151 S SALTAIR AVE 90049
Certificate Information: 151 S SALTAIR AVE 90049
- Application / Permit
- 21010-10000-05138
- Plan Check / Job No.
- B21LA18600
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2 STORY SFD WITH BASEMENT GARAGE / HABITABLE SPACE
- Permit Issued
- Issued on 3/28/2023
- Issuing Office
- Valley
- Current Status
- CofO Issued on 2/17/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/9/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/28/2021 | STARR CHEN |
| Corrections Issued | 10/30/2021 | STARR CHEN |
| Quality Review Completed | 11/9/2021 | TEODORO DIAZ RODRIGUEZ |
| Building Plans Picked Up | 11/12/2021 | APPLICANT |
| Applicant returned to address corrections | 2/16/2022 | STARR CHEN |
| Applicant returned to address corrections | 5/10/2022 | STARR CHEN |
| Applicant returned to address corrections | 5/31/2022 | STARR CHEN |
| Applicant returned to address corrections | 7/15/2022 | STARR CHEN |
| Applicant returned to address corrections | 8/16/2022 | STARR CHEN |
| Plan Check Approved | 3/15/2023 | STARR CHEN |
| Issued | 3/28/2023 | APPLICANT |
| CofO in Progress | 2/3/2026 | HERBERT GIRON |
| CofO in Progress | 2/9/2026 | JUAN VALENZUELA |
| CofO in Progress | 2/9/2026 | JUAN VALENZUELA |
| Permit Finaled | 2/17/2026 | RICHARD STEINBACH |
| CofO Issued | 2/17/2026 | RICHARD STEINBACH |
| Permit Finaled | 2/17/2026 | RICHARD STEINBACH |
Permit Application Clearance Information
| Eng Process Fee Ord 176,300 | Cleared | 12/13/2021 | HISASHI KOBAYAKAWA |
| Sewer availability | Cleared | 1/13/2022 | HISASHI KOBAYAKAWA |
| Excavation more than 5-ft deep | Cleared | 2/14/2022 | CALOSHA APPROVED |
| GPI Written Notices | Cleared | 2/16/2022 | STARR CHEN |
| Grading Pre-Inspection | Cleared | 2/16/2022 | STARR CHEN |
| Building over 36-ft | Cleared | 2/22/2022 | CALOSHA APPROVED |
| Specific Plan | Cleared | 2/22/2022 | FREDDY GARCIA |
| Hydrant and Access approval | Cleared | 2/23/2022 | JOHN CONNEALLY |
| Landscape for retaining wall | Cleared | 3/14/2022 | MAYELA VILLA |
| Trees in Parkway | Cleared | 6/30/2022 | ADALBERTO VERA |
| Low Impact Development | Cleared | 10/7/2022 | DEBORA LEITE |
| Permit | Cleared | 11/9/2022 | HISASHI KOBAYAKAWA |
| Roof/Waste drainage to street | Cleared | 11/29/2022 | HISASHI KOBAYAKAWA |
Contact Information
| Contractor | Schebler Construction Inc; Lic. No.: 302595-B | 6700 JULLIARD AVENUE MOORPARK, CA 93021 |
| Engineer | Everard,, Lester George; Lic. No.: L6774 | 5201 CLEMSON ST VENTURA, CA 93003 |
| Engineer | Holt,, Justin Denver; Lic. No.: C71452 | 702 GREENBRIAR AVE SIMI VALLEY, CA 93065 |
| Engineer | Lobana,, Singh Maninder Pa; Lic. No.: C50989 | 885 PATRIOT DR #G MOORPARK, CA 93021 |
| Engineer | Vardeh,, Edmond; Lic. No.: C56992 | 43 INVERARY TRABUCO CANYON, CA 92679 |
| Geologist | Hogrefe,, Scott Joseph; Lic. No.: EG1516 | 3157 ESCOLLERA AVE SANTA ROSA VALLEY, CA 93012 |
Inspector Information
| HERBERT GIRON, (310) 914-3891 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 6/14/2023 | Partial Approval | KENNETH NAGLE |
| Excavation/Setback/Form/Re-Bar | 6/15/2023 | Partial Approval | KENNETH NAGLE |
| Deputy Steel/Welding | 6/22/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 7/7/2023 | Partial Approval | CARLOS MATAMOROS |
| Deputy Steel/Welding | 7/10/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 7/14/2023 | Partial Approval | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 8/7/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 8/24/2023 | Partial Approval | KEVIN SARGSYAN |
| BUILDING-Rough-Frame | 9/8/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Final | 9/8/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Footing/Foundation/Slab | 9/8/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Final | 9/8/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Green Building Rough | 9/8/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Reinforced Concrete Frame | 9/8/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| SGSOV-Seismic Gas S/O Valve | 9/8/2023 | SGSOV Not Ready | CARLOS MATAMOROS |
| Service/Power Release | 9/8/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Smoke Detectors | 9/8/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Structural Steel Frame | 9/8/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 9/8/2023 | Not Ready for Inspection | CARLOS MATAMOROS |
