5652-5652 1/2 W LA MIRADA AVE 90038

Certificate Information: 5652-5652 1/2 W LA MIRADA AVE 90038

Application / Permit
21010-10000-05341
Plan Check / Job No.
B21LA19129
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 3-STORY DUPLEX WITH 2 CAR GARAGE AND AN ATTACHED ADU PER LAMC 12.22 A.33(c) and (e)
Permit Issued
Issued on 2/2/2023
Issuing Office
Metro
Current Status
CofO Issued on 3/13/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/17/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 KHEDER ALRAZAA
Corrections Issued 11/6/2021 KHEDER ALRAZAA
Quality Review Completed 11/16/2021 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 3/9/2022 KHEDER ALRAZAA
Building Plans Picked Up 3/23/2022 APPLICANT
Plan Check Approved 5/4/2022 KHEDER ALRAZAA
Issued 2/2/2023 APPLICANT
CofO in Progress 2/6/2025 CRAIG VAUGHAN
No Progress 2/23/2025 DEROLD HAUFF
CofO in Progress 2/23/2025 DEROLD HAUFF
Permit Finaled 3/13/2025 DEROLD HAUFF
CofO Issued 3/13/2025 DEROLD HAUFF
Permit Finaled 3/13/2025 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/8/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 12/13/2021 CELINA MORENO
Sewer availability Cleared 1/10/2022 CELINA MORENO
Historic Resource Verification Cleared 2/10/2022 MAX LODER
Hydrant and Access approval Cleared 2/11/2022 KURT CORRAL
Redevelopment Project Area Cleared 2/16/2022 DAVID URITA
Low Impact Development Cleared 3/3/2022 TA ANH
Roof/Waste drainage to street Cleared 3/4/2022 CELINA MORENO
DAS Clearance Cleared 5/4/2022 NORLITO MEDRANO

Contact Information

Contractor Emerald Builders And Developers; Lic. No.: 1068007-B 1412 W 22ND STREET      LOS ANGELES, CA 90007
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 4/17/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Underground Mechanical 4/18/2023 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 4/20/2023 Partial Approval JOAQUIN GREENOUGH
Underground Mechanical 4/20/2023 Partial Approval JOAQUIN GREENOUGH
Footing/Foundation/Slab 5/8/2023 Corrections Issued RUBEN SALAS
Excavation/Setback/Form/Re-Bar 5/11/2023 Corrections Issued JOAQUIN GREENOUGH
Footing/Foundation/Slab 5/17/2023 Approved JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 7/5/2023 Corrections Issued JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 8/1/2023 Partial Approval BRIAN SULLIVAN
PLUMBING-Rough 9/14/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Floor/Roof Diaphrgm/Shear Wall 9/28/2023 Partial Approval JOAQUIN GREENOUGH
PLUMBING-Rough 9/28/2023 Approved JOAQUIN GREENOUGH
Deputy Wood Construction 12/12/2023 Conditional Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 12/13/2023 Partial Approval BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 12/29/2023 Partial Approval STUART CHAPMAN
ELECTRICAL-Rough 1/4/2024 Not Ready for Inspection BRIAN SULLIVAN
ELECTRICAL-Rough 1/22/2024 Corrections Issued ROY SPAULDING
BUILDING-Rough-Frame 2/16/2024 Approved ROY SPAULDING
ELECTRICAL-Rough 2/16/2024 Approved ROY SPAULDING
Green Building Rough 2/16/2024 Approved ROY SPAULDING
HVAC-Rough 2/16/2024 Partial Approval ROY SPAULDING
MERV13>=Rough 2/16/2024 Approved ROY SPAULDING
Verify Sprinkler Sign Off 2/16/2024 Approved ROY SPAULDING
Insulation 2/26/2024 Approved ROY SPAULDING
Drywall Nailing 3/5/2024 Approved BRIAN SULLIVAN
Interior/Exterior Lathing 3/22/2024 Approved ROY SPAULDING
Final 1/7/2025 Not Ready for Inspection BRENDAN MORELLI
Green Building Final 1/7/2025 Not Ready for Inspection BRENDAN MORELLI
MERV13>=Final 1/7/2025 Not Ready for Inspection BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 1/7/2025 SGSOV Not Ready BRENDAN MORELLI
Service/Power Release 1/7/2025 Not Ready for Inspection BRENDAN MORELLI
Smoke Detectors 1/7/2025 Not Ready for Inspection BRENDAN MORELLI
ELECTRICAL-Final 1/17/2025 Corrections Issued BRENDAN MORELLI
Green Building Final 1/17/2025 Approved BRENDAN MORELLI
HVAC-Final 1/17/2025 Corrections Issued BRENDAN MORELLI
MERV13>=Final 1/17/2025 Approved BRENDAN MORELLI
SGSOV-Seismic Gas S/O Valve 1/17/2025 SGSOV Approved BRENDAN MORELLI
Service/Power Release 1/17/2025 Not Ready for Inspection BRENDAN MORELLI
Smoke Detectors 1/17/2025 Approved BRENDAN MORELLI
ELECTRICAL-Final 1/23/2025 Approved CRAIG VAUGHAN
Gas Test 1/23/2025 Approved CRAIG VAUGHAN
HVAC-Final 1/23/2025 Approved CRAIG VAUGHAN
PLUMBING-Final 1/23/2025 Approved CRAIG VAUGHAN
Service/Power Release 1/23/2025 Approved CRAIG VAUGHAN
Final 1/31/2025 Conditional Approval CRAIG VAUGHAN
Final 2/4/2025 OK to Issue CofO CRAIG VAUGHAN