13246 W CUMPSTON ST 91401
Certificate Information: 13246 W CUMPSTON ST 91401
- Application / Permit
- 21010-10000-05083
- Plan Check / Job No.
- B21LA18352
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- (N) SFD / GARAGE -
- Permit Issued
- Issued on 6/10/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 7/21/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/30/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/21/2021 | HERNAN ARREOLA |
| Corrections Issued | 11/12/2021 | HERNAN ARREOLA |
| Quality Review Completed | 11/19/2021 | TEODORO DIAZ RODRIGUEZ |
| Applicant returned to address corrections | 12/13/2021 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/3/2022 | HERNAN ARREOLA |
| Applicant returned to address corrections | 6/9/2022 | HERNAN ARREOLA |
| Plan Check Approved | 6/10/2022 | HERNAN ARREOLA |
| Issued | 6/10/2022 | APPLICANT |
| CofO in Progress | 7/12/2023 | RYAN SALAZAR |
| No Progress | 7/12/2023 | RYAN SALAZAR |
| CofO in Progress | 7/13/2023 | RYAN SALAZAR |
| CofO in Progress | 7/18/2023 | ROBERT GOLD |
| CofO in Progress | 7/18/2023 | ROBERT GOLD |
| CofO Issued | 7/21/2023 | DANIEL ORRANTE |
| Permit Finaled | 7/21/2023 | DANIEL ORRANTE |
Permit Application Clearance Information
| Sewer availability | Cleared | 12/7/2021 | WALLIE JONG |
| ZA Case | Cleared | 12/7/2021 | ANACANY HURTADO |
| Eng Process Fee Ord 176,300 | Cleared | 12/8/2021 | WALLIE JONG |
| Private street | Cleared | 12/15/2021 | ANACANY HURTADO |
| Hydrant and Access approval | Cleared | 2/23/2022 | JOHN CONNEALLY |
| Low Impact Development | Cleared | 5/25/2022 | KHAING AYE |
| Roof/Waste drainage to street | Cleared | 5/26/2022 | WALLIE JONG |
Contact Information
| Contractor | Trig Builders Inc; Lic. No.: 1030887-B | 6442 COLDWATER CANYON AVE 111 NORTH HOLLYWOOD, CA 91606 |
| Engineer | Ni,, Zhang Yuan; Lic. No.: C68149 | 8232 GARVEY AVE 203 ROSEMEAD, CA 91770 |
Inspector Information
| JOSE AVILA, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
| VINCENT HANLEY, (818) 374-1173 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Grading Pre-Inspection | 7/7/2022 | Corrections Issued | MATT KELLERMAN |
| PLUMBING-Rough | 7/26/2022 | Partial Approval | DEANDRE HOFFMAN |
| Excavation/Setback/Form/Re-Bar | 8/4/2022 | Corrections Issued | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 8/8/2022 | Partial Approval | RICHARD DOCKUS |
| Deputy Reinf. Concrete | 8/19/2022 | Conditional Approval | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 8/19/2022 | Not Ready for Inspection | RICHARD DOCKUS |
| Excavation/Setback/Form/Re-Bar | 8/25/2022 | Approved | ROBERT GOLD |
| Deputy Reinf. Concrete | 8/29/2022 | Conditional Approval | RICHARD DOCKUS |
| Deputy Steel/Welding | 9/13/2022 | Conditional Approval | RICHARD DOCKUS |
| Deputy Steel/Welding | 9/16/2022 | Conditional Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 9/16/2022 | Corrections Issued | RICHARD DOCKUS |
| Deputy Drilled-In Anchors | 9/29/2022 | Conditional Approval | RICHARD DOCKUS |
| Deputy Wood Construction | 9/30/2022 | Conditional Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 10/4/2022 | Partial Approval | RICHARD DOCKUS |
| Deputy Wood Construction | 10/26/2022 | Conditional Approval | MICHAEL SMITH |
| Deputy Wood Construction | 11/2/2022 | Conditional Approval | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2022 | Corrections Issued | RICHARD DOCKUS |
| Floor/Roof Diaphrgm/Shear Wall | 11/9/2022 | Approved | RICHARD DOCKUS |
| PLUMBING-Rough | 11/17/2022 | Approved | RICHARD DOCKUS |
| ELECTRICAL-Rough | 11/23/2022 | Not Ready for Inspection | JOHN COLEMAN |
| HVAC-Rough | 11/23/2022 | No Access for Inspection | JOHN COLEMAN |
| ELECTRICAL-Rough | 11/30/2022 | Approved | JOHN COLEMAN |
| HVAC-Rough | 11/30/2022 | Not Ready for Inspection | JOHN COLEMAN |
| Pre-Inspection | 12/5/2022 | No Access for Inspection | JOHN COLEMAN |
| BUILDING-Rough-Frame | 12/7/2022 | Not Ready for Inspection | JOHN COLEMAN |
| Green Building Rough | 12/7/2022 | Approved | JOHN COLEMAN |
| HVAC-Rough | 12/7/2022 | Approved | JOHN COLEMAN |
| Verify Sprinkler Sign Off | 12/7/2022 | Not Ready for Inspection | JOHN COLEMAN |
| BUILDING-Rough-Frame | 12/15/2022 | Partial Approval | RYAN SALAZAR |
| Verify Sprinkler Sign Off | 12/15/2022 | Approved | RYAN SALAZAR |
| Wood Frame | 12/15/2022 | Approved | RYAN SALAZAR |
| Insulation | 12/22/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Interior/Exterior Lathing | 12/22/2022 | Partial Approval | CHRISTOPHE COCHRAN |
| Shower Pan | 12/22/2022 | Corrections Issued | CHRISTOPHE COCHRAN |
| Insulation | 12/23/2022 | Approved | WILLIAM WREN |
| Shower Pan | 12/23/2022 | Approved | WILLIAM WREN |
| Interior/Exterior Lathing | 12/30/2022 | Approved | RYAN SALAZAR |
| Drywall Nailing | 1/6/2023 | Conditional Approval | RYAN SALAZAR |
| BUILDING-Rough-Frame | 6/13/2023 | Approved | RYAN SALAZAR |
| Drywall Nailing | 6/13/2023 | Approved | RYAN SALAZAR |
| Final | 6/13/2023 | Corrections Issued | RYAN SALAZAR |
| Footing/Foundation/Slab | 6/13/2023 | Approved | RYAN SALAZAR |
| Green Building Final | 6/13/2023 | Not Ready for Inspection | RYAN SALAZAR |
| SGSOV-Seismic Gas S/O Valve | 6/13/2023 | SGSOV Approved | RYAN SALAZAR |
| Service/Power Release | 6/13/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Smoke Detectors | 6/13/2023 | Corrections Issued | RYAN SALAZAR |
| Final | 6/29/2023 | Corrections Issued | RYAN SALAZAR |
| Green Building Final | 6/29/2023 | Approved | RYAN SALAZAR |
| Service/Power Release | 6/29/2023 | Not Ready for Inspection | RYAN SALAZAR |
| Smoke Detectors | 6/29/2023 | Approved | RYAN SALAZAR |
| Final | 7/12/2023 | OK to Issue CofO | RYAN SALAZAR |
| Service/Power Release | 7/12/2023 | Approved | RYAN SALAZAR |