3905 S WASATCH AVE 90066
Certificate Information: 3905 S WASATCH AVE 90066
- Application / Permit
- 21010-10000-05337
- Plan Check / Job No.
- B21LA19099
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- EPLAN PROPOSED 2-STORY ACCESSORY DWELLING UNIT PER ORDINANCE.
- Permit Issued
- Issued on 4/10/2024
- Issuing Office
- Current Status
- Issued on 4/10/2024
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2021 | MICHAEL LOPEZ |
| Corrections Issued | 11/19/2021 | MICHAEL LOPEZ |
| Quality Review Completed | 11/24/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/24/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 8/8/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 9/8/2022 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 2/17/2023 | MICHAEL LOPEZ |
| Applicant returned to address corrections | 5/12/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 11/1/2023 | MICHAEL LOPEZ |
| No Progress | 11/13/2023 | MICHAEL LOPEZ |
| Plan Check Approved | 11/13/2023 | MICHAEL LOPEZ |
| Issued | 4/10/2024 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 12/14/2021 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 2/17/2022 | JOHN CONNEALLY |
| Construction near power lines | Cleared | 4/11/2022 | RIDWAN HARDY |
| Eng Process Fee Ord 176,300 | Cleared | 6/15/2022 | TREVOR QUAN |
| Sewer availability | Cleared | 6/15/2022 | TREVOR QUAN |
| Roof/Waste drainage to street | Cleared | 6/17/2022 | TREVOR QUAN |
| Specific Plan | Cleared | 6/30/2022 | PEDRO AYALA |
Contact Information
| Architect | Crockett,, Cameron; Lic. No.: NA31503 | , |
| Contractor | Owner-Builder | , |
| Engineer | Adams,, Scott Michael; Lic. No.: C82587 | 5013 MONTAIR LAKEWOOD, CA 90712 |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 4/16/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Sewer | 4/16/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Gas Test | 4/22/2024 | Approved | JESUS RODRIGUEZ |
| Sewer | 4/22/2024 | Approved | JESUS RODRIGUEZ |
| Underground Mechanical | 4/22/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Rough | 7/3/2024 | Partial Approval | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 7/22/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Footing/Foundation/Slab | 7/22/2024 | Corrections Issued | JESUS RODRIGUEZ |
| Excavation/Setback/Form/Re-Bar | 8/8/2024 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 8/8/2024 | Corrections Issued | HERBERT GIRON |
| Excavation/Setback/Form/Re-Bar | 10/24/2024 | Approved | JESUS PINEDA |
| Footing/Foundation/Slab | 10/24/2024 | Partial Approval | JESUS PINEDA |