5053 N CHICOPEE AVE 91316
Certificate Information: 5053 N CHICOPEE AVE 91316
- Application / Permit
- 21010-10000-05155
- Plan Check / Job No.
- B21LA18678
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CREATE NEW ADU with attached patio 1 OF 3
- Permit Issued
- Issued on 1/31/2023
- Issuing Office
- Metro
- Current Status
- Issued on 1/31/2023
- Certificate of Occupancy
- Pending More Information
Permit Application Status History
| Submitted | 10/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 11/9/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 11/19/2021 | GARO TELMI |
| Building Plans Picked Up | 11/30/2021 | APPLICANT |
| Plan Check Approved | 1/31/2023 | ARSALAN SHABESTARI |
| Issued | 1/31/2023 | APPLICANT |
Permit Application Clearance Information
| Address approval | Cleared | 2/4/2022 | CARLOS AGUILERA |
| Eng Process Fee Ord 176,300 | Cleared | 2/8/2022 | CARLOS AGUILERA |
| Sewer availability | Cleared | 2/8/2022 | CARLOS AGUILERA |
| Low Impact Development | Cleared | 1/18/2023 | MITESH PATEL |
| Hydrant and Access approval | Cleared | 1/19/2023 | MATTHEW CRAIG |
| Roof/Waste drainage to street | Cleared | 1/24/2023 | AMAAN MALIK |
Contact Information
| Contractor | B C Design And Development Inc; Lic. No.: 1022562-B | P O BOX 1875 STUDIO CITY, CA 91604 |
Inspector Information
| JON MCHUGH, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
| IVAN SARABIA, (818) 774-4348 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 6/29/2023 | Corrections Issued | JON MCHUGH |
| Floor/Roof Diaphrgm/Shear Wall | 6/29/2023 | Partial Approval | JON MCHUGH |
| BUILDING-Rough-Frame | 10/2/2023 | Approved | JON MCHUGH |
| ELECTRICAL-Rough | 10/2/2023 | Approved | JON MCHUGH |
| Final | 10/2/2023 | Corrections Issued | JON MCHUGH |
| Green Building Rough | 10/2/2023 | Approved | JON MCHUGH |
| HVAC-Rough | 10/2/2023 | Approved | JON MCHUGH |
| Verify Sprinkler Sign Off | 10/2/2023 | Approved | JON MCHUGH |
| Drywall Nailing | 10/18/2023 | Approved | VINCENT HANLEY |
| Final | 4/19/2024 | Corrections Issued | JON MCHUGH |
| Footing/Foundation/Slab | 4/19/2024 | Approved | JON MCHUGH |
| Green Building Final | 4/19/2024 | Not Ready for Inspection | JON MCHUGH |
| SGSOV-Seismic Gas S/O Valve | 4/19/2024 | SGSOV Approved | JON MCHUGH |
| Service/Power Release | 4/19/2024 | Not Required | JON MCHUGH |
| Smoke Detectors | 4/19/2024 | Approved | JON MCHUGH |