2238 W EWING ST 90039

Certificate Information: 2238 W EWING ST 90039

Application / Permit
21010-10000-05132
Plan Check / Job No.
B21LA18564
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePlan PROPOSED DETACHED ACCESSORY DWELLING UNIT PER STATE LAW GCS 65852.2(e)(1)(B).
Permit Issued
Issued on 3/8/2022
Issuing Office
Current Status
CofO Issued on 8/20/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/4/2021 APPLICANT
Assigned to Plan Check Engineer 10/7/2021 MICHAEL LOPEZ
Corrections Issued 10/8/2021 MICHAEL LOPEZ
Applicant returned to address corrections 1/11/2022 MICHAEL LOPEZ
Applicant returned to address corrections 1/28/2022 MICHAEL LOPEZ
Applicant returned to address corrections 2/8/2022 MICHAEL LOPEZ
Plan Check Approved 3/1/2022 SEAN DANG
Issued 3/8/2022 APPLICANT
CofO in Progress 8/1/2022 THOMAS LOGRASSO
Permit Finaled 8/20/2022 DEROLD HAUFF
CofO Issued 8/20/2022 DEROLD HAUFF
Permit Finaled 8/20/2022 DEROLD HAUFF

Permit Application Clearance Information

BHO/Hillside ordinance Cleared 10/18/2021 STEVE MELGAR
Eng Process Fee Ord 176,300 Cleared 10/19/2021 STEVE MELGAR
Sewer availability Cleared 10/19/2021 STEVE MELGAR
Address approval Cleared 10/25/2021 STEVE MELGAR
Grading Pre-Inspection Cleared 10/26/2021 PATRICK MISCHLICH
Hydrant and Access approval Cleared 1/11/2022 KURT CORRAL
Low Impact Development Cleared 1/20/2022 TA ANH
Roof/Waste drainage to street Cleared 1/27/2022 STEVE MELGAR

Contact Information

Contractor Owner-Builder       ,

Inspector Information

HAMIK HARTOUNIAN, (213) 202-3275 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/10/2022 Partial Inspection THOMAS LOGRASSO
PLUMBING-Rough 3/23/2022 Partial Approval THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 4/8/2022 Not Ready for Inspection THOMAS LOGRASSO
Excavation/Setback/Form/Re-Bar 4/13/2022 Partial Approval THOMAS LOGRASSO
Footing/Foundation/Slab 4/27/2022 Approved THOMAS LOGRASSO
Underground Mechanical 5/9/2022 Partial Approval THOMAS LOGRASSO
Floor/Roof Diaphrgm/Shear Wall 5/13/2022 Partial Inspection THOMAS LOGRASSO
MERV13>=Rough 5/13/2022 Not Ready for Inspection THOMAS LOGRASSO
Verify Sprinkler Sign Off 5/13/2022 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 5/19/2022 Corrections Issued THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 5/19/2022 Corrections Issued THOMAS LOGRASSO
Rough-Elec/Plmb/HVAC 5/27/2022 Partial Approval THOMAS LOGRASSO
Wood Frame 5/27/2022 Partial Approval THOMAS LOGRASSO
Insulation 6/6/2022 Conditional Approval THOMAS LOGRASSO
Drywall Nailing 6/13/2022 Conditional Approval THOMAS LOGRASSO
PLUMBING-Final 7/1/2022 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 7/20/2022 Conditional Approval THOMAS LOGRASSO
Drywall Nailing 7/20/2022 Approved THOMAS LOGRASSO
Final 7/20/2022 Partial Inspection THOMAS LOGRASSO
SGSOV-Seismic Gas S/O Valve 7/20/2022 SGSOV Approved THOMAS LOGRASSO
Service/Power Release 7/20/2022 Not Required THOMAS LOGRASSO
Smoke Detectors 7/20/2022 Approved THOMAS LOGRASSO
Final 7/22/2022 Corrections Issued THOMAS LOGRASSO
Final 7/26/2022 Not Ready for Inspection THOMAS LOGRASSO
BUILDING-Rough-Frame 8/1/2022 Approved THOMAS LOGRASSO
Final 8/1/2022 OK to Issue CofO THOMAS LOGRASSO