1252-1254 W 37TH ST 90007
Certificate Information: 1252-1254 W 37TH ST 90007
- Application / Permit
- 21010-10000-05013
- Plan Check / Job No.
- B21LA18059
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) 4-STORY DUPLEX WITH ATTACHED 4-CAR GARAGE
- Permit Issued
- Issued on 4/29/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/26/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/27/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/14/2021 | DANIEL YIP |
| Corrections Issued | 10/18/2021 | DANIEL YIP |
| Quality Review Completed | 10/21/2021 | KEN GILL |
| Building Plans Picked Up | 10/26/2021 | APPLICANT |
| Plan Check Approved | 4/26/2022 | DANIEL YIP |
| Issued | 4/29/2022 | APPLICANT |
| CofO in Progress | 1/16/2024 | SABAS ALONSO |
| Permit Finaled | 1/26/2024 | DEROLD HAUFF |
| CofO Issued | 1/26/2024 | DEROLD HAUFF |
| Permit Finaled | 1/26/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/2/2021 | STEVE MELGAR |
| Eng Process Fee Ord 176,300 | Cleared | 11/3/2021 | CINDY QI |
| Sewer availability | Cleared | 11/3/2021 | CINDY QI |
| Roof/Waste drainage to street | Cleared | 12/6/2021 | CINDY QI |
| Frnt yard landscape/Water mgmt | Cleared | 12/30/2021 | ANACANY HURTADO |
| Low Impact Development | Cleared | 1/14/2022 | MARTIN FRAGOSO |
| Hydrant and Access approval | Cleared | 3/29/2022 | GREGORY HOERNER |
| Building over 36-ft | Cleared | 4/26/2022 | CALOSHA APPROVED |
Contact Information
| Contractor | Lida International Building System; Lic. No.: 1064214-B | 416 N LA FAYETTE PARK PL LOS ANGELES, CA 90026 |
| Engineer | Salto,, Alvaro; Lic. No.: C83859 | 2543 E NORMAN AVE WEST COVINA, CA 91791 |
Inspector Information
| SABAS ALONSO, (213) 202-3468 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Sewer | 7/6/2022 | Approved | SABAS ALONSO |
| Underground Mechanical | 7/6/2022 | Partial Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 7/20/2022 | Partial Approval | SABAS ALONSO |
| Excavation/Setback/Form/Re-Bar | 8/3/2022 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 8/3/2022 | Conditional Approval | SABAS ALONSO |
| Footing/Foundation/Slab | 8/24/2022 | Approved | JOAQUIN GREENOUGH |
| METHANE-Barrier | 8/24/2022 | Approved | JOAQUIN GREENOUGH |
| METHANE-Subgrade | 8/24/2022 | Approved | JOAQUIN GREENOUGH |
| Floor/Roof Diaphrgm/Shear Wall | 10/11/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 10/19/2022 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/2/2022 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 11/29/2022 | Partial Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 12/21/2022 | Not Ready for Inspection | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 3/22/2023 | Approved | SABAS ALONSO |
| Deputy Wood Construction | 3/23/2023 | Approved | SABAS ALONSO |
| ELECTRICAL-Rough | 3/28/2023 | Not Ready for Inspection | SABAS ALONSO |
| PLUMBING-Rough | 3/28/2023 | Not Ready for Inspection | SABAS ALONSO |
| ELECTRICAL-Rough | 4/26/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 4/26/2023 | Not Ready for Inspection | SABAS ALONSO |
| HVAC-Rough | 5/4/2023 | Approved | SABAS ALONSO |
| PLUMBING-Rough | 5/4/2023 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/10/2023 | Not Ready for Inspection | SABAS ALONSO |
| Green Building Rough | 5/10/2023 | Approved | SABAS ALONSO |
| METHANE-Rough | 5/10/2023 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 5/10/2023 | Not Ready for Inspection | SABAS ALONSO |
| Wood Frame | 5/19/2023 | Corrections Issued | SABAS ALONSO |
| BUILDING-Rough-Frame | 5/26/2023 | Approved | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 5/26/2023 | Approved | SABAS ALONSO |
| Insulation | 5/26/2023 | Approved | SABAS ALONSO |
| Verify Sprinkler Sign Off | 5/26/2023 | Approved | SABAS ALONSO |
| Drywall Nailing | 6/6/2023 | Approved | SABAS ALONSO |
| Gas Test | 7/14/2023 | Not Ready for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 7/14/2023 | Approved | SABAS ALONSO |
| Shower Pan | 7/14/2023 | Approved | SABAS ALONSO |
| Final | 11/28/2023 | Corrections Issued | SABAS ALONSO |
| Green Building Final | 11/28/2023 | Approved | SABAS ALONSO |
| SGSOV-Seismic Gas S/O Valve | 11/28/2023 | SGSOV Approved | SABAS ALONSO |
| Service/Power Release | 11/28/2023 | Approved | SABAS ALONSO |
| Smoke Detectors | 11/28/2023 | Approved | SABAS ALONSO |
| Final | 12/1/2023 | Corrections Issued | SABAS ALONSO |
| Service/Power Release | 12/1/2023 | Approved | SABAS ALONSO |
| Final | 12/12/2023 | Corrections Issued | SABAS ALONSO |
| Final | 1/10/2024 | Corrections Issued | SABAS ALONSO |
| Final | 1/12/2024 | OK to Issue CofO | SABAS ALONSO |