2824 E MACON ST 90065

Certificate Information: 2824 E MACON ST 90065

Application / Permit
21010-10000-05217
Plan Check / Job No.
B21LA18825
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) Garage to ADU. Per Ordinance 186481
Permit Issued
Issued on 4/28/2022
Issuing Office
Current Status
CofO Issued on 11/9/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/6/2021 APPLICANT
Assigned to Plan Check Engineer 10/8/2021 HERNAN ARREOLA
Corrections Issued 10/11/2021 HERNAN ARREOLA
Plan Check Approved 3/16/2022 HERNAN ARREOLA
Issued 4/28/2022 APPLICANT
CofO in Progress 11/7/2022 OSVALDO PARAMO
CofO in Progress 11/7/2022 OSVALDO PARAMO
Permit Finaled 11/9/2022 DEROLD HAUFF
CofO Issued 11/9/2022 DEROLD HAUFF
Permit Finaled 11/9/2022 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/8/2021 STEVE MELGAR
Sewer availability Cleared 11/8/2021 STEVE MELGAR
Specific Plan Cleared 11/8/2021 NASHYA JENSEN
Eng Process Fee Ord 176,300 Cleared 11/10/2021 STEVE MELGAR
Supp. Use District POD/CDO/TDO Cleared 3/2/2022 NASHYA JENSEN

Contact Information

Contractor Kafe Design & Construction; Lic. No.: 977712-B       ,

Inspector Information

OSVALDO PARAMO, (213) 202-9854 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 5/2/2022 Corrections Issued OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 5/5/2022 Not Ready for Inspection OSVALDO PARAMO
Footing/Foundation/Slab 5/5/2022 Not Ready for Inspection OSVALDO PARAMO
Underground Mechanical 5/5/2022 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 5/11/2022 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 5/11/2022 Not Ready for Inspection OSVALDO PARAMO
Underground Mechanical 5/11/2022 Not Ready for Inspection OSVALDO PARAMO
Excavation/Setback/Form/Re-Bar 5/16/2022 Corrections Issued OSVALDO PARAMO
Footing/Foundation/Slab 5/16/2022 Not Ready for Inspection OSVALDO PARAMO
Underground Mechanical 5/16/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 5/19/2022 Partial Approval OSVALDO PARAMO
Footing/Foundation/Slab 5/27/2022 Partial Approval OSVALDO PARAMO
BUILDING-Rough-Frame 7/1/2022 Corrections Issued OSVALDO PARAMO
ELECTRICAL-Rough 7/1/2022 Approved OSVALDO PARAMO
HVAC-Rough 7/1/2022 Approved OSVALDO PARAMO
PLUMBING-Rough 7/1/2022 Corrections Issued OSVALDO PARAMO
PLUMBING-Rough 7/6/2022 Approved OSVALDO PARAMO
Wood Frame 7/6/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 7/15/2022 Approved OSVALDO PARAMO
Insulation 7/19/2022 Corrections Issued AMY COLIN
Interior/Exterior Lathing 7/19/2022 Approved AMY COLIN
Drywall Nailing 7/25/2022 Approved AMY COLIN
Insulation 7/25/2022 Approved AMY COLIN
Interior/Exterior Lathing 7/25/2022 Approved AMY COLIN
Final 9/8/2022 No Access for Inspection OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 9/8/2022 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 9/8/2022 No Access for Inspection OSVALDO PARAMO
ELECTRICAL-Final 9/13/2022 Not Ready for Inspection OSVALDO PARAMO
HVAC-Final 9/13/2022 Not Ready for Inspection OSVALDO PARAMO
PLUMBING-Final 9/13/2022 Not Ready for Inspection OSVALDO PARAMO
Final 10/17/2022 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 10/17/2022 SGSOV Not Ready OSVALDO PARAMO
Smoke Detectors 10/17/2022 Not Ready for Inspection OSVALDO PARAMO
Final 10/24/2022 Corrections Issued OSVALDO PARAMO
SGSOV-Seismic Gas S/O Valve 10/24/2022 SGSOV Approved OSVALDO PARAMO
Smoke Detectors 10/24/2022 Approved OSVALDO PARAMO
ELECTRICAL-Final 10/28/2022 Approved OSVALDO PARAMO
HVAC-Final 10/28/2022 Approved OSVALDO PARAMO
PLUMBING-Final 10/28/2022 Approved OSVALDO PARAMO
Final 11/4/2022 OK to Issue CofO OSVALDO PARAMO
Service/Power Release 11/4/2022 Approved OSVALDO PARAMO