1614 N SOTO ST 90033
Certificate Information: 1614 N SOTO ST 90033
- Application / Permit
- 21010-10000-05020
- Plan Check / Job No.
- B21LA18080
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Dwelling - Single Family
- Work Description
- NEW 2-STORY SINGLE FAMILY DWELLING/GARAGE WITH 6-CAR GARAGE AT 1ST FLOOR & DWELLING AT 2ND FLOOR AT REAR OF LOT
- Permit Issued
- Issued on 2/18/2022
- Issuing Office
- Current Status
- CofO Issued on 1/9/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/28/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2021 | PRANITA SHAH |
| Corrections Issued | 11/2/2021 | PRANITA SHAH |
| Quality Review Completed | 11/8/2021 | MICHAEL PEREZ |
| Building Plans Picked Up | 11/15/2021 | APPLICANT |
| Applicant returned to address corrections | 2/2/2022 | PRANITA SHAH |
| Plan Check Approved | 2/9/2022 | PRANITA SHAH |
| Issued | 2/18/2022 | APPLICANT |
| CofO in Progress | 12/22/2022 | OSVALDO PARAMO |
| CofO in Progress | 12/22/2022 | OSVALDO PARAMO |
| Permit Finaled | 1/9/2023 | DEROLD HAUFF |
| CofO Issued | 1/9/2023 | DEROLD HAUFF |
| Permit Finaled | 1/9/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Hydrant and Access approval | Cleared | 11/23/2021 | ROBERT DUFF |
| Address approval | Cleared | 11/24/2021 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 11/24/2021 | JEANETTE VONG |
| Highway dedication | Cleared | 11/24/2021 | JEANETTE VONG |
| Sewer availability | Cleared | 11/24/2021 | JEANETTE VONG |
| Low Impact Development | Cleared | 12/22/2021 | MARCO SANCHEZ |
| Roof/Waste drainage to street | Cleared | 12/27/2021 | CELINA MORENO |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| OSVALDO PARAMO, (213) 202-9854 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 5/13/2022 | Approved | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 5/23/2022 | Partial Approval | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 5/24/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 6/8/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Floor/Roof Diaphrgm/Shear Wall | 6/28/2022 | Conditional Approval | AMY COLIN |
| PLUMBING-Rough | 6/29/2022 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 6/29/2022 | Partial Approval | OSVALDO PARAMO |
| HVAC-Rough | 6/30/2022 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 7/1/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| Special/Order Compliance | 7/5/2022 | Not Ready for Inspection | OSVALDO PARAMO |
| BUILDING-Rough-Frame | 8/3/2022 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Rough | 8/3/2022 | Approved | OSVALDO PARAMO |
| Green Building Rough | 8/3/2022 | Approved | OSVALDO PARAMO |
| Verify Sprinkler Sign Off | 8/3/2022 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 8/9/2022 | Partial Approval | ALIZAH MAYAGOITIA |
| Insulation | 8/15/2022 | Approved | OSVALDO PARAMO |
| Drywall Nailing | 8/31/2022 | Approved | OSVALDO PARAMO |
| Interior/Exterior Lathing | 8/31/2022 | Approved | OSVALDO PARAMO |
| Underground Mechanical | 11/1/2022 | Approved | OSVALDO PARAMO |
| ELECTRICAL-Final | 11/21/2022 | Partial Approval | OSVALDO PARAMO |
| ELECTRICAL-Final | 11/22/2022 | Not Ready for Inspection | RUBEN SALAS |
| Gas Test | 11/22/2022 | Approved | RUBEN SALAS |
| Green Building Final | 11/22/2022 | Not Ready for Inspection | RUBEN SALAS |
| HVAC-Final | 11/22/2022 | Not Ready for Inspection | RUBEN SALAS |
| PLUMBING-Final | 11/22/2022 | Not Ready for Inspection | RUBEN SALAS |
| SGSOV-Seismic Gas S/O Valve | 11/22/2022 | SGSOV Not Ready | RUBEN SALAS |
| Service/Power Release | 11/22/2022 | Not Ready for Inspection | RUBEN SALAS |
| Smoke Detectors | 11/22/2022 | Not Ready for Inspection | RUBEN SALAS |
| ELECTRICAL-Final | 11/30/2022 | Approved | OSVALDO PARAMO |
| Service/Power Release | 11/30/2022 | Approved | OSVALDO PARAMO |
| HVAC-Final | 12/5/2022 | Corrections Issued | OSVALDO PARAMO |
| PLUMBING-Final | 12/5/2022 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 12/6/2022 | SGSOV Not Ready | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 12/9/2022 | SGSOV Not Ready | OSVALDO PARAMO |
| Final | 12/14/2022 | Corrections Issued | OSVALDO PARAMO |
| Green Building Final | 12/14/2022 | Approved | OSVALDO PARAMO |
| HVAC-Final | 12/14/2022 | Approved | OSVALDO PARAMO |
| SGSOV-Seismic Gas S/O Valve | 12/14/2022 | SGSOV Approved | OSVALDO PARAMO |
| Smoke Detectors | 12/14/2022 | Approved | OSVALDO PARAMO |
| Final | 12/21/2022 | OK to Issue CofO | OSVALDO PARAMO |
| Service/Power Release | 1/9/2023 | Approved | OSVALDO PARAMO |