151 S SALTAIR AVE 90049

Certificate Information: 151 S SALTAIR AVE 90049

Application / Permit
21010-10000-05138
Plan Check / Job No.
B21LA18600
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
NEW 2 STORY SFD WITH BASEMENT GARAGE / HABITABLE SPACE
Permit Issued
Issued on 3/28/2023
Issuing Office
Valley
Current Status
CofO Issued on 2/17/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/9/2021 APPLICANT
Assigned to Plan Check Engineer 10/28/2021 STARR CHEN
Corrections Issued 10/30/2021 STARR CHEN
Quality Review Completed 11/9/2021 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 11/12/2021 APPLICANT
Applicant returned to address corrections 2/16/2022 STARR CHEN
Applicant returned to address corrections 5/10/2022 STARR CHEN
Applicant returned to address corrections 5/31/2022 STARR CHEN
Applicant returned to address corrections 7/15/2022 STARR CHEN
Applicant returned to address corrections 8/16/2022 STARR CHEN
Plan Check Approved 3/15/2023 STARR CHEN
Issued 3/28/2023 APPLICANT
CofO in Progress 2/3/2026 HERBERT GIRON
CofO in Progress 2/9/2026 JUAN VALENZUELA
CofO in Progress 2/9/2026 JUAN VALENZUELA
Permit Finaled 2/17/2026 RICHARD STEINBACH
CofO Issued 2/17/2026 RICHARD STEINBACH
Permit Finaled 2/17/2026 RICHARD STEINBACH

Permit Application Clearance Information

Eng Process Fee Ord 176,300 Cleared 12/13/2021 HISASHI KOBAYAKAWA
Sewer availability Cleared 1/13/2022 HISASHI KOBAYAKAWA
Excavation more than 5-ft deep Cleared 2/14/2022 CALOSHA APPROVED
GPI Written Notices Cleared 2/16/2022 STARR CHEN
Grading Pre-Inspection Cleared 2/16/2022 STARR CHEN
Building over 36-ft Cleared 2/22/2022 CALOSHA APPROVED
Specific Plan Cleared 2/22/2022 FREDDY GARCIA
Hydrant and Access approval Cleared 2/23/2022 JOHN CONNEALLY
Landscape for retaining wall Cleared 3/14/2022 MAYELA VILLA
Trees in Parkway Cleared 6/30/2022 ADALBERTO VERA
Low Impact Development Cleared 10/7/2022 DEBORA LEITE
Permit Cleared 11/9/2022 HISASHI KOBAYAKAWA
Roof/Waste drainage to street Cleared 11/29/2022 HISASHI KOBAYAKAWA

Contact Information

Contractor Schebler Construction Inc; Lic. No.: 302595-B 6700 JULLIARD AVENUE      MOORPARK, CA 93021
Engineer Everard,, Lester George; Lic. No.: L6774 5201 CLEMSON ST      VENTURA, CA 93003
Engineer Holt,, Justin Denver; Lic. No.: C71452 702 GREENBRIAR AVE      SIMI VALLEY, CA 93065
Engineer Lobana,, Singh Maninder Pa; Lic. No.: C50989 885 PATRIOT DR #G      MOORPARK, CA 93021
Engineer Vardeh,, Edmond; Lic. No.: C56992 43 INVERARY      TRABUCO CANYON, CA 92679
Geologist Hogrefe,, Scott Joseph; Lic. No.: EG1516 3157 ESCOLLERA AVE      SANTA ROSA VALLEY, CA 93012

Inspector Information

HERBERT GIRON, (310) 914-3891 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

