200 N SERRANO AVE 90004
Certificate Information: 200 N SERRANO AVE 90004
- Application / Permit
- 21010-10000-04928
- Plan Check / Job No.
- B21LA17763
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- New two story detached ADU with a second-floor deck at the rear of the lot per LAMC 12.22 A.33 (c)-(d)
- Permit Issued
- Issued on 11/18/2022
- Issuing Office
- Metro
- Current Status
- CofO Issued on 11/8/2024
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 11/10/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 11/18/2021 | KESETE HAREGOT |
| Corrections Issued | 11/29/2021 | KESETE HAREGOT |
| Quality Review Completed | 11/30/2021 | FARUK SEZER |
| Building Plans Picked Up | 12/6/2021 | APPLICANT |
| Plan Check Approved | 7/5/2022 | KESETE HAREGOT |
| Issued | 11/18/2022 | APPLICANT |
| CofO in Progress | 10/9/2024 | JEFFREY MEAD |
| Permit Finaled | 11/8/2024 | DEROLD HAUFF |
| CofO Issued | 11/8/2024 | DEROLD HAUFF |
| Permit Finaled | 11/8/2024 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 4/13/2022 | JEANETTE VONG |
| Eng Process Fee Ord 176,300 | Cleared | 4/21/2022 | JEANETTE VONG |
| Sewer availability | Cleared | 4/21/2022 | JEANETTE VONG |
| Low Impact Development | Cleared | 6/1/2022 | SARAH YOUSSEF |
| Roof/Waste drainage to street | Cleared | 6/3/2022 | CINDY QI |
| Green Code | Cleared | 7/5/2022 | KESETE HAREGOT |
Contact Information
| Contractor | All View Construction Inc; Lic. No.: 1068957-B | 1189 S KENISTONE AVE LOS ANGELES, CA 90019 |
| Engineer | Rhee,, Kyle; Lic. No.: C78215 | 2753 WAVERLY DR 403 LOS ANGELES, CA 90039 |
Inspector Information
| JEFFREY MEAD, (213) 202-3240 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| BUILDING-Rough-Frame | 2/14/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Final | 2/14/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Footing/Foundation/Slab | 2/14/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Final | 2/14/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Green Building Rough | 2/14/2023 | Not Ready for Inspection | STUART CHAPMAN |
| SGSOV-Seismic Gas S/O Valve | 2/14/2023 | SGSOV Not Ready | STUART CHAPMAN |
| Service/Power Release | 2/14/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Smoke Detectors | 2/14/2023 | Not Ready for Inspection | STUART CHAPMAN |
| Underground Mechanical | 2/14/2023 | Partial Approval | STUART CHAPMAN |
| Verify Sprinkler Sign Off | 2/14/2023 | Not Ready for Inspection | STUART CHAPMAN |
| ELECTRICAL-Rough | 2/21/2023 | Partial Approval | JOSEPH MCGARRY |
| Excavation/Setback/Form/Re-Bar | 2/21/2023 | Conditional Approval | JOSEPH MCGARRY |
| Floor/Roof Diaphrgm/Shear Wall | 3/15/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Green Building Rough | 3/15/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 3/15/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 3/16/2023 | Partial Approval | JEFFREY MEAD |
| Deputy Wood Construction | 3/17/2023 | Partial Approval | JEFFREY MEAD |
| Deputy Wood Construction | 3/31/2023 | Partial Approval | JEFFREY MEAD |
| Floor/Roof Diaphrgm/Shear Wall | 4/4/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 4/25/2023 | Not Ready for Inspection | JEFFREY MEAD |
| Rough-Elec/Plmb/HVAC | 4/25/2023 | Partial Approval | JEFFREY MEAD |
| BUILDING-Rough-Frame | 5/1/2023 | Partial Approval | JEFFREY MEAD |
| Gas Test | 5/1/2023 | Approved | JEFFREY MEAD |
| Green Building Rough | 5/1/2023 | Approved | JEFFREY MEAD |
| HVAC-Rough | 5/1/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Rough | 5/1/2023 | Approved | JEFFREY MEAD |
| Verify Sprinkler Sign Off | 5/1/2023 | Approved | JEFFREY MEAD |
| BUILDING-Rough-Frame | 5/3/2023 | Approved | JEFFREY MEAD |
| Insulation | 5/3/2023 | Approved | JEFFREY MEAD |
| Drywall Nailing | 5/16/2023 | Approved | JEFFREY MEAD |
| Interior/Exterior Lathing | 5/16/2023 | Approved | JEFFREY MEAD |
| Underground Mechanical | 8/8/2023 | Partial Approval | SCOTT FINNILA |
| ELECTRICAL-Final | 9/14/2023 | Corrections Issued | JEFFREY MEAD |
| Final | 11/28/2023 | Corrections Issued | JEFFREY MEAD |
| HVAC-Final | 11/28/2023 | Approved | JEFFREY MEAD |
| PLUMBING-Final | 11/28/2023 | Approved | JEFFREY MEAD |
| Final | 8/16/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Footing/Foundation/Slab | 8/16/2024 | Approved | ALIZAH MAYAGOITIA |
| Green Building Final | 8/16/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| SGSOV-Seismic Gas S/O Valve | 8/16/2024 | SGSOV Approved | ALIZAH MAYAGOITIA |
| Service/Power Release | 8/16/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Smoke Detectors | 8/16/2024 | Not Ready for Inspection | ALIZAH MAYAGOITIA |
| Final | 9/9/2024 | Corrections Issued | JEFFREY MEAD |
| Green Building Final | 9/9/2024 | Approved | JEFFREY MEAD |
| Service/Power Release | 9/9/2024 | Not Required | JEFFREY MEAD |
| Smoke Detectors | 9/9/2024 | Approved | JEFFREY MEAD |
| ELECTRICAL-Final | 10/8/2024 | Approved | JEFFREY MEAD |
| Final | 10/8/2024 | OK to Issue CofO | JEFFREY MEAD |