5652-5652 1/2 W LA MIRADA AVE 90038
Certificate Information: 5652-5652 1/2 W LA MIRADA AVE 90038
- Application / Permit
- 21010-10000-05341
- Plan Check / Job No.
- B21LA19129
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) 3-STORY DUPLEX WITH 2 CAR GARAGE AND AN ATTACHED ADU PER LAMC 12.22 A.33(c) and (e)
- Permit Issued
- Issued on 2/2/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 3/13/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/17/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | KHEDER ALRAZAA |
| Corrections Issued | 11/6/2021 | KHEDER ALRAZAA |
| Quality Review Completed | 11/16/2021 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 3/9/2022 | KHEDER ALRAZAA |
| Building Plans Picked Up | 3/23/2022 | APPLICANT |
| Plan Check Approved | 5/4/2022 | KHEDER ALRAZAA |
| Issued | 2/2/2023 | APPLICANT |
| CofO in Progress | 2/6/2025 | CRAIG VAUGHAN |
| No Progress | 2/23/2025 | DEROLD HAUFF |
| CofO in Progress | 2/23/2025 | DEROLD HAUFF |
| Permit Finaled | 3/13/2025 | DEROLD HAUFF |
| CofO Issued | 3/13/2025 | DEROLD HAUFF |
| Permit Finaled | 3/13/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/8/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2021 | CELINA MORENO |
| Sewer availability | Cleared | 1/10/2022 | CELINA MORENO |
| Historic Resource Verification | Cleared | 2/10/2022 | MAX LODER |
| Hydrant and Access approval | Cleared | 2/11/2022 | KURT CORRAL |
| Redevelopment Project Area | Cleared | 2/16/2022 | DAVID URITA |
| Low Impact Development | Cleared | 3/3/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 3/4/2022 | CELINA MORENO |
| DAS Clearance | Cleared | 5/4/2022 | NORLITO MEDRANO |
Contact Information
| Contractor | Emerald Builders And Developers; Lic. No.: 1068007-B | 1412 W 22ND STREET LOS ANGELES, CA 90007 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Underground Mechanical | 4/17/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Underground Mechanical | 4/18/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 4/20/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Underground Mechanical | 4/20/2023 | Partial Approval | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 5/8/2023 | Corrections Issued | RUBEN SALAS |
| Excavation/Setback/Form/Re-Bar | 5/11/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Footing/Foundation/Slab | 5/17/2023 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 7/5/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2023 | Partial Approval | BRIAN SULLIVAN |
| PLUMBING-Rough | 9/14/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 9/28/2023 | Partial Approval | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 9/28/2023 | Approved | JOAQUIN GREENOUGH |
| Deputy Wood Construction | 12/12/2023 | Conditional Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2023 | Partial Approval | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/29/2023 | Partial Approval | STUART CHAPMAN |
| ELECTRICAL-Rough | 1/4/2024 | Not Ready for Inspection | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 1/22/2024 | Corrections Issued | ROY SPAULDING |
| BUILDING-Rough-Frame | 2/16/2024 | Approved | ROY SPAULDING |
| ELECTRICAL-Rough | 2/16/2024 | Approved | ROY SPAULDING |
| Green Building Rough | 2/16/2024 | Approved | ROY SPAULDING |
| HVAC-Rough | 2/16/2024 | Partial Approval | ROY SPAULDING |
| MERV13>=Rough | 2/16/2024 | Approved | ROY SPAULDING |
| Verify Sprinkler Sign Off | 2/16/2024 | Approved | ROY SPAULDING |
| Insulation | 2/26/2024 | Approved | ROY SPAULDING |
| Drywall Nailing | 3/5/2024 | Approved | BRIAN SULLIVAN |
| Interior/Exterior Lathing | 3/22/2024 | Approved | ROY SPAULDING |
| Final | 1/7/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Green Building Final | 1/7/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| MERV13>=Final | 1/7/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 1/7/2025 | SGSOV Not Ready | BRENDAN MORELLI |
| Service/Power Release | 1/7/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Smoke Detectors | 1/7/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| ELECTRICAL-Final | 1/17/2025 | Corrections Issued | BRENDAN MORELLI |
| Green Building Final | 1/17/2025 | Approved | BRENDAN MORELLI |
| HVAC-Final | 1/17/2025 | Corrections Issued | BRENDAN MORELLI |
| MERV13>=Final | 1/17/2025 | Approved | BRENDAN MORELLI |
| SGSOV-Seismic Gas S/O Valve | 1/17/2025 | SGSOV Approved | BRENDAN MORELLI |
| Service/Power Release | 1/17/2025 | Not Ready for Inspection | BRENDAN MORELLI |
| Smoke Detectors | 1/17/2025 | Approved | BRENDAN MORELLI |
| ELECTRICAL-Final | 1/23/2025 | Approved | CRAIG VAUGHAN |
| Gas Test | 1/23/2025 | Approved | CRAIG VAUGHAN |
| HVAC-Final | 1/23/2025 | Approved | CRAIG VAUGHAN |
| PLUMBING-Final | 1/23/2025 | Approved | CRAIG VAUGHAN |
| Service/Power Release | 1/23/2025 | Approved | CRAIG VAUGHAN |
| Final | 1/31/2025 | Conditional Approval | CRAIG VAUGHAN |
| Final | 2/4/2025 | OK to Issue CofO | CRAIG VAUGHAN |