239 S 6TH AVE 90291

Certificate Information: 239 S 6TH AVE 90291

Application / Permit
21010-10000-05214
Plan Check / Job No.
B21LA18793
Group
Building
Type
Bldg-Alter/Repair
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. CONVERT (E) DETACHED GARAGE AND STORAGE TO AN ACCESSORY DWELLING UNIT PER CA Govt. Code 65852.2(e)(1)(A)
Permit Issued
Issued on 10/31/2022
Issuing Office
Current Status
CofO Issued on 11/29/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/6/2021 APPLICANT
Assigned to Plan Check Engineer 10/8/2021 KEVIN MORALES
Corrections Issued 10/11/2021 KEVIN MORALES
Applicant returned to address corrections 11/1/2021 KEVIN MORALES
Plan Check Approved 8/13/2022 KEVIN MORALES
Issued 10/31/2022 APPLICANT
CofO in Progress 11/27/2023 JESUS RODRIGUEZ
Permit Finaled 11/29/2023 DANIEL ORRANTE
CofO Issued 11/29/2023 DANIEL ORRANTE
Permit Finaled 11/29/2023 DANIEL ORRANTE

Permit Application Clearance Information

Address approval Cleared 10/25/2021 DENNIS BRAGIN
Sewer availability Cleared 10/25/2021 DENNIS BRAGIN
Specific Plan Cleared 10/25/2021 KEVIN ARUCAN
Eng Process Fee Ord 176,300 Cleared 10/26/2021 DENNIS BRAGIN
Coastal Zone Cleared 8/12/2022 MAXFIELD VERMY
Specific Plan Cleared 8/12/2022 MAXFIELD VERMY

Contact Information

Contractor Reuss Enterprises Corporation; Lic. No.: 637751-B 23777 MULHOLAND HWY SPC #15      CALABASAS, CA 91302
Engineer Baad,, Katherine Firestone; Lic. No.: C64669 5232 ZAKON RD      TORRANCE, CA 90505

Inspector Information

RUBEN RIVAS, (310) 914-3981 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 11/10/2022 Corrections Issued DAVID FEILER
PLUMBING-Rough 11/18/2022 Partial Approval DAVID FEILER
Sewer 11/18/2022 Approved DAVID FEILER
Deputy Drilled-In Anchors 12/8/2022 Conditional Approval EVAN COOPER
Footing/Foundation/Slab 12/9/2022 Partial Approval EVAN COOPER
Deputy Drilled-In Anchors 1/30/2023 Conditional Approval EVAN COOPER
ELECTRICAL-Rough 3/29/2023 Partial Approval JESUS RODRIGUEZ
Floor/Roof Diaphrgm/Shear Wall 3/29/2023 Partial Approval JESUS RODRIGUEZ
PLUMBING-Rough 3/29/2023 Partial Approval JESUS RODRIGUEZ
Footing/Foundation/Slab 4/14/2023 Approved EVAN COOPER
BUILDING-Rough-Frame 4/28/2023 Not Ready for Inspection JESUS RODRIGUEZ
ELECTRICAL-Final 4/28/2023 Corrections Issued JESUS RODRIGUEZ
HVAC-Final 4/28/2023 Corrections Issued JESUS RODRIGUEZ
Rough-Elec/Plmb/HVAC 4/28/2023 Approved JESUS RODRIGUEZ
Insulation 5/10/2023 Conditional Approval EVAN COOPER
Drywall Nailing 5/25/2023 Approved EVAN COOPER
HVAC-Rough 5/25/2023 Corrections Issued EVAN COOPER
Interior/Exterior Lathing 5/25/2023 Partial Approval EVAN COOPER
Smoke Detectors 5/25/2023 Corrections Issued EVAN COOPER
Interior/Exterior Lathing 6/23/2023 Approved JESUS RODRIGUEZ
Shower Pan 6/23/2023 Approved JESUS RODRIGUEZ
BUILDING-Rough-Frame 11/8/2023 Approved HERBERT GIRON
ELECTRICAL-Final 11/8/2023 Corrections Issued HERBERT GIRON
HVAC-Final 11/8/2023 Corrections Issued HERBERT GIRON
PLUMBING-Final 11/8/2023 Corrections Issued HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 11/8/2023 SGSOV Not Ready HERBERT GIRON
Smoke Detectors 11/8/2023 Approved HERBERT GIRON
ELECTRICAL-Final 11/17/2023 Corrections Issued HERBERT GIRON
Final 11/17/2023 Corrections Issued HERBERT GIRON
Gas Test 11/17/2023 Approved HERBERT GIRON
HVAC-Final 11/17/2023 Approved HERBERT GIRON
PLUMBING-Final 11/17/2023 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 11/17/2023 SGSOV Approved HERBERT GIRON
ELECTRICAL-Final 11/27/2023 Approved JESUS RODRIGUEZ
Final 11/27/2023 OK to Issue CofO JESUS RODRIGUEZ