1049 W 81ST PL 90044
Certificate Information: 1049 W 81ST PL 90044
- Application / Permit
- 21010-10000-05045
- Plan Check / Job No.
- B21LA18170
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- ADDITION TO DETACHED GARAGE AND CONVERSION TO ADU PER LAMC 12.22 A.33(c) and (d)
- Permit Issued
- Issued on 10/27/2022
- Issuing Office
- Current Status
- CofO Issued on 3/13/2026
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/4/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | JOE VO |
| Corrections Issued | 10/8/2021 | JOE VO |
| Applicant returned to address corrections | 1/12/2022 | JOE VO |
| Plan Check Approved | 3/26/2022 | JOE VO |
| Issued | 10/27/2022 | APPLICANT |
| CofO in Progress | 3/12/2026 | MICHAEL LEWIS |
| Permit Finaled | 3/13/2026 | DEROLD HAUFF |
| CofO Issued | 3/13/2026 | DEROLD HAUFF |
| Permit Finaled | 3/13/2026 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 12/9/2021 | JEANETTE VONG |
| Roof/Waste drainage to street | Cleared | 12/9/2021 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 12/10/2021 | JEANETTE VONG |
| Sewer availability | Cleared | 12/10/2021 | JEANETTE VONG |
| Construction near power lines | Cleared | 2/18/2022 | RIDWAN HARDY |
| Community Plan Implem. Overlay | Cleared | 3/23/2022 | RAFAEL FONTES |
Contact Information
| Contractor | Glenford Construction; Lic. No.: 950038-B | , |
Inspector Information
| JOHN QUINTANILLA, (213) 792-6055 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/12/2024 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Special/Order Compliance | 3/27/2025 | Partial Inspection | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 7/10/2025 | Corrections Issued | JOHN QUINTANILLA |
| Sewer | 7/10/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 7/16/2025 | Approved | JOHN QUINTANILLA |
| PLUMBING-Rough | 7/16/2025 | Approved | JOHN QUINTANILLA |
| HVAC-Rough | 7/17/2025 | Approved | JOHN QUINTANILLA |
| Floor/Roof Diaphrgm/Shear Wall | 7/24/2025 | Approved | JOHN QUINTANILLA |
| Pre-Inspection | 7/24/2025 | Partial Approval | JOHN QUINTANILLA |
| BUILDING-Rough-Frame | 8/6/2025 | Approved | JOHN QUINTANILLA |
| Green Building Rough | 8/6/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 8/6/2025 | Approved | JOHN QUINTANILLA |
| Interior/Exterior Lathing | 8/13/2025 | Corrections Issued | RONNIE MEDINA |
| Interior/Exterior Lathing | 8/19/2025 | Partial Approval | ANTHONY RAMOS |
| Drywall Nailing | 9/5/2025 | Corrections Issued | ANTHONY RAMOS |
| Insulation | 9/5/2025 | Approved | ANTHONY RAMOS |
| Drywall Nailing | 9/10/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Final | 10/20/2025 | Corrections Issued | JOHN QUINTANILLA |
| ELECTRICAL-Rough | 10/23/2025 | Partial Inspection | SALVADOR MARTINEZ |
| Insulation | 10/23/2025 | Partial Inspection | SALVADOR MARTINEZ |
| Shower Pan | 10/24/2025 | Approved | DEVON JACKSON |
| Interior/Exterior Lathing | 10/28/2025 | Approved | BRENDAN MORELLI |
| Final | 12/22/2025 | Corrections Issued | JOHN QUINTANILLA |
| Footing/Foundation/Slab | 12/22/2025 | Approved | JOHN QUINTANILLA |
| Green Building Final | 12/22/2025 | Approved | JOHN QUINTANILLA |
| SGSOV-Seismic Gas S/O Valve | 12/22/2025 | SGSOV Not Required | JOHN QUINTANILLA |
| Smoke Detectors | 12/22/2025 | Approved | JOHN QUINTANILLA |
| ELECTRICAL-Final | 12/29/2025 | Approved | JOHN QUINTANILLA |
| HVAC-Final | 12/29/2025 | Corrections Issued | JOHN QUINTANILLA |
| PLUMBING-Final | 12/29/2025 | Corrections Issued | JOHN QUINTANILLA |
| Final | 12/31/2025 | Conditional Approval | JOHN QUINTANILLA |
| Final | 3/11/2026 | OK to Issue CofO | MICHAEL LEWIS |