1625 S OGDEN DR 90019
Certificate Information: 1625 S OGDEN DR 90019
- Application / Permit
- 21010-10000-05034
- Plan Check / Job No.
- B21LA18133
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- eplan DETATCHED 391 SF ADU PER ORDINANCE
- Permit Issued
- Issued on 5/8/2022
- Issuing Office
- Current Status
- CofO Issued on 4/25/2025
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/12/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/9/2021 | ARSALAN SHABESTARI |
| Corrections Issued | 11/17/2021 | ARSALAN SHABESTARI |
| Quality Review Completed | 11/23/2021 | MICHAEL PEREZ |
| Plan Check Approved | 5/6/2022 | ARSALAN SHABESTARI |
| Issued | 5/8/2022 | APPLICANT |
| CofO in Progress | 1/22/2025 | ARTHUR NEGRETE |
| No Progress | 4/5/2025 | DEROLD HAUFF |
| CofO in Progress | 4/5/2025 | DEROLD HAUFF |
| Permit Finaled | 4/25/2025 | DEROLD HAUFF |
| CofO Issued | 4/25/2025 | DEROLD HAUFF |
| Permit Finaled | 4/25/2025 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 2/23/2022 | AMAAN MALIK |
| Roof/Waste drainage to street | Cleared | 2/23/2022 | AMAAN MALIK |
| Eng Process Fee Ord 176,300 | Cleared | 3/15/2022 | AMAAN MALIK |
| Sewer availability | Cleared | 3/15/2022 | AMAAN MALIK |
Contact Information
| Contractor | Owner-Builder | , |
Inspector Information
| DAVID WILLIAMS, (213) 202-3126 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 10/31/2022 | Corrections Issued | JOSE AVILA |
| METHANE-Barrier | 10/31/2022 | Approved | JOSE AVILA |
| METHANE-Subgrade | 10/31/2022 | Approved | JOSE AVILA |
| PLUMBING-Rough | 10/31/2022 | Partial Approval | JOSE AVILA |
| Underground Mechanical | 10/31/2022 | Partial Approval | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 11/9/2022 | Corrections Issued | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 11/16/2022 | Partial Inspection | JOSE AVILA |
| Footing/Foundation/Slab | 11/16/2022 | Partial Inspection | JOSE AVILA |
| Excavation/Setback/Form/Re-Bar | 11/17/2022 | Corrections Issued | JOSE AVILA |
| Footing/Foundation/Slab | 11/23/2022 | Approved | STUART CHAPMAN |
| Green Building Rough | 11/23/2022 | Not Ready for Inspection | STUART CHAPMAN |
| METHANE-Rough | 11/23/2022 | Approved | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 11/23/2022 | Approved | STUART CHAPMAN |
| Floor/Roof Diaphrgm/Shear Wall | 12/2/2022 | Corrections Issued | JOSE AVILA |
| BUILDING-Rough-Frame | 12/13/2022 | Not Ready for Inspection | MICHAEL LEWIS |
| Floor/Roof Diaphrgm/Shear Wall | 12/13/2022 | Conditional Approval | MICHAEL LEWIS |
| Green Building Rough | 12/13/2022 | Not Ready for Inspection | MICHAEL LEWIS |
| PLUMBING-Rough | 1/4/2023 | Corrections Issued | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 1/6/2023 | Corrections Issued | JOSE AVILA |
| ELECTRICAL-Rough | 1/12/2023 | Corrections Issued | MICHAEL LEWIS |
| HVAC-Rough | 1/12/2023 | Not Ready for Inspection | MICHAEL LEWIS |
| PLUMBING-Rough | 1/12/2023 | Approved | MICHAEL LEWIS |
| ELECTRICAL-Rough | 1/18/2023 | Approved | JOSE AVILA |
