444-444 1/2 W 89TH ST 90003

Certificate Information: 444-444 1/2 W 89TH ST 90003

Application / Permit
21010-10000-05106
Plan Check / Job No.
B21LA18454
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(2) Duplex
Work Description
(N) 2-STORY DUPLEX WITH ATTACHED 2-CAR GARAGE AT REAR
Permit Issued
Issued on 2/28/2022
Issuing Office
Current Status
CofO Issued on 11/10/2022
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/5/2021 APPLICANT
Assigned to Plan Check Engineer 10/21/2021 ARSALAN SHABESTARI
Corrections Issued 10/26/2021 ARSALAN SHABESTARI
Quality Review Completed 11/5/2021 GARO TELMI
Plan Check Approved 1/11/2022 ARSALAN SHABESTARI
Issued 2/28/2022 APPLICANT
Building Plans Picked Up 3/3/2022 APPLICANT
CofO in Progress 11/2/2022 LILIANA PORTILLO
Permit Finaled 11/10/2022 DEROLD HAUFF
CofO Issued 11/10/2022 DEROLD HAUFF
Permit Finaled 11/10/2022 DEROLD HAUFF

Permit Application Clearance Information

Hydrant and Access approval Cleared 11/29/2021 ROBERT DUFF
Frnt yard landscape/Water mgmt Cleared 11/30/2021 RICHARD REASER
Address approval Cleared 12/2/2021 CHRISTOPHER ROCHA
Highway dedication Cleared 12/2/2021 CHRISTOPHER ROCHA
Permit Cleared 12/2/2021 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 12/3/2021 CHRISTOPHER ROCHA
Sewer availability Cleared 12/3/2021 CHRISTOPHER ROCHA
Low Impact Development Cleared 12/10/2021 CHRIS VONG
Roof/Waste drainage to street Cleared 12/10/2021 CELINA MORENO

Contact Information

Contractor K N Consulting Inc; Lic. No.: 993102-B P O BOX 410      SUNSET BEACH, CA 90742

Inspector Information

JOHN QUINTANILLA, (213) 792-6055 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Footing/Foundation/Slab 3/15/2022 Approved ALEJANDRO DE ARTOLA
Deputy Reinf. Concrete 3/16/2022 No Access for Inspection LILIANA PORTILLO
BUILDING-Rough-Frame 4/11/2022 Partial Approval LILIANA PORTILLO
PLUMBING-Rough 4/11/2022 Partial Approval LILIANA PORTILLO
Sewer 4/11/2022 Approved LILIANA PORTILLO
Underground Mechanical 4/11/2022 Approved LILIANA PORTILLO
Insulation 4/20/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 4/21/2022 Approved ALEJANDRO DE ARTOLA
Pre-Inspection 5/4/2022 Approved ALEJANDRO DE ARTOLA
Verify Rec and Parks Fee Memo 5/4/2022 Approved ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 5/9/2022 Partial Approval ALEJANDRO DE ARTOLA
Floor/Roof Diaphrgm/Shear Wall 6/9/2022 Partial Approval ALEJANDRO DE ARTOLA
HVAC-Rough 7/8/2022 Not Ready for Inspection LILIANA PORTILLO
PLUMBING-Rough 7/8/2022 Approved LILIANA PORTILLO
BUILDING-Rough-Frame 7/12/2022 Conditional Approval LILIANA PORTILLO
ELECTRICAL-Rough 7/12/2022 Approved LILIANA PORTILLO
Green Building Rough 7/12/2022 Approved LILIANA PORTILLO
MERV13>=Rough 7/12/2022 Not Ready for Inspection LILIANA PORTILLO
Verify Sprinkler Sign Off 7/12/2022 Approved LILIANA PORTILLO
HVAC-Rough 7/18/2022 Approved LILIANA PORTILLO
Insulation 7/18/2022 Approved LILIANA PORTILLO
Drywall Nailing 7/26/2022 Approved ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 7/26/2022 Partial Approval ALEJANDRO DE ARTOLA
Interior/Exterior Lathing 8/5/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 9/22/2022 Partial Approval LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/20/2022 SGSOV Not Ready LILIANA PORTILLO
BUILDING-Rough-Frame 10/25/2022 Approved LILIANA PORTILLO
ELECTRICAL-Final 10/25/2022 Approved LILIANA PORTILLO
Final 10/25/2022 OK to Issue CofO LILIANA PORTILLO
Gas Test 10/25/2022 Approved LILIANA PORTILLO
Green Building Final 10/25/2022 Approved LILIANA PORTILLO
HVAC-Final 10/25/2022 Approved LILIANA PORTILLO
MERV13>=Final 10/25/2022 Approved LILIANA PORTILLO
MERV13>=Rough 10/25/2022 Approved LILIANA PORTILLO
PLUMBING-Final 10/25/2022 Approved LILIANA PORTILLO
SGSOV-Seismic Gas S/O Valve 10/25/2022 SGSOV Approved LILIANA PORTILLO
Service/Power Release 10/25/2022 Approved LILIANA PORTILLO
Smoke Detectors 10/25/2022 Approved LILIANA PORTILLO
Service/Power Release 11/1/2022 Approved LILIANA PORTILLO