PLUMBING-Rough 6/14/2023 Partial Approval KENNETH NAGLE
Excavation/Setback/Form/Re-Bar 6/15/2023 Partial Approval KENNETH NAGLE
Deputy Steel/Welding 6/22/2023 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 7/7/2023 Partial Approval CARLOS MATAMOROS
Deputy Steel/Welding 7/10/2023 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 7/14/2023 Partial Approval CARLOS MATAMOROS
Footing/Foundation/Slab 8/7/2023 Partial Approval OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 8/24/2023 Partial Approval KEVIN SARGSYAN
BUILDING-Rough-Frame 9/8/2023 Not Ready for Inspection CARLOS MATAMOROS
Final 9/8/2023 Not Ready for Inspection CARLOS MATAMOROS
Footing/Foundation/Slab 9/8/2023 Not Ready for Inspection CARLOS MATAMOROS
Green Building Final 9/8/2023 Not Ready for Inspection CARLOS MATAMOROS
Green Building Rough 9/8/2023 Not Ready for Inspection CARLOS MATAMOROS
Reinforced Concrete Frame 9/8/2023 Not Ready for Inspection CARLOS MATAMOROS
SGSOV-Seismic Gas S/O Valve 9/8/2023 SGSOV Not Ready CARLOS MATAMOROS
Service/Power Release 9/8/2023 Not Ready for Inspection CARLOS MATAMOROS
Smoke Detectors 9/8/2023 Not Ready for Inspection CARLOS MATAMOROS
Structural Steel Frame 9/8/2023 Not Ready for Inspection CARLOS MATAMOROS
Verify Sprinkler Sign Off 9/8/2023 Not Ready for Inspection CARLOS MATAMOROS
Deputy Steel/Welding 9/11/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Steel/Welding 9/15/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Steel/Welding 9/27/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Steel/Welding 10/6/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 10/26/2023 Partial Approval OGANES TARAKHCHYAN
Deputy Steel/Welding 11/2/2023 Partial Approval OGANES TARAKHCHYAN
Footing/Foundation/Slab 11/9/2023 No Access for Inspection OGANES TARAKHCHYAN
Excavation/Setback/Form/Re-Bar 11/15/2023 Partial Approval ARAM AVEDISIAN
Excavation/Setback/Form/Re-Bar 11/30/2023 Corrections Issued STEPHANIE SWANSON
Footing/Foundation/Slab 11/30/2023 Not Ready for Inspection STEPHANIE SWANSON
Excavation/Setback/Form/Re-Bar 12/5/2023 Conditional Approval ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 12/14/2023 Partial Approval KENNETH NAGLE
Floor/Roof Diaphrgm/Shear Wall 1/23/2024 Conditional Approval JESUS RODRIGUEZ
Gas Test 2/16/2024 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 2/16/2024 Partial Approval ARAM AVEDISIAN
PLUMBING-Rough 3/18/2024 Partial Approval ARAM AVEDISIAN
Sewer 3/18/2024 Approved ARAM AVEDISIAN
Special/Order Compliance 3/18/2024 Partial Approval ARAM AVEDISIAN
Gas Test 3/22/2024 Partial Approval KEVIN SARGSYAN
Floor/Roof Diaphrgm/Shear Wall 4/8/2024 Corrections Issued ARAM AVEDISIAN
Rough-Elec/Plmb/HVAC 4/8/2024 Corrections Issued ARAM AVEDISIAN
Floor/Roof Diaphrgm/Shear Wall 4/17/2024 Partial Approval ARAM AVEDISIAN
BUILDING-Rough-Frame 4/19/2024 No Access for Inspection ARAM AVEDISIAN
Interior/Exterior Lathing 5/6/2024 Partial Approval CARLOS MATAMOROS
Rough-Elec/Plmb/HVAC 5/13/2024 Not Ready for Inspection SEAN HAUPT
BUILDING-Rough-Frame 5/14/2024 Corrections Issued CARLOS MATAMOROS
ELECTRICAL-Rough 5/14/2024 Corrections Issued CARLOS MATAMOROS
Green Building Rough 5/14/2024 Not Ready for Inspection CARLOS MATAMOROS
HVAC-Rough 5/14/2024 Corrections Issued CARLOS MATAMOROS
Verify Sprinkler Sign Off 5/14/2024 Approved CARLOS MATAMOROS
ELECTRICAL-Rough 5/17/2024 Approved ARAM AVEDISIAN
HVAC-Rough 5/17/2024 Corrections Issued ARAM AVEDISIAN
PLUMBING-Rough 5/17/2024 Not Ready for Inspection ARAM AVEDISIAN
BUILDING-Rough-Frame 5/20/2024 Partial Approval ARAM AVEDISIAN
Green Building Rough 5/20/2024 Approved ARAM AVEDISIAN
Rough-Elec/Plmb/HVAC 5/20/2024 Approved ARAM AVEDISIAN
Insulation 5/22/2024 Approved ARAM AVEDISIAN
Drywall Nailing 5/29/2024 Partial Approval KIRK SANDERS
Interior/Exterior Lathing 6/17/2024 Corrections Issued ARAM AVEDISIAN
ELECTRICAL-Final 12/6/2024 Not Ready for Inspection JESUS RODRIGUEZ
Shower Pan 12/6/2024 Approved JESUS RODRIGUEZ
ELECTRICAL-Rough 3/28/2025 Conditional Approval HERBERT GIRON
ELECTRICAL-Final 3/29/2025 Corrections Issued CHRISTOPHER WILSON
ELECTRICAL-Final 4/17/2025 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 7/16/2025 Not Ready for Inspection HAMIK HARTOUNIAN
ELECTRICAL-Final 7/18/2025 Not Ready for Inspection STEPHANIE SWANSON
PLUMBING-Final 12/10/2025 Corrections Issued HERBERT GIRON
HVAC-Final 12/16/2025 Corrections Issued HERBERT GIRON
ELECTRICAL-Final 12/19/2025 Approved HERBERT GIRON
HVAC-Final 12/19/2025 Approved HERBERT GIRON
Pre-Inspection 1/6/2026 Partial Inspection HERBERT GIRON
Gas Test 1/8/2026 Approved HERBERT GIRON
PLUMBING-Final 1/8/2026 Approved HERBERT GIRON
BUILDING-Rough-Frame 1/29/2026 Approved HERBERT GIRON
Final 1/29/2026 Corrections Issued HERBERT GIRON
Footing/Foundation/Slab 1/29/2026 Approved HERBERT GIRON
Green Building Final 1/29/2026 Approved HERBERT GIRON
Reinforced Concrete Frame 1/29/2026 Approved HERBERT GIRON
SGSOV-Seismic Gas S/O Valve 1/29/2026 SGSOV Approved HERBERT GIRON
Smoke Detectors 1/29/2026 Approved HERBERT GIRON
Structural Steel Frame 1/29/2026 Approved HERBERT GIRON
Final 2/3/2026 OK to Issue CofO HERBERT GIRON
Service/Power Release 2/3/2026 Approved HERBERT GIRON