SGSOV Not Ready OGANES TARAKHCHYAN
BUILDING-Rough-Frame 12/6/2022 Approved OGANES TARAKHCHYAN
ELECTRICAL-Final 12/6/2022 Approved OGANES TARAKHCHYAN
Footing/Foundation/Slab 12/6/2022 Approved OGANES TARAKHCHYAN
Green Building Final 12/6/2022 Approved OGANES TARAKHCHYAN
Green Building Rough 12/6/2022 Approved OGANES TARAKHCHYAN
HVAC-Final 12/6/2022 Approved OGANES TARAKHCHYAN
METHANE-Barrier 12/6/2022 Approved OGANES TARAKHCHYAN
METHANE-Final 12/6/2022 Approved OGANES TARAKHCHYAN
METHANE-Rough 12/6/2022 Approved OGANES TARAKHCHYAN
METHANE-Subgrade 12/6/2022 Approved OGANES TARAKHCHYAN
PLUMBING-Final 12/6/2022 Approved OGANES TARAKHCHYAN
SGSOV-Seismic Gas S/O Valve 12/6/2022 SGSOV Approved OGANES TARAKHCHYAN
Service/Power Release 12/6/2022 Approved OGANES TARAKHCHYAN
Smoke Detectors 12/6/2022 Approved OGANES TARAKHCHYAN
Final 12/16/2022 OK to Issue CofO MICHAEL PELHAM