1203 W ROLLAND CURTIS PL 90037

Certificate Information: 1203 W ROLLAND CURTIS PL 90037

Application / Permit
21010-10000-05014
Plan Check / Job No.
B21LA18062
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Dwelling - Single Family
Work Description
(N) 3-STORY SINGLE FAMILY DWELLING WITH 2-CAR GARAGE.
Permit Issued
Issued on 4/27/2022
Issuing Office
Current Status
CofO Issued on 8/7/2023
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/27/2021 APPLICANT
Assigned to Plan Check Engineer 10/14/2021 DANIEL YIP
Corrections Issued 10/19/2021 DANIEL YIP
Quality Review Completed 10/27/2021 TEODORO DIAZ RODRIGUEZ
Plan Check Approved 3/18/2022 DANIEL YIP
Issued 4/27/2022 APPLICANT
Building Plans Picked Up 5/4/2022 APPLICANT
CofO in Progress 8/2/2023 SABAS ALONSO
Permit Finaled 8/7/2023 DEROLD HAUFF
CofO Issued 8/7/2023 DEROLD HAUFF
Permit Finaled 8/7/2023 DEROLD HAUFF

Permit Application Clearance Information

Address approval Cleared 11/24/2021 CHRISTOPHER ROCHA
Eng Process Fee Ord 176,300 Cleared 12/2/2021 CHRISTOPHER ROCHA
Sewer availability Cleared 12/2/2021 CHRISTOPHER ROCHA
Frnt yard landscape/Water mgmt Cleared 12/14/2021 MAXFIELD VERMY
ZI Cleared 12/14/2021 JASON CHAN
Hydrant and Access approval Cleared 2/11/2022 KURT CORRAL
Low Impact Development Cleared 3/4/2022 SUNG JOON WON
Roof/Waste drainage to street Cleared 3/11/2022 CHRISTOPHER ROCHA

Contact Information

Contractor Emerald Builders And Developers; Lic. No.: 1068007-B 1412 W 22ND STREET      LOS ANGELES, CA 90007
Engineer Alvarado,, Carlos Humberto; Lic. No.: C19857 745 N WALNUTHAVEN DR      WEST COVINA, CA 91790
Engineer Salto,, Alvaro; Lic. No.: C83859 2543 E NORMAN AVE      WEST COVINA, CA 91791
Engineer Zhong,, Raymond Meng; Lic. No.: M27635 2416 W VALLEY BLVD      ALHAMBRA, CA 91803

Inspector Information

SABAS ALONSO, (213) 202-3468 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Underground Mechanical 6/6/2022 Approved SABAS ALONSO
Footing/Foundation/Slab 6/27/2022 Approved SABAS ALONSO
Deputy Reinf. Concrete 6/30/2022 Conditional Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/1/2022 Partial Approval SABAS ALONSO
Floor/Roof Diaphrgm/Shear Wall 8/18/2022 Partial Approval SABAS ALONSO
ELECTRICAL-Rough 10/25/2022 Approved SABAS ALONSO
HVAC-Rough 10/25/2022 Approved SABAS ALONSO
PLUMBING-Rough 10/25/2022 Not Ready for Inspection SABAS ALONSO
BUILDING-Rough-Frame 11/3/2022 Corrections Issued SABAS ALONSO
Green Building Rough 11/3/2022 Approved SABAS ALONSO
PLUMBING-Rough 11/3/2022 Approved SABAS ALONSO
Verify Sprinkler Sign Off 11/3/2022 Approved SABAS ALONSO
Insulation 11/23/2022 Approved JAMES CHAVEZ
Drywall Nailing 12/2/2022 Approved SABAS ALONSO
BUILDING-Rough-Frame 7/11/2023 Approved SABAS ALONSO
Final 7/11/2023 Corrections Issued SABAS ALONSO
Green Building Final 7/11/2023 Approved SABAS ALONSO
SGSOV-Seismic Gas S/O Valve 7/11/2023 SGSOV Approved SABAS ALONSO
Smoke Detectors 7/11/2023 Approved SABAS ALONSO
Final 7/14/2023 Corrections Issued SABAS ALONSO
Final 8/1/2023 OK to Issue CofO SABAS ALONSO
Service/Power Release 8/1/2023 Approved SABAS ALONSO