| Deputy Steel/Welding | 9/11/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 9/15/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 9/27/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 10/6/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 10/26/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Deputy Steel/Welding | 11/2/2023 | Partial Approval | OGANES TARAKHCHYAN |
| Footing/Foundation/Slab | 11/9/2023 | No Access for Inspection | OGANES TARAKHCHYAN |
| Excavation/Setback/Form/Re-Bar | 11/15/2023 | Partial Approval | ARAM AVEDISIAN |
| Excavation/Setback/Form/Re-Bar | 11/30/2023 | Corrections Issued | STEPHANIE SWANSON |
| Footing/Foundation/Slab | 11/30/2023 | Not Ready for Inspection | STEPHANIE SWANSON |
| Excavation/Setback/Form/Re-Bar | 12/5/2023 | Conditional Approval | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/14/2023 | Partial Approval | KENNETH NAGLE |
| Floor/Roof Diaphrgm/Shear Wall | 1/23/2024 | Conditional Approval | JESUS RODRIGUEZ |
| Gas Test | 2/16/2024 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 2/16/2024 | Partial Approval | ARAM AVEDISIAN |
| PLUMBING-Rough | 3/18/2024 | Partial Approval | ARAM AVEDISIAN |
| Sewer | 3/18/2024 | Approved | ARAM AVEDISIAN |
| Special/Order Compliance | 3/18/2024 | Partial Approval | ARAM AVEDISIAN |
| Gas Test | 3/22/2024 | Partial Approval | KEVIN SARGSYAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/8/2024 | Corrections Issued | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 4/8/2024 | Corrections Issued | ARAM AVEDISIAN |
| Floor/Roof Diaphrgm/Shear Wall | 4/17/2024 | Partial Approval | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 4/19/2024 | No Access for Inspection | ARAM AVEDISIAN |
| Interior/Exterior Lathing | 5/6/2024 | Partial Approval | CARLOS MATAMOROS |
| Rough-Elec/Plmb/HVAC | 5/13/2024 | Not Ready for Inspection | SEAN HAUPT |
| BUILDING-Rough-Frame | 5/14/2024 | Corrections Issued | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 5/14/2024 | Corrections Issued | CARLOS MATAMOROS |
| Green Building Rough | 5/14/2024 | Not Ready for Inspection | CARLOS MATAMOROS |
| HVAC-Rough | 5/14/2024 | Corrections Issued | CARLOS MATAMOROS |
| Verify Sprinkler Sign Off | 5/14/2024 | Approved | CARLOS MATAMOROS |
| ELECTRICAL-Rough | 5/17/2024 | Approved | ARAM AVEDISIAN |
| HVAC-Rough | 5/17/2024 | Corrections Issued | ARAM AVEDISIAN |
| PLUMBING-Rough | 5/17/2024 | Not Ready for Inspection | ARAM AVEDISIAN |
| BUILDING-Rough-Frame | 5/20/2024 | Partial Approval | ARAM AVEDISIAN |
| Green Building Rough | 5/20/2024 | Approved | ARAM AVEDISIAN |
| Rough-Elec/Plmb/HVAC | 5/20/2024 | Approved | ARAM AVEDISIAN |
| Insulation | 5/22/2024 | Approved | ARAM AVEDISIAN |
| Drywall Nailing | 5/29/2024 | Partial Approval | KIRK SANDERS |
| Interior/Exterior Lathing | 6/17/2024 | Corrections Issued | ARAM AVEDISIAN |
| ELECTRICAL-Final | 12/6/2024 | Not Ready for Inspection | JESUS RODRIGUEZ |
| Shower Pan | 12/6/2024 | Approved | JESUS RODRIGUEZ |
| ELECTRICAL-Rough | 3/28/2025 | Conditional Approval | HERBERT GIRON |
| ELECTRICAL-Final | 3/29/2025 | Corrections Issued | CHRISTOPHER WILSON |
| ELECTRICAL-Final | 4/17/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 7/16/2025 | Not Ready for Inspection | HAMIK HARTOUNIAN |
| ELECTRICAL-Final | 7/18/2025 | Not Ready for Inspection | STEPHANIE SWANSON |
| PLUMBING-Final | 12/10/2025 | Corrections Issued | HERBERT GIRON |
| HVAC-Final | 12/16/2025 | Corrections Issued | HERBERT GIRON |
| ELECTRICAL-Final | 12/19/2025 | Approved | HERBERT GIRON |
| HVAC-Final | 12/19/2025 | Approved | HERBERT GIRON |
| Pre-Inspection | 1/6/2026 | Partial Inspection | HERBERT GIRON |
| Gas Test | 1/8/2026 | Approved | HERBERT GIRON |
| PLUMBING-Final | 1/8/2026 | Approved | HERBERT GIRON |
| BUILDING-Rough-Frame | 1/29/2026 | Approved | HERBERT GIRON |
| Final | 1/29/2026 | Corrections Issued | HERBERT GIRON |
| Footing/Foundation/Slab | 1/29/2026 | Approved | HERBERT GIRON |
| Green Building Final | 1/29/2026 | Approved | HERBERT GIRON |
| Reinforced Concrete Frame | 1/29/2026 | Approved | HERBERT GIRON |
| SGSOV-Seismic Gas S/O Valve | 1/29/2026 | SGSOV Approved | HERBERT GIRON |
| Smoke Detectors | 1/29/2026 | Approved | HERBERT GIRON |
| Structural Steel Frame | 1/29/2026 | Approved | HERBERT GIRON |
| Final | 2/3/2026 | OK to Issue CofO | HERBERT GIRON |
| Service/Power Release | 2/3/2026 | Approved | HERBERT GIRON |