5120 N ROCKLAND AVE 90041
Certificate Information: 5120 N ROCKLAND AVE 90041
- Application / Permit
- 21010-10000-04952
- Plan Check / Job No.
- B21LA17829
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER ORDINACE (1-STORY)
- Permit Issued
- Issued on 6/5/2023
- Issuing Office
- Current Status
- CofO Issued on 12/5/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 10/5/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/4/2021 | CARLOS MONTES |
| Corrections Issued | 11/9/2021 | CARLOS MONTES |
| Quality Review Completed | 11/16/2021 | HERNAN ARREOLA |
| Plan Check Approved | 3/16/2023 | CARLOS MONTES |
| Issued | 6/5/2023 | APPLICANT |
| CofO in Progress | 12/4/2023 | CRAIG VAUGHAN |
| CofO Issued | 12/5/2023 | DEROLD HAUFF |
| Permit Finaled | 12/5/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 1/27/2022 | CHRISTOPHER ROCHA |
| Eng Process Fee Ord 176,300 | Cleared | 1/28/2022 | CHRISTOPHER ROCHA |
| Sewer availability | Cleared | 1/28/2022 | CHRISTOPHER ROCHA |
| Grading Pre-Inspection | Cleared | 9/29/2022 | KIRK LINKLATER |
| Construction near power lines | Cleared | 11/16/2022 | RIDWAN HARDY |
| Low Impact Development | Cleared | 12/7/2022 | LONDY ALVARADO |
| Roof/Waste drainage to street | Cleared | 12/7/2022 | AMAAN MALIK |
| GPI Written Notices | Cleared | 3/16/2023 | CARLOS MONTES |
Contact Information
| Contractor | Gaga Builders Inc; Lic. No.: 1038675-B | , |
| Engineer | Barakat,, Fouad Chafic; Lic. No.: C67449 | 8916 LONGDON AVE #C TEMPLE CITY, CA 91780 |
Inspector Information
| RONNIE MEDINA, (213) 469-5852 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/8/2023 | Not Ready for Inspection | CRAIG VAUGHAN |
| Pre-Inspection | 6/8/2023 | Partial Inspection | CRAIG VAUGHAN |
| Underground Mechanical | 6/16/2023 | Approved | BRIAN SULLIVAN |
| Footing/Foundation/Slab | 6/21/2023 | Approved | BRIAN SULLIVAN |
| BUILDING-Rough-Frame | 7/12/2023 | Partial Approval | CRAIG VAUGHAN |
| Green Building Rough | 7/12/2023 | Approved | CRAIG VAUGHAN |
| PLUMBING-Rough | 7/12/2023 | Approved | CRAIG VAUGHAN |
| BUILDING-Rough-Frame | 7/25/2023 | Approved | CRAIG VAUGHAN |
| ELECTRICAL-Rough | 7/25/2023 | Approved | CRAIG VAUGHAN |
| HVAC-Rough | 7/25/2023 | Approved | CRAIG VAUGHAN |
| Verify Sprinkler Sign Off | 7/25/2023 | Approved | CRAIG VAUGHAN |
| Insulation | 8/11/2023 | Approved | CRAIG VAUGHAN |
| Interior/Exterior Lathing | 8/11/2023 | Partial Approval | CRAIG VAUGHAN |
| Drywall Nailing | 8/15/2023 | Approved | JOSH MEISTER |
| Interior/Exterior Lathing | 8/24/2023 | Approved | BRIAN SULLIVAN |
| Shower Pan | 8/24/2023 | Approved | BRIAN SULLIVAN |
| Final | 11/17/2023 | Corrections Issued | CRAIG VAUGHAN |
| Green Building Final | 11/17/2023 | Approved | CRAIG VAUGHAN |
| SGSOV-Seismic Gas S/O Valve | 11/17/2023 | SGSOV Approved | CRAIG VAUGHAN |
| Service/Power Release | 11/17/2023 | Approved | CRAIG VAUGHAN |
| Smoke Detectors | 11/17/2023 | Approved | CRAIG VAUGHAN |
| Final | 12/1/2023 | OK to Issue CofO | CRAIG VAUGHAN |