4511 S PURDUE AVE 90230
Certificate Information: 4511 S PURDUE AVE 90230
- Application / Permit
- 21010-10000-05213
- Plan Check / Job No.
- B21LA18792
- Group
- Building
- Type
- Bldg-Alter/Repair
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- CONVERT (E) ATTACHED GARAGE TO AN ATTACHED ADU PER STATE LAW
- Permit Issued
- Issued on 3/30/2022
- Issuing Office
- Current Status
- CofO Issued on 7/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/12/2021 | CARLOS MONTES |
| Corrections Issued | 10/15/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 12/14/2021 | CARLOS MONTES |
| Applicant returned to address corrections | 12/21/2021 | CARLOS MONTES |
| Plan Check Approved | 3/25/2022 | CARLOS MONTES |
| Issued | 3/30/2022 | APPLICANT |
| CofO in Progress | 7/10/2024 | RICHARD STEINBACH |
| Permit Finaled | 7/12/2024 | DANIEL ORRANTE |
| CofO Issued | 7/12/2024 | DANIEL ORRANTE |
| Permit Finaled | 7/12/2024 | DANIEL ORRANTE |
Permit Application Clearance Information
| Address approval | Cleared | 10/21/2021 | SAUL GARCIA |
| Eng Process Fee Ord 176,300 | Cleared | 10/21/2021 | SAUL GARCIA |
| Sewer availability | Cleared | 10/21/2021 | SAUL GARCIA |
| Specific Plan | Cleared | 11/10/2021 | VALERIA CEJA |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAKOTA LOW, (310) 914-3895 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Rough-Elec/Plmb/HVAC | 4/22/2022 | No Access for Inspection | PATRICK QUALEY |
| Pre-Inspection | 5/12/2022 | Corrections Issued | BRENDAN LOONEY |
| Pre-Inspection | 6/7/2022 | Partial Inspection | PATRICK QUALEY |
| Footing/Foundation/Slab | 7/22/2022 | Approved | PATRICK QUALEY |
| PLUMBING-Rough | 7/22/2022 | Corrections Issued | PATRICK QUALEY |
| Sewer | 7/22/2022 | Approved | PATRICK QUALEY |
| Shower Pan | 7/22/2022 | Approved | PATRICK QUALEY |
| PLUMBING-Rough | 8/25/2022 | Approved | JESUS RODRIGUEZ |
| Sewer | 8/25/2022 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/4/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Green Building Rough | 1/4/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| MERV13>=Rough | 1/4/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 1/6/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2023 | Partial Approval | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 1/10/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 1/10/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Green Building Rough | 1/10/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Insulation | 1/10/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 1/10/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Insulation | 1/27/2023 | Corrections Issued | EVAN COOPER |
| Interior/Exterior Lathing | 1/27/2023 | Partial Approval | EVAN COOPER |
| Floor/Roof Diaphrgm/Shear Wall | 2/10/2023 | Not Ready for Inspection | HERBERT GIRON |
| Insulation | 2/10/2023 | Not Ready for Inspection | HERBERT GIRON |
| BUILDING-Rough-Frame | 2/15/2023 | Partial Approval | JESUS RODRIGUEZ |
| Drywall Nailing | 2/15/2023 | Not Ready for Inspection | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 2/15/2023 | Approved | JESUS RODRIGUEZ |
| Floor/Roof Diaphrgm/Shear Wall | 2/15/2023 | Approved | JESUS RODRIGUEZ |
| Green Building Rough | 2/15/2023 | Approved | JESUS RODRIGUEZ |
| HVAC-Rough | 2/15/2023 | Approved | JESUS RODRIGUEZ |
| Insulation | 2/15/2023 | Approved | JESUS RODRIGUEZ |
| Interior/Exterior Lathing | 2/15/2023 | Approved | JESUS RODRIGUEZ |
| MERV13>=Rough | 2/15/2023 | Approved | JESUS RODRIGUEZ |
| Drywall Nailing | 3/28/2023 | Approved | JESUS RODRIGUEZ |
| BUILDING-Rough-Frame | 9/5/2023 | Approved | JESUS RODRIGUEZ |
| Final | 9/5/2023 | Corrections Issued | JESUS RODRIGUEZ |
| Green Building Final | 9/5/2023 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 9/5/2023 | SGSOV Not Ready | JESUS RODRIGUEZ |
| Smoke Detectors | 9/5/2023 | Corrections Issued | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 6/7/2024 | SGSOV Not Ready | JESUS RODRIGUEZ |
| ELECTRICAL-Final | 7/2/2024 | Approved | JESUS RODRIGUEZ |
| Final | 7/2/2024 | OK to Issue CofO | JESUS RODRIGUEZ |
| Green Building Final | 7/2/2024 | Approved | JESUS RODRIGUEZ |
| HVAC-Final | 7/2/2024 | Approved | JESUS RODRIGUEZ |
| PLUMBING-Final | 7/2/2024 | Approved | JESUS RODRIGUEZ |
| SGSOV-Seismic Gas S/O Valve | 7/2/2024 | SGSOV Approved | JESUS RODRIGUEZ |
| Service/Power Release | 7/2/2024 | Approved | JESUS RODRIGUEZ |
| Smoke Detectors | 7/2/2024 | Approved | JESUS RODRIGUEZ |