623 1/2 W LACONIA BLVD 90044
Certificate Information: 623 1/2 W LACONIA BLVD 90044
- Application / Permit
- 21010-10000-05102
- Plan Check / Job No.
- B21LA18424
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- (N) 1 story ADU with attached garage per LAMC 12.22 A.33 (c)-(d) per WFPP
- Permit Issued
- Issued on 1/13/2023
- Issuing Office
- Metro
- Current Status
- CofO Issued on 12/12/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/8/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2021 | LAWRENCE QUIRANTE |
| Corrections Issued | 10/16/2021 | LAWRENCE QUIRANTE |
| Applicant returned to address corrections | 12/8/2022 | SHANGQIN XIE |
| Applicant returned to address corrections | 12/13/2022 | DANIEL SMILEY |
| Applicant returned to address corrections | 12/13/2022 | CRISTINA SALAZAR |
| Applicant returned to address corrections | 12/16/2022 | MINA HABILI |
| Plan Check Approved | 1/13/2023 | MINA HABILI |
| Issued | 1/13/2023 | APPLICANT |
| CofO in Progress | 12/11/2024 | BEN MOLSTAD |
| CofO Issued | 12/12/2024 | ANSON MAGLASANG |
| Permit Finaled | 12/12/2024 | ANSON MAGLASANG |
Permit Application Clearance Information
| Address approval | Cleared | 10/26/2021 | ERIK BEASLEY |
| Eng Process Fee Ord 176,300 | Cleared | 10/28/2021 | ERIK BEASLEY |
| Roof/Waste drainage to street | Cleared | 11/14/2022 | ERIK BEASLEY |
| Low Impact Development | Cleared | 12/13/2022 | MARTIN FRAGOSO |
| Sewer availability | Cleared | 12/13/2022 | TREVOR QUAN |
| Hydrant and Access approval | Cleared | 1/6/2023 | MATTHEW CRAIG |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| BEN MOLSTAD, (310) 732-4557 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 2/15/2023 | Partial Inspection | JAMES CHAVEZ |
| METHANE-Barrier | 2/15/2023 | Approved | JAMES CHAVEZ |
| METHANE-Subgrade | 2/15/2023 | Approved | JAMES CHAVEZ |
| Footing/Foundation/Slab | 4/6/2023 | Approved | JAMES CHAVEZ |
| Pre-Inspection | 4/6/2023 | Partial Inspection | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 4/24/2023 | Corrections Issued | JAMES CHAVEZ |
| Green Building Rough | 4/24/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| MERV13>=Rough | 4/24/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| METHANE-Rough | 4/24/2023 | Approved | JAMES CHAVEZ |
| Verify Sprinkler Sign Off | 4/24/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Deputy Drilled-In Anchors | 4/27/2023 | Conditional Approval | JAMES CHAVEZ |
| Footing/Foundation/Slab | 4/28/2023 | Approved | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 5/17/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Floor/Roof Diaphrgm/Shear Wall | 5/17/2023 | Partial Approval | JAMES CHAVEZ |
| Green Building Rough | 5/17/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| MERV13>=Rough | 5/17/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Verify Sprinkler Sign Off | 5/17/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Deputy Wood Construction | 5/19/2023 | Conditional Approval | JAMES CHAVEZ |
| ELECTRICAL-Rough | 7/31/2023 | Corrections Issued | JAMES CHAVEZ |
| ELECTRICAL-Rough | 8/4/2023 | Approved | JAMES CHAVEZ |
| HVAC-Rough | 8/4/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| PLUMBING-Rough | 8/4/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| HVAC-Rough | 8/10/2023 | Approved | JAMES CHAVEZ |
| PLUMBING-Rough | 8/10/2023 | Approved | JAMES CHAVEZ |
| Insulation | 8/18/2023 | Not Ready for Inspection | JAMES CHAVEZ |
| Insulation | 10/19/2023 | Approved | JOHN KLARIN |
| Drywall Nailing | 10/25/2023 | Approved | JAMES CHAVEZ |
| Interior/Exterior Lathing | 12/6/2023 | Partial Approval | JAMES CHAVEZ |
| Final | 5/7/2024 | Corrections Issued | JAMES CHAVEZ |
| BUILDING-Rough-Frame | 11/8/2024 | Approved | BEN MOLSTAD |
| Final | 11/8/2024 | Corrections Issued | BEN MOLSTAD |
| Green Building Final | 11/8/2024 | Approved | BEN MOLSTAD |
| Green Building Rough | 11/8/2024 | Approved | BEN MOLSTAD |
| MERV13>=Final | 11/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| MERV13>=Rough | 11/8/2024 | Approved | BEN MOLSTAD |
| SGSOV-Seismic Gas S/O Valve | 11/8/2024 | SGSOV Approved | BEN MOLSTAD |
| Service/Power Release | 11/8/2024 | Not Ready for Inspection | BEN MOLSTAD |
| Smoke Detectors | 11/8/2024 | Approved | BEN MOLSTAD |
| Verify Sprinkler Sign Off | 11/8/2024 | Approved | BEN MOLSTAD |
| Final | 12/3/2024 | Corrections Issued | BEN MOLSTAD |
| MERV13>=Final | 12/3/2024 | Approved | BEN MOLSTAD |
| Service/Power Release | 12/3/2024 | Approved | BEN MOLSTAD |
| Final | 12/4/2024 | Corrections Issued | BEN MOLSTAD |
| Final | 12/11/2024 | OK to Issue CofO | BEN MOLSTAD |