2914-2914 1/2 E GARNET ST 90023

Certificate Information: 2914-2914 1/2 E GARNET ST 90023

Application / Permit
21010-10000-04923
Plan Check / Job No.
B21LA17750
Group
Building
Type
Bldg-New
Sub-Type
1 or 2 Family Dwelling
Primary Use
(1) Accessory Dwelling Unit
Work Description
NEW DETACHED TWO ADU PER STATE LAW CA Govt. Code 65852.2(e)(1)(D) and applicable part2 of LAMC 12.22 A.33 (c)-(d), (g) [CUGU-Project is a municipal project located within 1,000 feet of a Freeway or State Route specified in LAMC Section 13.18.F.4. ]
Permit Issued
Issued on 8/21/2023
Issuing Office
Metro
Current Status
CofO Issued on 9/5/2025
Certificate of Occupancy
CofO Issued More Information

Permit Application Status History

Submitted 9/22/2021 APPLICANT
Assigned to Plan Check Engineer 10/28/2021 MAHNAZ NOURHASHEMI
Corrections Issued 11/4/2021 MAHNAZ NOURHASHEMI
Quality Review Completed 11/16/2021 TEODORO DIAZ RODRIGUEZ
Building Plans Picked Up 11/24/2021 APPLICANT
Applicant returned to address corrections 4/10/2023 MAHNAZ NOURHASHEMI
Applicant returned to address corrections 6/9/2023 MAHNAZ NOURHASHEMI
Plan Check Approved 8/21/2023 CHAD DOI
Issued 8/21/2023 APPLICANT
CofO in Progress 8/27/2025 FREDDIE RIVERA
No Progress 9/1/2025 DEROLD HAUFF
CofO in Progress 9/1/2025 DEROLD HAUFF
CofO Issued 9/5/2025 DEROLD HAUFF
Permit Finaled 9/5/2025 DEROLD HAUFF

Permit Application Clearance Information

Grading Pre-Inspection Cleared 12/8/2021 ALEXANDER ANDREWS
Clean Up Green Up Cleared 4/7/2022 LOUIS ORTEGA
Address approval Cleared 4/11/2022 AMAAN MALIK
Roof/Waste drainage to street Cleared 4/11/2022 AMAAN MALIK
Hydrant and Access approval Cleared 5/16/2022 CINDY JOSSELYN
Eng Process Fee Ord 176,300 Cleared 6/22/2023 JEANIE LAM
Sewer availability Cleared 6/22/2023 JEANIE LAM

Contact Information

Contractor Owner-Builder       ,

Inspector Information

FREDDIE RIVERA, (213) 202-3437 Office Hours: 7:00-8:00 AM MON-FRI

Pending Inspections

No Data Available.

Inspection Request History

Excavation/Setback/Form/Re-Bar 10/30/2023 Corrections Issued FREDDIE RIVERA
Footing/Foundation/Slab 10/30/2023 Partial Inspection FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 11/1/2023 Partial Inspection FREDDIE RIVERA
Footing/Foundation/Slab 11/1/2023 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 11/1/2023 Partial Inspection FREDDIE RIVERA
Excavation/Setback/Form/Re-Bar 11/6/2023 Approved FREDDIE RIVERA
PLUMBING-Rough 11/6/2023 Partial Approval FREDDIE RIVERA
Floor/Roof Diaphrgm/Shear Wall 11/27/2023 Approved FREDDIE RIVERA
ELECTRICAL-Rough 12/12/2023 Partial Inspection FREDDIE RIVERA
HVAC-Rough 12/12/2023 Partial Inspection FREDDIE RIVERA
PLUMBING-Rough 12/12/2023 Partial Inspection FREDDIE RIVERA
BUILDING-Rough-Frame 12/21/2023 Approved ENRIQUE MIRELES
Green Building Rough 12/21/2023 Approved ENRIQUE MIRELES
HVAC-Rough 12/21/2023 Approved ENRIQUE MIRELES
MERV13>=Rough 12/21/2023 Approved ENRIQUE MIRELES
Shower Pan 12/21/2023 Approved ENRIQUE MIRELES
Verify Sprinkler Sign Off 12/21/2023 Approved ENRIQUE MIRELES
Insulation 12/29/2023 Approved ENRIQUE MIRELES
Interior/Exterior Lathing 12/29/2023 Corrections Issued ENRIQUE MIRELES
Drywall Nailing 1/9/2024 Approved FREDDIE RIVERA
Interior/Exterior Lathing 1/9/2024 Approved FREDDIE RIVERA
Gas Test 2/23/2024 Approved FREDDIE RIVERA
PLUMBING-Rough 2/23/2024 Partial Inspection FREDDIE RIVERA
Sewer 2/23/2024 Approved FREDDIE RIVERA
ELECTRICAL-Final 7/12/2024 Corrections Issued FREDDIE RIVERA
Gas Test 7/12/2024 Approved FREDDIE RIVERA
HVAC-Final 7/12/2024 Corrections Issued FREDDIE RIVERA
PLUMBING-Final 7/12/2024 Approved FREDDIE RIVERA
ELECTRICAL-Final 10/18/2024 Approved JOHN QUINTANILLA
Final 10/23/2024 Corrections Issued JOHN QUINTANILLA
Footing/Foundation/Slab 10/23/2024 Approved JOHN QUINTANILLA
Green Building Final 10/23/2024 Approved JOHN QUINTANILLA
MERV13>=Final 10/23/2024 Approved JOHN QUINTANILLA
SGSOV-Seismic Gas S/O Valve 10/23/2024 SGSOV Approved JOHN QUINTANILLA
Service/Power Release 10/23/2024 Not Ready for Inspection JOHN QUINTANILLA
Smoke Detectors 10/23/2024 Approved JOHN QUINTANILLA
Service/Power Release 2/14/2025 Approved OSVALDO PARAMO
Final 8/26/2025 OK to Issue CofO FREDDIE RIVERA