5864 W FOOTHILL DR 90068

Certificate Information: 5864 W FOOTHILL DR 90068

Application / Permit
21010-10000-05130
Plan Check / Job No.
B21LA18549
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED TWO-STORY BUILDING WITH ACCESSORY DWELLING UNIT BELOW AND A RECREATION ROOM ABOVE. PER DETACHED ADU ORDINANCE
Permit Issued
Issued on 4/26/2022
Issuing Office
Current Status
CofO Issued on 10/2/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2021 APPLICANT
Assigned to Plan Check Engineer 11/4/2021 CARLOS MONTES
Corrections Issued 11/9/2021 CARLOS MONTES
Quality Review Completed 11/10/2021 KEN GILL
Applicant returned to address corrections 3/7/2022 CARLOS MONTES
Plan Check Approved 3/25/2022 CARLOS MONTES
Building Plans Picked Up 3/29/2022 APPLICANT
Issued 4/26/2022 APPLICANT
Intent to Revoke-Status Void 5/12/2022 CHARMIE HUYNH
Re-Activate Permit 5/23/2022 CHARMIE HUYNH
CofO in Progress 9/30/2023 JOAQUIN GREENOUGH
Permit Finaled 10/2/2023 DEROLD HAUFF
CofO Issued 10/2/2023 DEROLD HAUFF
Permit Finaled 10/2/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/1/2021 AMAAN MALIK
Eng Process Fee Ord 176,300 Cleared 12/2/2021 AMAAN MALIK
Sewer availability Cleared 12/2/2021 AMAAN MALIK
Tenant Habitability Plan Cleared 12/2/2021 GABRIEL RETA
Watercourse Cleared 12/2/2021 TERRY PHAN
Low Impact Development Cleared 2/22/2022 MARCO SANCHEZ
GPI Written Notices Cleared 3/17/2022 CARLOS MONTES
Grading Pre-Inspection Cleared 3/17/2022 CARLOS MONTES
Roof/Waste drainage to street Cleared 3/22/2022 AMAAN MALIK

Contact Information

Contractor Lightning Construction & Design Inc; Lic. No.: 951122-B 6047 TAMPA AVE #303      TARZANA, CA 91356
Engineer Phillips,, Craig Richard; Lic. No.: C69673 2123 VESTAL AVE      LOS ANGELES, CA 90026

Inspector Information

CRAIG VAUGHAN, (213) 202-3250 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 4/28/2022 Partial Approval SCOTT FINNILA
Underground Mechanical 4/28/2022 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 5/9/2022 Corrections Issued JOSEPH MCGARRY
Footing/Foundation/Slab 5/12/2022 Not Ready for Inspection BRIAN SULLIVAN
Floor/Roof Diaphrgm/Shear Wall 6/10/2022 Partial Approval SCOTT FINNILA
Footing/Foundation/Slab 6/10/2022 Approved SCOTT FINNILA
Wood Frame 7/18/2022 Partial Approval STUART CHAPMAN
Deputy Wood Construction 7/20/2022 Conditional Approval BRIAN SULLIVAN
ELECTRICAL-Rough 9/6/2022 Approved JOAQUIN GREENOUGH
HVAC-Rough 9/6/2022 Approved JOAQUIN GREENOUGH
PLUMBING-Rough 9/6/2022 Approved JOAQUIN GREENOUGH
Sewer 9/6/2022 Approved JOAQUIN GREENOUGH
Underground Mechanical 9/6/2022 Approved JOAQUIN GREENOUGH
Wood Frame 9/6/2022 Not Ready for Inspection JOAQUIN GREENOUGH
BUILDING-Rough-Frame 9/9/2022 Conditional Approval JOAQUIN GREENOUGH
Insulation 11/3/2022 Corrections Issued JOAQUIN GREENOUGH
Interior/Exterior Lathing 11/3/2022 Partial Approval JOAQUIN GREENOUGH
HVAC-Rough 11/18/2022 Approved JOAQUIN GREENOUGH
Insulation 11/18/2022 Approved JOAQUIN GREENOUGH
BUILDING-Rough-Frame 12/5/2022 Approved JOAQUIN GREENOUGH
Drywall Nailing 12/5/2022 Corrections Issued JOAQUIN GREENOUGH
Green Building Rough 12/5/2022 Approved JOAQUIN GREENOUGH
Verify Sprinkler Sign Off 12/5/2022 Approved JOAQUIN GREENOUGH
Wood Frame 12/5/2022 Approved JOAQUIN GREENOUGH
Drywall Nailing 12/9/2022 Approved JOAQUIN GREENOUGH
Interior/Exterior Lathing 12/9/2022 Partial Approval JOAQUIN GREENOUGH
Shower Pan 12/27/2022 Approved RUBEN SALAS
Interior/Exterior Lathing 1/3/2023 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 6/29/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Final 6/29/2023 Corrections Issued JOAQUIN GREENOUGH
Green Building Final 6/29/2023 Approved JOAQUIN GREENOUGH
HVAC-Final 6/29/2023 Not Ready for Inspection JOAQUIN GREENOUGH
PLUMBING-Final 6/29/2023 Not Ready for Inspection JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 6/29/2023 SGSOV Not Ready JOAQUIN GREENOUGH
Service/Power Release 6/29/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Smoke Detectors 6/29/2023 Approved JOAQUIN GREENOUGH
ELECTRICAL-Final 8/11/2023 Approved JOAQUIN GREENOUGH
Final 8/11/2023 Corrections Issued JOAQUIN GREENOUGH
HVAC-Final 8/11/2023 Approved JOAQUIN GREENOUGH
PLUMBING-Final 8/11/2023 Approved JOAQUIN GREENOUGH
SGSOV-Seismic Gas S/O Valve 8/11/2023 SGSOV Approved JOAQUIN GREENOUGH
Service/Power Release 8/11/2023 Not Ready for Inspection JOAQUIN GREENOUGH
Final 9/25/2023 Partial Inspection JOAQUIN GREENOUGH
Service/Power Release 9/25/2023 Not Required JOAQUIN GREENOUGH
Final 9/30/2023 OK to Issue CofO JOAQUIN GREENOUGH