924 N HIGHLAND AVE 90036

Certificate Information: 924 N HIGHLAND AVE 90036

Application / Permit
21010-10000-05031
Plan Check / Job No.
B21LA18131
Group
Building
Type
Bldg-Addition
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
Convert (E) Recreation room into ADU w/ Trellis
Permit Issued
Issued on 1/12/2023
Issuing Office
Current Status
CofO Issued on 9/25/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 10/5/2021 APPLICANT
Assigned to Plan Check Engineer 10/8/2021 HERNAN ARREOLA
Corrections Issued 10/9/2021 HERNAN ARREOLA
Applicant returned to address corrections 6/18/2022 SHANGQIN XIE
Applicant returned to address corrections 10/17/2022 HERNAN ARREOLA
Plan Check Approved 1/12/2023 HERNAN ARREOLA
Issued 1/12/2023 APPLICANT
CofO in Progress 9/20/2023 DONALD CRICHLOW
CofO in Progress 9/21/2023 RICHARD DOCKUS
Permit Finaled 9/25/2023 DEROLD HAUFF
CofO Issued 9/25/2023 DEROLD HAUFF
Permit Finaled 9/25/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 12/1/2021 WALLIE JONG
Sewer availability Cleared 12/1/2021 WALLIE JONG
Construction near power lines Cleared 3/21/2022 RIDWAN HARDY
Eng Process Fee Ord 176,300 Cleared 3/23/2022 WALLIE JONG

Contact Information

Contractor Owner-Builder       ,
Engineer Barakat,, Fouad Chafic; Lic. No.: NA67449       ,

Inspector Information

RONNIE MINDANAO, (213) 202-3252 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Pre-Inspection 3/20/2023 Partial Inspection RICHARD DOCKUS
Excavation/Setback/Form/Re-Bar 4/3/2023 Approved MICHAEL LEWIS
Footing/Foundation/Slab 4/3/2023 Partial Approval MICHAEL LEWIS
METHANE-Subgrade 4/3/2023 Approved MICHAEL LEWIS
Sewer 4/3/2023 Approved MICHAEL LEWIS
Deputy Drilled-In Anchors 4/5/2023 Conditional Approval RICHARD DOCKUS
BUILDING-Rough-Frame 4/12/2023 Corrections Issued RICHARD DOCKUS
ELECTRICAL-Rough 4/12/2023 Corrections Issued RICHARD DOCKUS
PLUMBING-Rough 4/12/2023 Approved RICHARD DOCKUS
Underground Mechanical 4/12/2023 Partial Approval RICHARD DOCKUS
ELECTRICAL-Rough 5/26/2023 Not Ready for Inspection RICHARD DOCKUS
METHANE-Barrier 5/26/2023 Approved RICHARD DOCKUS
METHANE-Rough 5/26/2023 Approved RICHARD DOCKUS
ELECTRICAL-Rough 6/1/2023 Corrections Issued RICHARD DOCKUS
ELECTRICAL-Rough 6/7/2023 Approved RICHARD DOCKUS
Footing/Foundation/Slab 6/7/2023 Approved RICHARD DOCKUS
HVAC-Rough 6/7/2023 Corrections Issued RICHARD DOCKUS
Floor/Roof Diaphrgm/Shear Wall 6/13/2023 Not Ready for Inspection RICHARD DOCKUS
HVAC-Rough 6/13/2023 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 6/20/2023 Corrections Issued RICHARD DOCKUS
Green Building Rough 6/20/2023 Approved RICHARD DOCKUS
BUILDING-Rough-Frame 6/29/2023 Approved RICHARD DOCKUS
Gas Test 6/29/2023 Corrections Issued RICHARD DOCKUS
Insulation 6/29/2023 Approved RICHARD DOCKUS
Interior/Exterior Lathing 6/29/2023 Corrections Issued RICHARD DOCKUS
Drywall Nailing 7/3/2023 Approved RICHARD DOCKUS
Gas Test 7/3/2023 Approved RICHARD DOCKUS
Interior/Exterior Lathing 7/3/2023 Order to Comply Issued RICHARD DOCKUS
ELECTRICAL-Final 8/3/2023 Corrections Issued SCOTT FINNILA
Final 8/3/2023 Corrections Issued SCOTT FINNILA
Green Building Final 8/3/2023 Corrections Issued SCOTT FINNILA
HVAC-Final 8/3/2023 Corrections Issued SCOTT FINNILA
PLUMBING-Final 8/3/2023 Corrections Issued SCOTT FINNILA
SGSOV-Seismic Gas S/O Valve 8/3/2023 SGSOV Approved SCOTT FINNILA
Smoke Detectors 8/3/2023 Corrections Issued SCOTT FINNILA
Final 9/14/2023 OK to Issue CofO RICHARD DOCKUS
Green Building Final 9/14/2023 Approved RICHARD DOCKUS
Smoke Detectors 9/14/2023 Approved RICHARD DOCKUS