1265 S WINDSOR BLVD 90019

Certificate Information: 1265 S WINDSOR BLVD 90019

Application / Permit
21010-10000-05333
Plan Check / Job No.
B21LA19086
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Addition to existing garage and convert into a new ADU. The building is under a Mills Act contract and the ADU will maintain it's historic character.
Permit Issued
Issued on 3/23/2022
Issuing Office
Current Status
CofO Issued on 4/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 11/22/2021 APPLICANT
Assigned to Plan Check Engineer 11/24/2021 JOE VO
Corrections Issued 11/25/2021 JOE VO
Applicant returned to address corrections 1/18/2022 JOE VO
Plan Check Approved 3/23/2022 JOE VO
Issued 3/23/2022 APPLICANT
CofO in Progress 4/4/2025 JEFFREY MEAD
Permit Finaled 4/5/2025 DEROLD HAUFF
CofO Issued 4/5/2025 DEROLD HAUFF
Permit Finaled 4/5/2025 DEROLD HAUFF

Permit Application Clearance Information

HPOZ Cleared 1/10/2022 LAMBERT GIESSINGER
Hist. Property Cntrct Mgr Appr Cleared 1/10/2022 LAMBERT GIESSINGER
Historic monument Cleared 1/10/2022 LAMBERT GIESSINGER
Address approval Cleared 1/25/2022 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 1/26/2022 STEVE MELGAR
Sewer availability Cleared 1/26/2022 STEVE MELGAR
Low Impact Development Cleared 3/14/2022 JULIAN SUNG
Roof/Waste drainage to street Cleared 3/15/2022 STEVE MELGAR

Contact Information

Architect Newmark,, Kara Elise; Lic. No.: C29594 1263 SO. WINDSOR BLVD      LOS ANGELES, CA 90019
Contractor Owner-Builder       ,

Inspector Information

JUSTIN HAWLEY, (213) 202-3432 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 9/16/2022 Approved STUART CHAPMAN
PLUMBING-Rough 11/7/2022 Partial Approval STUART CHAPMAN
Underground Mechanical 11/7/2022 Partial Approval STUART CHAPMAN
Footing/Foundation/Slab 11/28/2022 Not Ready for Inspection ALIZAH MAYAGOITIA
Footing/Foundation/Slab 12/5/2022 Partial Inspection FREDDIE RIVERA
Footing/Foundation/Slab 12/9/2022 Not Ready for Inspection MICHAEL LEWIS
Footing/Foundation/Slab 12/13/2022 Not Ready for Inspection CALEB MEISTER
Footing/Foundation/Slab 12/16/2022 Conditional Approval CALEB MEISTER
ELECTRICAL-Rough 4/24/2023 Approved SCOTT FINNILA
Floor/Roof Diaphrgm/Shear Wall 4/24/2023 Partial Approval SCOTT FINNILA
HVAC-Rough 4/24/2023 No Access for Inspection SCOTT FINNILA
PLUMBING-Rough 4/24/2023 Approved SCOTT FINNILA
BUILDING-Rough-Frame 6/1/2023 Partial Approval CALEB MEISTER
Insulation 6/1/2023 Approved CALEB MEISTER
Interior/Exterior Lathing 6/1/2023 Approved CALEB MEISTER
Drywall Nailing 6/29/2023 Approved CALEB MEISTER
Service/Power Release 8/28/2023 Not Ready for Inspection CALEB MEISTER
ELECTRICAL-Final 9/27/2023 Not Ready for Inspection CALEB MEISTER
PLUMBING-Final 9/27/2023 Not Ready for Inspection CALEB MEISTER
Service/Power Release 9/27/2023 Approved CALEB MEISTER
BUILDING-Rough-Frame 11/3/2023 Approved CALEB MEISTER
Final 11/3/2023 Corrections Issued CALEB MEISTER
Green Building Final 11/3/2023 Approved CALEB MEISTER
Green Building Rough 11/3/2023 Approved CALEB MEISTER
METHANE-Final 11/3/2023 Approved CALEB MEISTER
METHANE-Rough 11/3/2023 Approved CALEB MEISTER
SGSOV-Seismic Gas S/O Valve 11/3/2023 SGSOV Approved CALEB MEISTER
Smoke Detectors 11/3/2023 Approved CALEB MEISTER
Final 4/3/2025 OK to Issue CofO JEFFREY MEAD