2209 1/3 N SICHEL ST 90031

Certificate Information: 2209 1/3 N SICHEL ST 90031

Application / Permit
21010-10000-05367
Plan Check / Job No.
B21LA19198
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan NEW 2-STORY DETACHED ADU PER LAMC 12.22 A.33(c) AND (d)
Permit Issued
Issued on 3/22/2022
Issuing Office
Current Status
CofO Issued on 12/15/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/13/2021 APPLICANT
Assigned to Plan Check Engineer 11/18/2021 CRYSTEL MAALOUF
Corrections Issued 12/1/2021 CRYSTEL MAALOUF
Quality Review Completed 12/6/2021 HERNAN ARREOLA
Applicant returned to address corrections 12/27/2021 CRYSTEL MAALOUF
Applicant returned to address corrections 1/12/2022 CRYSTEL MAALOUF
Plan Check Approved 1/28/2022 CRYSTEL MAALOUF
Issued 3/22/2022 APPLICANT
CofO in Progress 10/2/2023 OSVALDO PARAMO
CofO in Progress 10/2/2023 OSVALDO PARAMO
No Progress 10/2/2023 OSVALDO PARAMO
CofO in Progress 10/2/2023 SCOTT FINNILA
CofO in Progress 12/13/2023 SCOTT FINNILA
CofO Issued 12/15/2023 DEROLD HAUFF
Permit Finaled 12/15/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/21/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 1/6/2022 CELINA MORENO
Sewer availability Cleared 1/6/2022 CELINA MORENO
CPC Cleared 1/20/2022 JONATHAN KAPLAN
HPOZ Cleared 1/20/2022 JONATHAN KAPLAN

Contact Information

Contractor Derbarsegian Robert; Lic. No.: 863925-B 3315 MONTROSE AVE      GLENDALE, CA 91214
Engineer Gharai,, Armin; Lic. No.: C61464 6701 CORIE LN      WEST HILLS, CA 91307

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 4/13/2022 Partial Approval OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 4/28/2022 Approved OSVALDO PARAMO
Footing/Foundation/Slab 5/4/2022 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 5/12/2022 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 5/23/2022 Partial Approval OSVALDO PARAMO
Deputy Wood Construction 6/1/2022 Conditional Approval OSVALDO PARAMO
ELECTRICAL-Rough 7/14/2022 Approved OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 7/14/2022 Approved OSVALDO PARAMO
PLUMBING-Rough 7/14/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 8/1/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 8/1/2022 Partial Approval OSVALDO PARAMO
Verify Sprinkler Sign Off 8/1/2022 Approved OSVALDO PARAMO
Insulation 8/9/2022 Approved ALIZAH MAYAGOITIA
Shower Pan 8/9/2022 Approved ALIZAH MAYAGOITIA
Drywall Nailing 8/16/2022 Approved OSVALDO PARAMO
Interior/Exterior Lathing 8/16/2022 Approved OSVALDO PARAMO
Underground Mechanical 11/29/2022 Approved OSVALDO PARAMO
Final 9/11/2023 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 9/11/2023 SGSOV Not Ready OSVALDO PARAMO
Service/Power Release 9/11/2023 Not Ready for Inspection OSVALDO PARAMO
Smoke Detectors 9/11/2023 Approved OSVALDO PARAMO
Final 9/28/2023 Partial Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 9/28/2023 SGSOV Approved OSVALDO PARAMO
Service/Power Release 9/28/2023 Approved OSVALDO PARAMO
Final 11/20/2023 Not Ready for Inspection OSVALDO PARAMO
Final 12/11/2023 OK to Issue CofO OSVALDO PARAMO