4720 S ST ANDREWS PL 90062
Certificate Information: 4720 S ST ANDREWS PL 90062
- Application / Permit
- 21010-10000-04937
- Plan Check / Job No.
- B21LA17809
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (2) Duplex
- Work Description
- (N) 2-STORY DUPLEX WITH ATTACHED 3 CAR GARAGE
- Permit Issued
- Issued on 6/21/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 1/7/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/22/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 10/7/2021 | MAHNAZ NOURHASHEMI |
| Corrections Issued | 10/13/2021 | MAHNAZ NOURHASHEMI |
| Quality Review Completed | 10/21/2021 | KEN GILL |
| Building Plans Picked Up | 10/25/2021 | APPLICANT |
| Plan Check Approved | 12/3/2021 | MAHNAZ NOURHASHEMI |
| Issued | 6/21/2022 | APPLICANT |
| CofO in Progress | 12/31/2022 | ALEJANDRO DE ARTOLA |
| Permit Finaled | 1/7/2023 | DEROLD HAUFF |
| CofO Issued | 1/7/2023 | DEROLD HAUFF |
| Permit Finaled | 1/7/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 11/9/2021 | WALLIE JONG |
| Permit | Cleared | 11/9/2021 | WALLIE JONG |
| Hydrant and Access approval | Cleared | 11/12/2021 | ROBERT DUFF |
| Low Impact Development | Cleared | 11/12/2021 | JONATAN VELASQUEZ |
| Roof/Waste drainage to street | Cleared | 11/12/2021 | CELINA MORENO |
| Eng Process Fee Ord 176,300 | Cleared | 11/15/2021 | WALLIE JONG |
| Sewer availability | Cleared | 11/15/2021 | WALLIE JONG |
Contact Information
| Contractor | K N Consulting Inc; Lic. No.: 993102-B | P O BOX 410 SUNSET BEACH, CA 90742 |
| Engineer | Madero,, Fidencio; Lic. No.: C81695 | 10002 PANGBORN AVE DOWNEY, CA 90240 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Excavation/Setback/Form/Re-Bar | 6/27/2022 | Approved | SABAS ALONSO |
| Footing/Foundation/Slab | 6/27/2022 | Approved | SABAS ALONSO |
| BUILDING-Rough-Frame | 7/15/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Sewer | 7/15/2022 | Approved | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 7/15/2022 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 7/18/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 7/19/2022 | Approved | ALEJANDRO DE ARTOLA |
| Wood Frame | 7/19/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Underground Mechanical | 7/20/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Floor/Roof Diaphrgm/Shear Wall | 8/1/2022 | Partial Approval | SABAS ALONSO |
| Deputy Wood Construction | 8/23/2022 | Conditional Approval | SABAS ALONSO |
| Floor/Roof Diaphrgm/Shear Wall | 8/24/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 9/2/2022 | Corrections Issued | ANDREW BEELI |
| PLUMBING-Rough | 9/2/2022 | Approved | ANDREW BEELI |
| BUILDING-Rough-Frame | 9/8/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Rough | 9/8/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 9/8/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 9/8/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/13/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Green Building Rough | 9/13/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| HVAC-Rough | 9/13/2022 | Approved | ALEJANDRO DE ARTOLA |
| Verify Sprinkler Sign Off | 9/13/2022 | Approved | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 9/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Rough | 9/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| Insulation | 9/16/2022 | Approved | ALEJANDRO DE ARTOLA |
| Drywall Nailing | 10/5/2022 | No Access for Inspection | SABAS ALONSO |
| Interior/Exterior Lathing | 10/5/2022 | No Access for Inspection | SABAS ALONSO |
| Drywall Nailing | 10/13/2022 | Approved | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/13/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| Interior/Exterior Lathing | 10/25/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 11/28/2022 | Partial Approval | ALEJANDRO DE ARTOLA |
| ELECTRICAL-Final | 12/23/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/23/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 12/23/2022 | Approved | ALEJANDRO DE ARTOLA |
| Green Building Final | 12/23/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/23/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/23/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 12/23/2022 | SGSOV Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 12/23/2022 | Approved | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 12/23/2022 | Approved | ALEJANDRO DE ARTOLA |
| Final | 12/30/2022 | OK to Issue CofO | ALEJANDRO DE ARTOLA |
| HVAC-Final | 12/30/2022 | Approved | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 12/30/2022 | Approved | ALEJANDRO DE ARTOLA |
| Service/Power Release | 12/30/2022 | Approved | ALEJANDRO DE ARTOLA |