| HVAC-Rough | 1/27/2023 | Approved | JOSE AVILA |
| Underground Mechanical | 1/30/2023 | Approved | JOSE AVILA |
| Floor/Roof Diaphrgm/Shear Wall | 2/1/2023 | Partial Approval | JOSE AVILA |
| Wood Frame | 2/3/2023 | Corrections Issued | SCOTT FINNILA |
| Wood Frame | 2/16/2023 | Corrections Issued | JOSE AVILA |
| Underground Mechanical | 4/13/2023 | Approved | JOSE AVILA |
| Pre-Inspection | 7/20/2023 | No Access for Inspection | JOSE AVILA |
| BUILDING-Rough-Frame | 8/28/2023 | Conditional Approval | JOSE AVILA |
| Insulation | 9/11/2023 | Corrections Issued | JOSE AVILA |
| Insulation | 10/5/2023 | Approved | LILIANA PORTILLO |
| Drywall Nailing | 10/24/2023 | Corrections Issued | BRENDAN MORELLI |
| Drywall Nailing | 10/30/2023 | Corrections Issued | RONNIE MINDANAO |
| Drywall Nailing | 11/6/2023 | Approved | RONNIE MINDANAO |
| Shower Pan | 11/21/2023 | Approved | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 11/30/2023 | Partial Approval | STUART CHAPMAN |
| BUILDING-Rough-Frame | 5/3/2024 | No Access for Inspection | RICHARD DOCKUS |
| Final | 5/3/2024 | No Access for Inspection | RICHARD DOCKUS |
| Green Building Final | 5/3/2024 | No Access for Inspection | RICHARD DOCKUS |
| Green Building Rough | 5/3/2024 | No Access for Inspection | RICHARD DOCKUS |
| SGSOV-Seismic Gas S/O Valve | 5/3/2024 | SGSOV Not Ready | RICHARD DOCKUS |
| Service/Power Release | 5/3/2024 | No Access for Inspection | RICHARD DOCKUS |
| Smoke Detectors | 5/3/2024 | No Access for Inspection | RICHARD DOCKUS |
| BUILDING-Rough-Frame | 5/20/2024 | No Access for Inspection | ARTHUR NEGRETE |
| Final | 5/20/2024 | No Access for Inspection | ARTHUR NEGRETE |
| Green Building Final | 5/20/2024 | No Access for Inspection | ARTHUR NEGRETE |
| Green Building Rough | 5/20/2024 | No Access for Inspection | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 5/20/2024 | SGSOV Not Ready | ARTHUR NEGRETE |
| Service/Power Release | 5/20/2024 | No Access for Inspection | ARTHUR NEGRETE |
| Smoke Detectors | 5/20/2024 | No Access for Inspection | ARTHUR NEGRETE |
| BUILDING-Rough-Frame | 5/31/2024 | Approved | ARTHUR NEGRETE |
| Final | 5/31/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Green Building Final | 5/31/2024 | Corrections Issued | ARTHUR NEGRETE |
| Green Building Rough | 5/31/2024 | Approved | ARTHUR NEGRETE |
| SGSOV-Seismic Gas S/O Valve | 5/31/2024 | SGSOV Approved | ARTHUR NEGRETE |
| Service/Power Release | 5/31/2024 | Not Ready for Inspection | ARTHUR NEGRETE |
| Smoke Detectors | 5/31/2024 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 1/17/2025 | Approved | ARTHUR NEGRETE |
| Final | 1/17/2025 | OK to Issue CofO | ARTHUR NEGRETE |
| Green Building Final | 1/17/2025 | Approved | ARTHUR NEGRETE |
| HVAC-Final | 1/17/2025 | Approved | ARTHUR NEGRETE |
| PLUMBING-Final | 1/17/2025 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 1/17/2025 | Approved | ARTHUR NEGRETE |
| ELECTRICAL-Final | 3/18/2025 | Approved | ARTHUR NEGRETE |
| Service/Power Release | 3/18/2025 | Approved | ARTHUR NEGRETE |