1165 1/4-1/2 W 39TH ST 90037
Certificate Information: 1165 1/4-1/2 W 39TH ST 90037
- Application / Permit
- 21010-10000-05397
- Plan Check / Job No.
- B21LA19264
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- 2 OF 3 (N) 3-STORY, TYPE V-B DUPLEXES WITH (1) ATTACHED ADU. **REAR BUILDING**
- Permit Issued
- Issued on 2/10/2023
- Issuing Office
- Current Status
- CofO Issued on 5/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/14/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | JOHNNY WU |
| Corrections Issued | 12/9/2021 | JOHNNY WU |
| Quality Review Completed | 12/10/2021 | FARUK SEZER |
| Building Plans Picked Up | 12/14/2021 | APPLICANT |
| Applicant returned to address corrections | 1/13/2022 | JOHNNY WU |
| Applicant returned to address corrections | 8/11/2022 | JOHNNY WU |
| Applicant returned to address corrections | 8/23/2022 | JOHNNY WU |
| Applicant returned to address corrections | 1/26/2023 | JOHNNY WU |
| Plan Check Approved | 1/26/2023 | JOHNNY WU |
| Issued | 2/10/2023 | APPLICANT |
| CofO in Progress | 5/6/2024 | SABAS ALONSO |
| Permit Finaled | 5/7/2024 | DEROLD HAUFF |
| CofO Issued | 5/7/2024 | DEROLD HAUFF |
| Permit Finaled | 5/7/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/6/2022 | AMAAN MALIK |
| Address approval | Cleared | 1/6/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 1/21/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 1/21/2022 | AMAAN MALIK |
| Hydrant and Access approval | Cleared | 10/6/2022 | MATTHEW CRAIG |
| Low Impact Development | Cleared | 12/7/2022 | AMMAR ELTAWIL |
| Highway dedication | Cleared | 1/17/2023 | AMAAN MALIK |
| Permit | Cleared | 1/17/2023 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 1/17/2023 | AMAAN MALIK |
| ZI | Cleared | 1/17/2023 | JASON CHAN |
| Green Code | Cleared | 1/26/2023 | JOHNNY WU |
Contact Information
| Contractor | Amr Construction Co Inc; Lic. No.: 1082830-B | 4950 S YOSEMITE ST GREENWOOD VILLAGE, CO 80111 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 4/10/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Underground Mechanical | 4/10/2023 | Partial Approval | STUART CHAPMAN |
| Footing/Foundation/Slab | 4/14/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 4/24/2023 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Sewer | 4/24/2023 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 4/24/2023 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Rough | 4/25/2023 | Partial Approval | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 6/5/2023 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 6/5/2023 | Partial Approval | SABAS ALONSO |
| Green Building Rough | 6/5/2023 | Not Ready for Inspection | SABAS ALONSO |
| Verify Sprinkler Sign Off | 6/5/2023 | Not Ready for Inspection | SABAS ALONSO |
| Wood Frame | 6/5/2023 | Not Ready for Inspection | SABAS ALONSO |
| Deputy Wood Construction | 6/6/2023 | Conditional Approval | SABAS ALONSO |
| ELECTRICAL-Rough | 7/10/2023 | Approved | SABAS ALONSO |
| Green Building Rough | 7/10/2023 | Approved | SABAS ALONSO |
| HVAC-Rough | 7/10/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 7/10/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 7/17/2023 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Rough | 7/17/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 7/17/2023 | Not Ready for Inspection | ANTHONY EGSON |
| Wood Frame | 7/17/2023 | Not Ready for Inspection | ANTHONY EGSON |
| BUILDING-Rough-Frame | 7/21/2023 | Corrections Issued | ALIZAH MAYAGOITIA |
| BUILDING-Rough-Frame | 7/31/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Drywall Nailing | 7/31/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Insulation | 7/31/2023 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 7/31/2023 | Corrections Issued | ENRIQUE MIRELES |
| Drywall Nailing | 8/8/2023 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/8/2023 | Approved | SABAS ALONSO |
| Drywall Nailing | 8/11/2023 | Approved | SABAS ALONSO |
| Shower Pan | 9/27/2023 | Approved | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 10/31/2023 | Approved | SABAS ALONSO |
| Special/Order Compliance | 11/16/2023 | Partial Inspection | SABAS ALONSO |
| BUILDING-Rough-Frame | 1/5/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 1/5/2024 | Not Ready for Inspection | SABAS ALONSO |
| Final | 1/5/2024 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 1/5/2024 | Approved | SABAS ALONSO |
| HVAC-Final | 1/5/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 1/5/2024 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 1/5/2024 | SGSOV Not Required | SABAS ALONSO |
| Service/Power Release | 1/5/2024 | Not Ready for Inspection | SABAS ALONSO |
| Smoke Detectors | 1/5/2024 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 1/5/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 1/11/2024 | Approved | SABAS ALONSO |
| Final | 1/11/2024 | Corrections Issued | SABAS ALONSO |
| HVAC-Final | 1/11/2024 | Approved | SABAS ALONSO |
| PLUMBING-Final | 1/11/2024 | Approved | SABAS ALONSO |
| ELECTRICAL-Final | 4/3/2024 | Approved | SABAS ALONSO |
| Final | 4/3/2024 | Corrections Issued | SABAS ALONSO |
| Final | 5/6/2024 | OK to Issue CofO | SABAS ALONSO |
| Service/Power Release | 5/6/2024 | Approved | SABAS ALONSO |