815 N GENESEE AVE 90046

Certificate Information: 815 N GENESEE AVE 90046

Application / Permit
21010-10000-05137
Plan Check / Job No.
B21LA18582
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3-STORY SINGLE FAMILY DWELLING WITH ATTACHED 2-CAR GARAGE
Permit Issued
Issued on 4/13/2022
Issuing Office
Current Status
CofO Issued on 2/23/2026
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 DANIEL YIP
Corrections Issued 10/26/2021 DANIEL YIP
Quality Review Completed 11/5/2021 TEODORO DIAZ RODRIGUEZ
Applicant returned to address corrections 12/15/2021 DANIEL YIP
Plan Check Approved 2/22/2022 DANIEL YIP
Issued 4/13/2022 APPLICANT
Building Plans Picked Up 5/3/2022 APPLICANT
CofO in Progress 2/17/2026 JOSH MEISTER
Permit Finaled 2/23/2026 DEROLD HAUFF
CofO Issued 2/23/2026 DEROLD HAUFF
Permit Finaled 2/23/2026 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/19/2021 CELINA MORENO
Permit Cleared 11/19/2021 CELINA MORENO
Eng Process Fee Ord 176,300 Cleared 11/29/2021 CELINA MORENO
Low Impact Development Cleared 1/31/2022 ANTHONY VARGAS
Roof/Waste drainage to street Cleared 2/7/2022 CELINA MORENO
Sewer availability Cleared 2/7/2022 CELINA MORENO
Hydrant and Access approval Cleared 2/14/2022 JOHN CONNEALLY

Contact Information

Contractor Owner-Builder       ,

Inspector Information

JOSE MACIAS, (213) 202-3125 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 8/15/2023 Partial Inspection LILIANA PORTILLO
PLUMBING-Rough 12/5/2023 Partial Approval LILIANA PORTILLO
Sewer 12/14/2023 Approved LILIANA PORTILLO
Structural Steel Frame 12/20/2023 Partial Approval LILIANA PORTILLO
Footing/Foundation/Slab 1/9/2024 Not Ready for Inspection JOAQUIN GREENOUGH
Footing/Foundation/Slab 1/16/2024 Approved LILIANA PORTILLO
Floor/Roof Diaphrgm/Shear Wall 3/5/2024 Partial Approval AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 4/4/2024 Partial Approval AMIR NAZARIAN
PLUMBING-Rough 5/14/2024 Not Ready for Inspection AMIR NAZARIAN
Underground Mechanical 5/14/2024 Corrections Issued AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 6/5/2024 Corrections Issued AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 6/13/2024 Partial Approval AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 7/2/2024 Corrections Issued AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 7/5/2024 Corrections Issued AMIR NAZARIAN
HVAC-Rough 8/1/2024 Not Ready for Inspection AMIR NAZARIAN
Floor/Roof Diaphrgm/Shear Wall 8/2/2024 Approved AMIR NAZARIAN
HVAC-Rough 8/6/2024 Not Ready for Inspection AMIR NAZARIAN
ELECTRICAL-Rough 8/21/2024 Corrections Issued AMIR NAZARIAN
ELECTRICAL-Rough 8/26/2024 Approved BRENDAN MORELLI
PLUMBING-Rough 9/27/2024 Conditional Approval JOSE MACIAS
Shower Pan 10/1/2024 Approved JOSE MACIAS
PLUMBING-Rough 10/18/2024 Approved JOSE MACIAS
HVAC-Rough 10/30/2024 Corrections Issued JOSE MACIAS
Interior/Exterior Lathing 11/15/2024 Approved JOSE MACIAS
HVAC-Rough 11/18/2024 Approved JOSE MACIAS
BUILDING-Rough-Frame 11/21/2024 Approved JOSE MACIAS
Green Building Rough 11/21/2024 Approved JOSE MACIAS
Verify Sprinkler Sign Off 11/21/2024 Approved JOSE MACIAS
Insulation 12/3/2024 Approved JOSE MACIAS
Underground Mechanical 4/30/2025 Approved WAYNE REGESTER
Masonry Wall/Backfill 7/3/2025 Approved JOSE MACIAS
ELECTRICAL-Final 8/26/2025 Approved ALIZAH MAYAGOITIA
Service/Power Release 10/9/2025 Approved RAUL BARAJAS
Drywall Nailing 2/4/2026 Not Ready for Inspection JOSH MEISTER
Final 2/4/2026 Not Ready for Inspection JOSH MEISTER
Green Building Final 2/4/2026 Not Ready for Inspection JOSH MEISTER
SGSOV-Seismic Gas S/O Valve 2/4/2026 SGSOV Not Ready JOSH MEISTER
Smoke Detectors 2/4/2026 Not Ready for Inspection JOSH MEISTER
Drywall Nailing 2/6/2026 Approved JOSH MEISTER
Final 2/6/2026 Not Ready for Inspection JOSH MEISTER
Green Building Final 2/6/2026 Not Ready for Inspection JOSH MEISTER
SGSOV-Seismic Gas S/O Valve 2/6/2026 SGSOV Not Ready JOSH MEISTER
Smoke Detectors 2/6/2026 Not Ready for Inspection JOSH MEISTER
Final 2/11/2026 OK to Issue CofO JOSH MEISTER
Green Building Final 2/11/2026 Approved JOSH MEISTER
SGSOV-Seismic Gas S/O Valve 2/11/2026 SGSOV Approved JOSH MEISTER
Smoke Detectors 2/11/2026 Approved JOSH MEISTER