14238 W LORNE ST 91402
Certificate Information: 14238 W LORNE ST 91402
- Application / Permit
- 21010-10000-05244
- Plan Check / Job No.
- B21LA18900
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- PROPOSED 25' X 33' 1-STORY ACCESSORY DWELLING UNIT PER WFPP PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 1/5/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 9/4/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/18/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 10/19/2021 | LAWRENCE QUIRANTE |
| Building Plans Picked Up | 12/6/2021 | APPLICANT |
| Applicant returned to address corrections | 12/29/2022 | ANGELICA DAVE |
| Applicant returned to address corrections | 1/3/2023 | DANIEL SMILEY |
| Plan Check Approved | 1/4/2023 | JOSEPH RAFOLS |
| Plan Check Approved | 1/4/2023 | JOSEPH RAFOLS |
| Issued | 1/5/2023 | APPLICANT |
| CofO in Progress | 8/19/2025 | JENNIFER RABUCHIN |
| Permit Finaled | 9/4/2025 | RUBEN SALAS |
| CofO Issued | 9/4/2025 | RUBEN SALAS |
| Permit Finaled | 9/4/2025 | RUBEN SALAS |
Permit Application Clearance Information
| Address approval | Cleared | 12/9/2021 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 12/27/2021 | CARLOS AGUILERA |
| Construction near power lines | Cleared | 2/28/2022 | OSCAR CASTRO |
| Sewer availability | Cleared | 12/6/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 12/23/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 12/28/2022 | COLIN LOREDO |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| OGANES TARAKHCHYAN, (818) 374-1162 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Pre-Inspection | 6/17/2024 | Corrections Issued | GREGG CUMMINGS |
| Excavation/Setback/Form/Re-Bar | 7/3/2024 | Approved | VINCENT HANLEY |
| Footing/Foundation/Slab | 7/3/2024 | Partial Approval | VINCENT HANLEY |
| BUILDING-Rough-Frame | 7/10/2024 | Partial Approval | VINCENT HANLEY |
| Insulation | 7/10/2024 | Partial Approval | VINCENT HANLEY |
| PLUMBING-Rough | 7/10/2024 | Partial Approval | VINCENT HANLEY |
| Pre-Inspection | 7/11/2024 | Corrections Issued | VINCENT HANLEY |
| Floor/Roof Diaphrgm/Shear Wall | 7/17/2024 | Corrections Issued | GREGG CUMMINGS |
| Floor/Roof Diaphrgm/Shear Wall | 7/18/2024 | Partial Approval | JACK KARGODORIAN |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 8/13/2024 | Approved | DAVID ANDERSON |
| PLUMBING-Rough | 8/13/2024 | Approved | DAVID ANDERSON |
| Sewer | 8/13/2024 | Approved | DAVID ANDERSON |
| Underground Mechanical | 8/13/2024 | Partial Approval | DAVID ANDERSON |
| ELECTRICAL-Rough | 8/19/2024 | Corrections Issued | GREGG CUMMINGS |
| HVAC-Rough | 8/19/2024 | Corrections Issued | GREGG CUMMINGS |
| Interior/Exterior Lathing | 8/19/2024 | Not Ready for Inspection | GREGG CUMMINGS |
| BUILDING-Rough-Frame | 8/27/2024 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Rough | 8/27/2024 | Approved | VINCENT HANLEY |
| Green Building Rough | 8/27/2024 | Approved | VINCENT HANLEY |
| HVAC-Rough | 8/27/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 8/27/2024 | Partial Approval | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 8/27/2024 | Not Ready for Inspection | VINCENT HANLEY |
| Insulation | 9/5/2024 | Approved | VINCENT HANLEY |
| Drywall Nailing | 9/9/2024 | Approved | VINCENT HANLEY |
| Interior/Exterior Lathing | 9/9/2024 | Approved | VINCENT HANLEY |
| BUILDING-Rough-Frame | 2/19/2025 | Partial Approval | VINCENT HANLEY |
| Final | 2/19/2025 | Corrections Issued | VINCENT HANLEY |
| Footing/Foundation/Slab | 2/19/2025 | Approved | VINCENT HANLEY |
| Green Building Final | 2/19/2025 | Approved | VINCENT HANLEY |
| SGSOV-Seismic Gas S/O Valve | 2/19/2025 | SGSOV Approved | VINCENT HANLEY |
| Service/Power Release | 2/19/2025 | Approved | VINCENT HANLEY |
| Smoke Detectors | 2/19/2025 | Approved | VINCENT HANLEY |
| Verify Sprinkler Sign Off | 2/19/2025 | Not Ready for Inspection | VINCENT HANLEY |
| BUILDING-Rough-Frame | 4/24/2025 | Partial Approval | VINCENT HANLEY |
| ELECTRICAL-Final | 4/24/2025 | Corrections Issued | VINCENT HANLEY |
| Final | 4/24/2025 | Corrections Issued | VINCENT HANLEY |
| HVAC-Final | 4/24/2025 | Corrections Issued | VINCENT HANLEY |
| PLUMBING-Final | 4/24/2025 | Corrections Issued | VINCENT HANLEY |
| BUILDING-Rough-Frame | 5/27/2025 | Approved | VINCENT HANLEY |
| Final | 5/27/2025 | Corrections Issued | VINCENT HANLEY |
| ELECTRICAL-Final | 8/19/2025 | Approved | JENNIFER RABUCHIN |
| Final | 8/19/2025 | OK to Issue CofO | JENNIFER RABUCHIN |
| HVAC-Final | 8/19/2025 | Approved | JENNIFER RABUCHIN |
| PLUMBING-Final | 8/19/2025 | Approved | JENNIFER RABUCHIN |