784 W 4TH ST 90731

Certificate Information: 784 W 4TH ST 90731

Application / Permit
21010-10000-05028
Plan Check / Job No.
B21LA18127
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
ePLAN. NEW DETACHED ACCESSORY DWELLING UNIT AT REAR PER LAMC 12.22 A.33 (c)-(d).
Permit Issued
Issued on 12/1/2022
Issuing Office
Current Status
CofO Issued on 2/15/2024
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/28/2021 APPLICANT
Assigned to Plan Check Engineer 10/1/2021 KEVIN MORALES
Corrections Issued 10/1/2021 KEVIN MORALES
Applicant returned to address corrections 10/21/2021 KEVIN MORALES
Applicant returned to address corrections 10/28/2021 KEVIN MORALES
Applicant returned to address corrections 11/8/2021 KEVIN MORALES
Applicant returned to address corrections 6/24/2022 KEVIN MORALES
Applicant returned to address corrections 9/17/2022 AUNG SOE
Applicant returned to address corrections 10/13/2022 KEVIN MORALES
Applicant returned to address corrections 11/3/2022 KEVIN MORALES
Plan Check Approved 11/21/2022 KEVIN MORALES
Issued 12/1/2022 APPLICANT
CofO in Progress 2/15/2024 JAMES CHAVEZ
Permit Finaled 2/15/2024 ANSON MAGLASANG
CofO Issued 2/15/2024 ANSON MAGLASANG
Permit Finaled 2/15/2024 ANSON MAGLASANG

Permit Application Clearance Information

Address approval Cleared 10/8/2021 JOSE HERNANDEZ
Eng Process Fee Ord 176,300 Cleared 10/22/2021 JOSE HERNANDEZ
Sewer availability Cleared 10/22/2021 JOSE HERNANDEZ
GPI Written Notices Cleared 10/13/2022 KEVIN MORALES
Grading Pre-Inspection Cleared 10/13/2022 KEVIN MORALES
Roof/Waste drainage to street Cleared 11/9/2022 ANA SORIANO
Low Impact Development Cleared 11/18/2022 ROGELIO CORTES

Contact Information

Contractor Owner-Builder       ,
Engineer Gao,, Jianfeng; Lic. No.: C88478 1432 STARDUST DR      WEST COVINA, CA 91790

Inspector Information

JOSEPH MCGARRY, (310) 732-4559 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 3/31/2023 Not Ready for Inspection ANSON MAGLASANG
PLUMBING-Rough 3/31/2023 Partial Approval ANSON MAGLASANG
Sewer 3/31/2023 Partial Approval ANSON MAGLASANG
Excavation/Setback/Form/Re-Bar 4/7/2023 Not Ready for Inspection JOHN KLARIN
BUILDING-Rough-Frame 5/22/2023 Approved JOHN KLARIN
ELECTRICAL-Rough 5/22/2023 Corrections Issued JOHN KLARIN
Green Building Rough 5/22/2023 Approved JOHN KLARIN
PLUMBING-Rough 5/22/2023 Approved JOHN KLARIN
Verify Sprinkler Sign Off 5/22/2023 Approved JOHN KLARIN
ELECTRICAL-Rough 6/8/2023 Approved JOHN KLARIN
Floor/Roof Diaphrgm/Shear Wall 6/8/2023 Approved JOHN KLARIN
Insulation 6/8/2023 Corrections Issued JOHN KLARIN
Interior/Exterior Lathing 6/8/2023 Approved JOHN KLARIN
Drywall Nailing 7/25/2023 Approved ANSON MAGLASANG
Interior/Exterior Lathing 7/25/2023 Partial Approval ANSON MAGLASANG
Shower Pan 7/25/2023 Approved ANSON MAGLASANG
ELECTRICAL-Final 11/17/2023 Not Ready for Inspection JAMES CHAVEZ
Final 11/17/2023 Corrections Issued JAMES CHAVEZ
Footing/Foundation/Slab 11/17/2023 Approved JAMES CHAVEZ
Gas Test 11/17/2023 Approved JAMES CHAVEZ
Green Building Final 11/17/2023 Not Ready for Inspection JAMES CHAVEZ
HVAC-Final 11/17/2023 Not Ready for Inspection JAMES CHAVEZ
PLUMBING-Final 11/17/2023 Not Ready for Inspection JAMES CHAVEZ
SGSOV-Seismic Gas S/O Valve 11/17/2023 SGSOV Approved JAMES CHAVEZ
Service/Power Release 11/17/2023 Not Ready for Inspection JAMES CHAVEZ
Smoke Detectors 11/17/2023 Not Ready for Inspection JAMES CHAVEZ
Final 2/2/2024 OK to Issue CofO JAMES CHAVEZ
Green Building Final 2/2/2024 Approved JAMES CHAVEZ
Service/Power Release 2/2/2024 Approved JAMES CHAVEZ
Smoke Detectors 2/2/2024 Approved JAMES CHAVEZ