3932 S MINERVA AVE 90066

Certificate Information: 3932 S MINERVA AVE 90066

Application / Permit
21010-10000-05347
Plan Check / Job No.
B21LA19143
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY DWELLING WITH ATTACHED 2 CARS GARAGE
Permit Issued
Issued on 10/10/2023
Issuing Office
Metro
Current Status
CofO Issued on 2/5/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/12/2021 APPLICANT
Assigned to Plan Check Engineer 11/9/2021 KHEDER ALRAZAA
Corrections Issued 11/12/2021 KHEDER ALRAZAA
Quality Review Completed 11/24/2021 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 12/1/2021 APPLICANT
Applicant returned to address corrections 4/6/2022 KHEDER ALRAZAA
Applicant returned to address corrections 9/13/2022 KHEDER ALRAZAA
Applicant returned to address corrections 11/2/2022 KHEDER ALRAZAA
Applicant returned to address corrections 3/20/2023 KHEDER ALRAZAA
Plan Check Approved 3/30/2023 KHEDER ALRAZAA
Issued 10/10/2023 APPLICANT
CofO in Progress 2/4/2026 JESUS PINEDA
Permit Finaled 2/5/2026 RICHARD STEINBACH
CofO Issued 2/5/2026 RICHARD STEINBACH
Permit Finaled 2/5/2026 RICHARD STEINBACH

Permit Application Clearance Information

Hydrant and Access approval Cleared 3/11/2022 CINDY JOSSELYN
Trees in Parkway Cleared 3/23/2022 KHEDER ALRAZAA
Specific Plan Cleared 3/31/2022 FREDDY GARCIA
Low Impact Development Cleared 4/28/2022 SARAH YOUSSEF
Permit Cleared 5/26/2022 ANTHONY MAINEZ
Eng Process Fee Ord 176,300 Cleared 5/31/2022 ANTHONY MAINEZ
Sewer availability Cleared 5/31/2022 ANTHONY MAINEZ
Miscellaneous Cleared 8/4/2022 RAYMOND MUGAMBWA
Roof/Waste drainage to street Cleared 8/29/2022 ANTHONY MAINEZ

Contact Information

Architect Wang,, Sean; Lic. No.: C31230 1000 ABAJO DR. #208      MONTEREY PARK, CA 91754
Contractor Mcwong Holding Company; Lic. No.: 685220-B 809 S ATLANTIC BLVD 201      MONTEREY PARK, CA 91754
Engineer Lin,, Jason; Lic. No.: S6095 801 CREST VISTA DR      MONTEREY PARK, CA 91754
Landscape Architect Ye,, Jenny Haiyan; Lic. No.: LA5059 14315 HARVEST VALLEY AVENUE      EASTVALE, CA 92880

Inspector Information

DAKOTA LOW, (310) 914-3895 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/7/2024 Corrections Issued JESUS RODRIGUEZ
Sewer 6/7/2024 Corrections Issued JESUS RODRIGUEZ
PLUMBING-Rough 6/13/2024 Partial Approval JESUS RODRIGUEZ
Sewer 6/13/2024 Approved JESUS RODRIGUEZ
Footing/Foundation/Slab 7/16/2024 Approved JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 8/9/2024 Partial Approval EVAN COOPER
Floor/Roof Diaphrgm/Shear Wall 9/6/2024 Not Ready for Inspection TEMISTOCLES CAAL
Floor/Roof Diaphrgm/Shear Wall 9/30/2024 Corrections Issued JESUS PINEDA
Deputy Wood Construction 10/1/2024 Conditional Approval MICHAEL PELHAM
Floor/Roof Diaphrgm/Shear Wall 10/7/2024 Corrections Issued JESUS PINEDA
Floor/Roof Diaphrgm/Shear Wall 10/28/2024 Conditional Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 12/6/2024 Corrections Issued JESUS PINEDA
ELECTRICAL-Rough 12/6/2024 Approved JESUS PINEDA
Green Building Rough 12/6/2024 Not Ready for Inspection JESUS PINEDA
HVAC-Rough 12/6/2024 Corrections Issued JESUS PINEDA
PLUMBING-Rough 12/6/2024 Corrections Issued JESUS PINEDA
Verify Sprinkler Sign Off 12/6/2024 Approved JESUS PINEDA
BUILDING-Rough-Frame 12/24/2024 Approved JESUS PINEDA
ELECTRICAL-Rough 12/24/2024 Approved JESUS PINEDA
Green Building Rough 12/24/2024 Approved JESUS PINEDA
HVAC-Rough 12/24/2024 Approved JESUS PINEDA
Interior/Exterior Lathing 12/24/2024 Partial Approval JESUS PINEDA
PLUMBING-Rough 12/24/2024 Approved JESUS PINEDA
Insulation 1/17/2025 Corrections Issued JESUS PINEDA
Drywall Nailing 2/4/2025 Approved BOBBY KEY
Insulation 2/4/2025 Approved BOBBY KEY
Interior/Exterior Lathing 2/4/2025 Approved BOBBY KEY
Shower Pan 2/4/2025 Approved BOBBY KEY
Sewer 6/12/2025 Partial Approval MICHAEL ALLEN
ELECTRICAL-Rough 6/18/2025 Partial Approval MICHAEL ALLEN
Gas Test 6/18/2025 Approved MICHAEL ALLEN
PLUMBING-Rough 6/25/2025 Partial Approval BOBBY KEY
Gas Test 8/4/2025 Approved MICHAEL ALLEN
ELECTRICAL-Final 9/10/2025 Not Ready for Inspection MICHAEL ALLEN
HVAC-Final 9/10/2025 Partial Approval MICHAEL ALLEN
PLUMBING-Final 9/10/2025 Approved MICHAEL ALLEN
Special/Order Compliance 9/10/2025 Corrections Issued MICHAEL ALLEN
ELECTRICAL-Final 9/19/2025 Corrections Issued JESUS PINEDA
Service/Power Release 9/19/2025 Not Ready for Inspection JESUS PINEDA
ELECTRICAL-Final 9/24/2025 Approved WILBER ROSALES
Service/Power Release 10/8/2025 Approved MICHAEL ALLEN
Final 11/5/2025 No Access for Inspection WILBER ROSALES
Green Building Final 11/5/2025 No Access for Inspection WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 11/5/2025 SGSOV Not Ready WILBER ROSALES
Smoke Detectors 11/5/2025 No Access for Inspection WILBER ROSALES
Final 11/10/2025 Corrections Issued WILBER ROSALES
Green Building Final 11/10/2025 Approved WILBER ROSALES
HVAC-Final 11/10/2025 Approved WILBER ROSALES
SGSOV-Seismic Gas S/O Valve 11/10/2025 SGSOV Approved WILBER ROSALES
Smoke Detectors 11/10/2025 Approved WILBER ROSALES
Final 1/27/2026 Corrections Issued ANTHONY EGSON
Final 2/3/2026 OK to Issue CofO JESUS PINEDA