1323 1/2 W 69TH ST 90044
Certificate Information: 1323 1/2 W 69TH ST 90044
- Application / Permit
- 21010-10000-05035
- Plan Check / Job No.
- B21LA18135
- Group
- Building
- Type
- Bldg-Addition
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- CONVERT (E) GARAGE WITH AN ADDITION OF 74 SF, INTO AN A.D.U OF 388 SF.
- Permit Issued
- Issued on 11/24/2021
- Issuing Office
- Current Status
- CofO Issued on 12/7/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/30/2021 | JOE VO |
| Corrections Issued | 10/1/2021 | JOE VO |
| Plan Check Approved | 11/6/2021 | JOE VO |
| Issued | 11/24/2021 | APPLICANT |
| CofO in Progress | 11/27/2024 | CRAIG DAVIS |
| Permit Finaled | 12/7/2024 | DEROLD HAUFF |
| CofO Issued | 12/7/2024 | DEROLD HAUFF |
| Permit Finaled | 12/7/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/6/2021 | THOMAS LANG |
| Roof/Waste drainage to street | Cleared | 10/6/2021 | THOMAS LANG |
| Sewer availability | Cleared | 10/12/2021 | THOMAS LANG |
| Eng Process Fee Ord 176,300 | Cleared | 10/22/2021 | THOMAS LANG |
Contact Information
| Contractor | Frost Construction; Lic. No.: 580847-B | 1041 WEST 105TH STREET LOS ANGELES, CA 90044 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| PLUMBING-Rough | 3/24/2022 | Partial Approval | HORACE FULTZ |
| PLUMBING-Rough | 3/30/2022 | Approved | ENRIQUE MIRELES |
| Deputy Drilled-In Anchors | 4/8/2022 | Approved | ENRIQUE MIRELES |
| Footing/Foundation/Slab | 4/8/2022 | Corrections Issued | ENRIQUE MIRELES |
| Excavation/Setback/Form/Re-Bar | 5/27/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 5/15/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 5/15/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/15/2023 | Not Ready for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 5/19/2023 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/11/2023 | No Access for Inspection | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 7/11/2023 | No Access for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/11/2023 | No Access for Inspection | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 7/20/2023 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 7/20/2023 | Approved | ENRIQUE MIRELES |
| PLUMBING-Rough | 7/20/2023 | Approved | ENRIQUE MIRELES |
| Insulation | 11/20/2023 | Approved | RONNIE MINDANAO |
| Interior/Exterior Lathing | 11/20/2023 | Corrections Issued | RONNIE MINDANAO |
| Interior/Exterior Lathing | 11/27/2023 | Partial Approval | BRENDAN MORELLI |
| Drywall Nailing | 12/4/2023 | Approved | CRAIG DAVIS |
| ELECTRICAL-Final | 6/20/2024 | Corrections Issued | CRAIG DAVIS |
| HVAC-Final | 6/20/2024 | Not Ready for Inspection | CRAIG DAVIS |
| PLUMBING-Final | 6/20/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Shower Pan | 6/20/2024 | Corrections Issued | CRAIG DAVIS |
| Smoke Detectors | 6/20/2024 | Not Ready for Inspection | CRAIG DAVIS |
| ELECTRICAL-Final | 6/26/2024 | No Access for Inspection | CRAIG DAVIS |
| Shower Pan | 6/26/2024 | No Access for Inspection | JOSH MEISTER |
| ELECTRICAL-Final | 7/10/2024 | Corrections Issued | CRAIG DAVIS |
| Shower Pan | 7/10/2024 | Not Ready for Inspection | CRAIG DAVIS |
| Gas Test | 7/12/2024 | Not Ready for Inspection | DAVID FEILER |
| Interior/Exterior Lathing | 7/12/2024 | Not Ready for Inspection | DAVID FEILER |
| Shower Pan | 7/12/2024 | Not Ready for Inspection | DAVID FEILER |
| ELECTRICAL-Rough | 7/23/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Interior/Exterior Lathing | 7/23/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Shower Pan | 7/23/2024 | Not Ready for Inspection | MICHAEL LEWIS |
| Shower Pan | 10/18/2024 | Corrections Issued | JOSH MEISTER |
| Gas Test | 10/21/2024 | Corrections Issued | CRAIG DAVIS |
| Interior/Exterior Lathing | 10/21/2024 | Corrections Issued | CRAIG DAVIS |
| Shower Pan | 10/21/2024 | Corrections Issued | CRAIG DAVIS |
| Interior/Exterior Lathing | 10/28/2024 | Approved | CRAIG DAVIS |
| Shower Pan | 10/28/2024 | Approved | CRAIG DAVIS |
| BUILDING-Rough-Frame | 11/19/2024 | Approved | MICHAEL LEWIS |
| Final | 11/19/2024 | Corrections Issued | MICHAEL LEWIS |
| Footing/Foundation/Slab | 11/19/2024 | Approved | MICHAEL LEWIS |
| Gas Test | 11/19/2024 | Approved | MICHAEL LEWIS |
| Green Building Final | 11/19/2024 | Approved | MICHAEL LEWIS |
| Green Building Rough | 11/19/2024 | Approved | MICHAEL LEWIS |
| SGSOV-Seismic Gas S/O Valve | 11/19/2024 | SGSOV Approved | MICHAEL LEWIS |
| Smoke Detectors | 11/19/2024 | Approved | MICHAEL LEWIS |
| Final | 11/26/2024 | OK to Issue CofO | CRAIG DAVIS |