444-444 1/2 W 89TH ST 90003
Certificate Information: 444-444 1/2 W 89TH ST 90003
- Application / Permit
- 21010-10000-05106
- Plan Check / Job No.
- B21LA18454
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) 2-STORY DUPLEX WITH ATTACHED 2-CAR GARAGE AT REAR
- Permit Issued
- Issued on 2/28/2022
- Issuing Office
- Current Status
- CofO Issued on 11/10/2022
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 10/26/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 11/5/2021 | GARO TELMI |
| Plan Check Approved | 1/11/2022 | ARSALAN SHABESTARI |
| Issued | 2/28/2022 | APPLICANT |
| Building Plans Picked Up | 3/3/2022 | APPLICANT |
| CofO in Progress | 11/2/2022 | LILIANA PORTILLO |
| Permit Finaled | 11/10/2022 | DEROLD HAUFF |
| CofO Issued | 11/10/2022 | DEROLD HAUFF |
| Permit Finaled | 11/10/2022 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 11/29/2021 | ROBERT DUFF |
| Frnt yard landscape/Water mgmt | Cleared | 11/30/2021 | RICHARD REASER |
| Address approval | Cleared | 12/2/2021 | CHRISTOPHER ROCHA |
| Highway dedication | Cleared | 12/2/2021 | CHRISTOPHER ROCHA |
| Permit | Cleared | 12/2/2021 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 12/3/2021 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 12/3/2021 | CHRISTOPHER ROCHA |
| Low Impact Development | Cleared | 12/10/2021 | CHRIS VONG |
| Roof/Waste drainage to street | Cleared | 12/10/2021 | CELINA MORENO |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/15/2022 | Approved | ALEJANDRO DE ARTOLA |
| Deputy Reinf. Concrete | 3/16/2022 | No Access for Inspection | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 4/11/2022 | Partial Approval | LILIANA PORTILLO |
| PLUMBING-Rough | 4/11/2022 | Partial Approval | LILIANA PORTILLO |
| Sewer | 4/11/2022 | Approved | LILIANA PORTILLO |
| Underground Mechanical | 4/11/2022 | Approved | LILIANA PORTILLO |
| Insulation | 4/20/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 4/21/2022 | Approved | ALEJANDRO DE ARTOLA |
| Pre-Inspection | 5/4/2022 | Approved | ALEJANDRO DE ARTOLA |
| Verify Rec and Parks Fee Memo | 5/4/2022 | Approved | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 5/9/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 6/9/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 7/8/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| PLUMBING-Rough | 7/8/2022 | Approved | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 7/12/2022 | Conditional Approval | LILIANA PORTILLO |
| ELECTRICAL-Rough | 7/12/2022 | Approved | LILIANA PORTILLO |
| Green Building Rough | 7/12/2022 | Approved | LILIANA PORTILLO |
| MERV13>=Rough | 7/12/2022 | Not Ready for Inspection | LILIANA PORTILLO |
| Verify Sprinkler Sign Off | 7/12/2022 | Approved | LILIANA PORTILLO |
| HVAC-Rough | 7/18/2022 | Approved | LILIANA PORTILLO |
| Insulation | 7/18/2022 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 7/26/2022 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 7/26/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 8/5/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 9/22/2022 | Partial Approval | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/20/2022 | SGSOV Not Ready | LILIANA PORTILLO |
| BUILDING-Rough-Frame | 10/25/2022 | Approved | LILIANA PORTILLO |
| ELECTRICAL-Final | 10/25/2022 | Approved | LILIANA PORTILLO |
| Final | 10/25/2022 | OK to Issue CofO | LILIANA PORTILLO |
| Gas Test | 10/25/2022 | Approved | LILIANA PORTILLO |
| Green Building Final | 10/25/2022 | Approved | LILIANA PORTILLO |
| HVAC-Final | 10/25/2022 | Approved | LILIANA PORTILLO |
| MERV13>=Final | 10/25/2022 | Approved | LILIANA PORTILLO |
| MERV13>=Rough | 10/25/2022 | Approved | LILIANA PORTILLO |
| PLUMBING-Final | 10/25/2022 | Approved | LILIANA PORTILLO |
| SGSOV-Seismic Gas S/O Valve | 10/25/2022 | SGSOV Approved | LILIANA PORTILLO |
| Service/Power Release | 10/25/2022 | Approved | LILIANA PORTILLO |
| Smoke Detectors | 10/25/2022 | Approved | LILIANA PORTILLO |
| Service/Power Release | 11/1/2022 | Approved | LILIANA PORTILLO |