2811-2811 1/2 N GRIFFIN AVE 90031

Certificate Information: 2811-2811 1/2 N GRIFFIN AVE 90031

Application / Permit
21010-10000-05121
Plan Check / Job No.
B21LA18520
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
New (2) Detached Accessory Dwelling Units (LID temp deferral required prior to C of O)
Permit Issued
Issued on 6/22/2022
Issuing Office
Current Status
CofO Issued on 7/26/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/1/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 JOE VO
Corrections Issued 10/23/2021 JOE VO
Quality Review Completed 11/4/2021 MICHAEL PEREZ
Plan Check Approved 2/26/2022 JOE VO
Issued 6/22/2022 APPLICANT
CofO in Progress 6/26/2023 AMY COLIN
CofO Issued 7/26/2023 RUBEN SALAS
Permit Finaled 7/26/2023 RUBEN SALAS

Permit Application Clearance Information

HPOZ Cleared 11/23/2021 JONATHAN KAPLAN
Historic monument Cleared 11/23/2021 JONATHAN KAPLAN
Address approval Cleared 11/30/2021 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 12/1/2021 CHRISTOPHER ROCHA
Sewer availability Cleared 12/1/2021 CHRISTOPHER ROCHA
Hydrant and Access approval Cleared 2/7/2022 DWAYNE LAURENT
Roof/Waste drainage to street Cleared 2/14/2022 CHRISTOPHER ROCHA

Contact Information

Contractor A T A Construction Inc; Lic. No.: 1044074-B 9109 GREGORY WAY      BEVERLY HILLS, CA 90211
Engineer Burnazyan,, Gegam; Lic. No.: C76761 5832 JAMIESON AVE      ENCINO, CA 91316

Inspector Information

No Data Available.

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 8/1/2022 Approved AMY COLIN
Footing/Foundation/Slab 8/1/2022 Approved AMY COLIN
PLUMBING-Rough 8/16/2022 Partial Approval OSVALDO PARAMO
Wood Frame 8/16/2022 Partial Approval OSVALDO PARAMO
Insulation 8/17/2022 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 8/19/2022 Approved AMY COLIN
Deputy Wood Construction 8/25/2022 Conditional Approval CRAIG VAUGHAN
Floor/Roof Diaphrgm/Shear Wall 8/25/2022 Partial Approval OSVALDO PARAMO
Floor/Roof Diaphrgm/Shear Wall 8/29/2022 Approved OSVALDO PARAMO
BUILDING-Rough-Frame 9/28/2022 Not Ready for Inspection AMY COLIN
ELECTRICAL-Rough 9/28/2022 Corrections Issued AMY COLIN
Green Building Rough 9/28/2022 Approved AMY COLIN
HVAC-Rough 9/28/2022 Approved AMY COLIN
Interior/Exterior Lathing 9/28/2022 Partial Approval AMY COLIN
PLUMBING-Rough 9/28/2022 Not Ready for Inspection AMY COLIN
Verify Sprinkler Sign Off 9/28/2022 Corrections Issued AMY COLIN
BUILDING-Rough-Frame 10/6/2022 Corrections Issued AMY COLIN
ELECTRICAL-Rough 10/6/2022 Approved AMY COLIN
Interior/Exterior Lathing 10/6/2022 Approved AMY COLIN
PLUMBING-Rough 10/6/2022 Approved AMY COLIN
Insulation 11/3/2022 Approved AMY COLIN
Drywall Nailing 11/15/2022 Approved AMY COLIN
Underground Mechanical 2/9/2023 Partial Approval ALIZAH MAYAGOITIA
Sewer 2/17/2023 Approved AMY COLIN
Underground Mechanical 3/9/2023 Approved AMY COLIN
ELECTRICAL-Final 4/19/2023 Approved AMY COLIN
SGSOV-Seismic Gas S/O Valve 4/19/2023 SGSOV Approved AMY COLIN
Smoke Detectors 4/19/2023 Approved AMY COLIN
BUILDING-Rough-Frame 6/14/2023 Approved AMY COLIN
Final 6/14/2023 Corrections Issued AMY COLIN
Green Building Final 6/14/2023 Approved AMY COLIN
HVAC-Final 6/14/2023 Approved AMY COLIN
PLUMBING-Final 6/14/2023 Approved AMY COLIN
Service/Power Release 6/14/2023 Approved AMY COLIN
Verify Sprinkler Sign Off 6/14/2023 Approved AMY COLIN
Final 6/22/2023 OK to Issue CofO AMY COLIN