1634 S CREST DR 90035
Certificate Information: 1634 S CREST DR 90035
- Application / Permit
- 21010-10000-05405
- Plan Check / Job No.
- B21LA19312
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) TWO-STORY SFD WITH ATTACHED TWO CAR GARAGE
- Permit Issued
- Issued on 3/8/2022
- Issuing Office
- Current Status
- CofO Issued on 1/13/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | LARRY LEE |
| Corrections Issued | 11/3/2021 | LARRY LEE |
| Quality Review Completed | 11/5/2021 | SAI KHUM |
| Plan Check Approved | 3/3/2022 | LARRY LEE |
| Issued | 3/8/2022 | APPLICANT |
| Building Plans Picked Up | 3/8/2022 | APPLICANT |
| CofO in Progress | 12/16/2022 | MICHAEL PELHAM |
| Permit Finaled | 1/13/2023 | RONALD MYRICK |
| CofO Issued | 1/13/2023 | RONALD MYRICK |
| Permit Finaled | 1/13/2023 | RONALD MYRICK |
Permit Application Clearance Information
| Address approval | Cleared | 11/17/2021 | CINDY QI |
| Eng Process Fee Ord 176,300 | Cleared | 11/17/2021 | CINDY QI |
| Permit | Cleared | 11/17/2021 | CINDY QI |
| Sewer availability | Cleared | 11/17/2021 | CINDY QI |
| Trees in Parkway | Cleared | 12/29/2021 | ADALBERTO VERA |
| Hydrant and Access approval | Cleared | 1/16/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 2/9/2022 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 2/10/2022 | CINDY QI |
| GPI Written Notices | Cleared | 2/28/2022 | SAI KHUM |
Contact Information
| Architect | Leishman,, Thomas Edward; Lic. No.: C15059 | 28100 RIDGEFERN COURT RANCHO PALOS VERDES, CA 90275 |
| Contractor | Owner-Builder | , |
| Engineer | Yuzon,, Benigno Sari; Lic. No.: S3454 | 2511 PEACHWOOD PLACE WESTLAKE VILLAGE, CA 91361 |
| Geologist | Minas,, Shant; Lic. No.: GEO8859 | 566 RIVERDALE DRIVE GLENDALE, CA 91204 |
Inspector Information
| WILBER ROSALES, (310) 914-3892 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| METHANE-Rough | 3/15/2022 | Not Ready for Inspection | EVAN COOPER |
| Underground Mechanical | 3/15/2022 | Not Ready for Inspection | EVAN COOPER |
| Excavation/Setback/Form/Re-Bar | 3/18/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 3/18/2022 | Corrections Issued | KEVIN SARGSYAN |
| PLUMBING-Rough | 3/19/2022 | Partial Approval | JUAN VALENZUELA |
| Underground Mechanical | 3/19/2022 | Partial Approval | JUAN VALENZUELA |
| Excavation/Setback/Form/Re-Bar | 3/21/2022 | Approved | JOHNNY MIRANDA |
| Deputy Reinf. Concrete | 3/23/2022 | Conditional Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 4/11/2022 | Partial Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 5/19/2022 | Corrections Issued | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2022 | Partial Approval | EVAN COOPER |
| Deputy Wood Construction | 5/23/2022 | Conditional Approval | EVAN COOPER |
| PLUMBING-Rough | 5/25/2022 | Approved | EVAN COOPER |
| ELECTRICAL-Rough | 6/1/2022 | Approved | EVAN COOPER |
| HVAC-Rough | 6/7/2022 | Approved | EVAN COOPER |
| Shower Pan | 6/7/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/9/2022 | Partial Approval | STEPHANIE SWANSON |
| BUILDING-Rough-Frame | 6/16/2022 | Corrections Issued | KEVIN SARGSYAN |
| Green Building Rough | 6/16/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| METHANE-Rough | 6/16/2022 | Not Ready for Inspection | KEVIN SARGSYAN |
| Verify Sprinkler Sign Off | 6/16/2022 | Approved | KEVIN SARGSYAN |
| Wood Frame | 6/24/2022 | Approved | EVAN COOPER |
| Insulation | 6/29/2022 | Approved | EVAN COOPER |
| Insulation | 6/30/2022 | Approved | EVAN COOPER |
| Interior/Exterior Lathing | 6/30/2022 | Approved | EVAN COOPER |
| Drywall Nailing | 7/7/2022 | Approved | EVAN COOPER |
| HVAC-Final | 9/1/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| PLUMBING-Final | 9/1/2022 | Corrections Issued | GERMAN RODRIGUEZ MENDOZA |
| ELECTRICAL-Final | 9/6/2022 | Partial Approval | EVAN COOPER |
| HVAC-Final | 9/6/2022 | Approved | EVAN COOPER |
| PLUMBING-Final | 9/6/2022 | Approved | EVAN COOPER |
| Service/Power Release | 9/6/2022 | Not Ready for Inspection | EVAN COOPER |
| Service/Power Release | 10/25/2022 | Not Ready for Inspection | EVAN COOPER |
| BUILDING-Rough-Frame | 11/21/2022 | No Access for Inspection | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 11/21/2022 | SGSOV Not Ready | OGANES TARAKHCHYAN |
| BUILDING-Rough-Frame | 12/6/2022 | Approved | OGANES TARAKHCHYAN |
| ELECTRICAL-Final | 12/6/2022 | Approved | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 12/6/2022 | Approved | OGANES TARAKHCHYAN |
| Green Building Final | 12/6/2022 | Approved | OGANES TARAKHCHYAN |
| Green Building Rough | 12/6/2022 | Approved | OGANES TARAKHCHYAN |
| HVAC-Final | 12/6/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Barrier | 12/6/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Final | 12/6/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Rough | 12/6/2022 | Approved | OGANES TARAKHCHYAN |
| METHANE-Subgrade | 12/6/2022 | Approved | OGANES TARAKHCHYAN |
| PLUMBING-Final | 12/6/2022 | Approved | OGANES TARAKHCHYAN |
| SGSOV-Seismic Gas S/O Valve | 12/6/2022 | SGSOV Approved | OGANES TARAKHCHYAN |
| Service/Power Release | 12/6/2022 | Approved | OGANES TARAKHCHYAN |
| Smoke Detectors | 12/6/2022 | Approved | OGANES TARAKHCHYAN |
| Final | 12/16/2022 | OK to Issue CofO | MICHAEL PELHAM |