5864 W FOOTHILL DR 90068
Certificate Information: 5864 W FOOTHILL DR 90068
- Application / Permit
- 21010-10000-05130
- Plan Check / Job No.
- B21LA18549
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED TWO-STORY BUILDING WITH ACCESSORY DWELLING UNIT BELOW AND A RECREATION ROOM ABOVE. PER DETACHED ADU ORDINANCE
- Permit Issued
- Issued on 4/26/2022
- Issuing Office
- Current Status
- CofO Issued on 10/2/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/1/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | CARLOS MONTES |
| Corrections Issued | 11/9/2021 | CARLOS MONTES |
| Quality Review Completed | 11/10/2021 | KEN GILL |
| Applicant returned to address corrections | 3/7/2022 | CARLOS MONTES |
| Plan Check Approved | 3/25/2022 | CARLOS MONTES |
| Building Plans Picked Up | 3/29/2022 | APPLICANT |
| Issued | 4/26/2022 | APPLICANT |
| Intent to Revoke-Status Void | 5/12/2022 | CHARMIE HUYNH |
| Re-Activate Permit | 5/23/2022 | CHARMIE HUYNH |
| CofO in Progress | 9/30/2023 | JOAQUIN GREENOUGH |
| Permit Finaled | 10/2/2023 | DEROLD HAUFF |
| CofO Issued | 10/2/2023 | DEROLD HAUFF |
| Permit Finaled | 10/2/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/1/2021 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 12/2/2021 | AMAAN MALIK |
| Sewer availability | Cleared | 12/2/2021 | AMAAN MALIK |
| Tenant Habitability Plan | Cleared | 12/2/2021 | GABRIEL RETA |
| Watercourse | Cleared | 12/2/2021 | TERRY PHAN |
| Low Impact Development | Cleared | 2/22/2022 | MARCO SANCHEZ |
| GPI Written Notices | Cleared | 3/17/2022 | CARLOS MONTES |
| Grading Pre-Inspection | Cleared | 3/17/2022 | CARLOS MONTES |
| Roof/Waste drainage to street | Cleared | 3/22/2022 | AMAAN MALIK |
Contact Information
| Contractor | Lightning Construction & Design Inc; Lic. No.: 951122-B | 6047 TAMPA AVE #303 TARZANA, CA 91356 |
| Engineer | Phillips,, Craig Richard; Lic. No.: C69673 | 2123 VESTAL AVE LOS ANGELES, CA 90026 |
Inspector Information
| CRAIG VAUGHAN, (213) 202-3250 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 4/28/2022 | Partial Approval | SCOTT FINNILA |
| Underground Mechanical | 4/28/2022 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 5/9/2022 | Corrections Issued | JOSEPH MCGARRY |
| Footing/Foundation/Slab | 5/12/2022 | Not Ready for Inspection | BRIAN SULLIVAN |
| Floor/Roof Diaphrgm/Shear Wall | 6/10/2022 | Partial Approval | SCOTT FINNILA |
| Footing/Foundation/Slab | 6/10/2022 | Approved | SCOTT FINNILA |
| Wood Frame | 7/18/2022 | Partial Approval | STUART CHAPMAN |
| Deputy Wood Construction | 7/20/2022 | Conditional Approval | BRIAN SULLIVAN |
| ELECTRICAL-Rough | 9/6/2022 | Approved | JOAQUIN GREENOUGH |
| HVAC-Rough | 9/6/2022 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Rough | 9/6/2022 | Approved | JOAQUIN GREENOUGH |
| Sewer | 9/6/2022 | Approved | JOAQUIN GREENOUGH |
| Underground Mechanical | 9/6/2022 | Approved | JOAQUIN GREENOUGH |
| Wood Frame | 9/6/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 9/9/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Insulation | 11/3/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 11/3/2022 | Partial Approval | JOAQUIN GREENOUGH |
| HVAC-Rough | 11/18/2022 | Approved | JOAQUIN GREENOUGH |
| Insulation | 11/18/2022 | Approved | JOAQUIN GREENOUGH |
| BUILDING-Rough-Frame | 12/5/2022 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 12/5/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 12/5/2022 | Approved | JOAQUIN GREENOUGH |
| Verify Sprinkler Sign Off | 12/5/2022 | Approved | JOAQUIN GREENOUGH |
| Wood Frame | 12/5/2022 | Approved | JOAQUIN GREENOUGH |
| Drywall Nailing | 12/9/2022 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 12/9/2022 | Partial Approval | JOAQUIN GREENOUGH |
| Shower Pan | 12/27/2022 | Approved | RUBEN SALAS |
| Interior/Exterior Lathing | 1/3/2023 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 6/29/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 6/29/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Final | 6/29/2023 | Approved | JOAQUIN GREENOUGH |
| HVAC-Final | 6/29/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| PLUMBING-Final | 6/29/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 6/29/2023 | SGSOV Not Ready | JOAQUIN GREENOUGH |
| Service/Power Release | 6/29/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Smoke Detectors | 6/29/2023 | Approved | JOAQUIN GREENOUGH |
| ELECTRICAL-Final | 8/11/2023 | Approved | JOAQUIN GREENOUGH |
| Final | 8/11/2023 | Corrections Issued | JOAQUIN GREENOUGH |
| HVAC-Final | 8/11/2023 | Approved | JOAQUIN GREENOUGH |
| PLUMBING-Final | 8/11/2023 | Approved | JOAQUIN GREENOUGH |
| SGSOV-Seismic Gas S/O Valve | 8/11/2023 | SGSOV Approved | JOAQUIN GREENOUGH |
| Service/Power Release | 8/11/2023 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Final | 9/25/2023 | Partial Inspection | JOAQUIN GREENOUGH |
| Service/Power Release | 9/25/2023 | Not Required | JOAQUIN GREENOUGH |
| Final | 9/30/2023 | OK to Issue CofO | JOAQUIN GREENOUGH |