1333 W 67TH ST 90044
Certificate Information: 1333 W 67TH ST 90044
- Application / Permit
- 21010-10000-04896
- Plan Check / Job No.
- B21LA17673
- Group
- Building
- Type
- Bldg-New
- Sub-Type
- 1 or 2 Family Dwelling
- Primary Use
- (1) Accessory Dwelling Unit
- Work Description
- NEW DETACHED ADU PER ORDINANCE (1-STORY)
- Permit Issued
- Issued on 2/24/2022
- Issuing Office
- Current Status
- CofO Issued on 1/14/2023
- Certificate of Occupancy
- CofO Issued More Information
Permit Application Status History
| Submitted | 9/21/2021 | APPLICANT |
| Assigned to Plan Check Engineer | 9/22/2021 | CARLOS MONTES |
| Corrections Issued | 9/23/2021 | CARLOS MONTES |
| Plan Check Approved | 2/17/2022 | CARLOS MONTES |
| Issued | 2/24/2022 | APPLICANT |
| CofO in Progress | 1/10/2023 | ENRIQUE MIRELES |
| Permit Finaled | 1/14/2023 | DEROLD HAUFF |
| CofO Issued | 1/14/2023 | DEROLD HAUFF |
| Permit Finaled | 1/14/2023 | DEROLD HAUFF |
Permit Application Clearance Information
| Address approval | Cleared | 10/16/2021 | RENZ SORIANO |
| Eng Process Fee Ord 176,300 | Cleared | 10/20/2021 | RENZ SORIANO |
| Sewer availability | Cleared | 10/20/2021 | RENZ SORIANO |
| Low Impact Development | Cleared | 2/7/2022 | TA ANH |
| Roof/Waste drainage to street | Cleared | 2/7/2022 | JEANETTE VONG |
Contact Information
| Contractor | Owner-Builder | , |
| Engineer | Kim,, Hong Kook; Lic. No.: C64529 | 3600 WILSHIRE BLVD STE 1903 LOS ANGELES, CA 90010 |
Inspector Information
| BARRY HACHE, (213) 202-9851 | Office Hours: 7:00-8:00 AM MON-FRI |
Pending Inspections
| No Data Available. |
Inspection Request History
| Footing/Foundation/Slab | 3/16/2022 | Approved | ENRIQUE MIRELES |
| Underground Mechanical | 3/30/2022 | Approved | ENRIQUE MIRELES |
| Wood Frame | 3/30/2022 | Approved | ENRIQUE MIRELES |
| Floor/Roof Diaphrgm/Shear Wall | 5/4/2022 | Approved | ENRIQUE MIRELES |
| HVAC-Rough | 5/4/2022 | Approved | ENRIQUE MIRELES |
| ELECTRICAL-Rough | 5/27/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| PLUMBING-Rough | 5/27/2022 | Not Ready for Inspection | ENRIQUE MIRELES |
| Wood Frame | 5/27/2022 | Corrections Issued | ENRIQUE MIRELES |
| PLUMBING-Rough | 6/6/2022 | Approved | ENRIQUE MIRELES |
| Rough-Elec/Plmb/HVAC | 6/6/2022 | Approved | ENRIQUE MIRELES |
| Wood Frame | 6/6/2022 | Approved | ENRIQUE MIRELES |
| Insulation | 6/13/2022 | Conditional Approval | JOAQUIN GREENOUGH |
| Interior/Exterior Lathing | 6/13/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Green Building Rough | 6/17/2022 | Not Ready for Inspection | SHAVONNE ESPINOZA |
| Interior/Exterior Lathing | 6/17/2022 | Corrections Issued | SHAVONNE ESPINOZA |
| Drywall Nailing | 6/28/2022 | Corrections Issued | JOAQUIN GREENOUGH |
| Green Building Rough | 6/28/2022 | Not Ready for Inspection | JOAQUIN GREENOUGH |
| Drywall Nailing | 6/30/2022 | No Access for Inspection | ENRIQUE MIRELES |
| Green Building Rough | 6/30/2022 | Approved | ENRIQUE MIRELES |
| Drywall Nailing | 7/1/2022 | Approved | HORACE FULTZ |
| Green Building Rough | 7/1/2022 | Approved | HORACE FULTZ |
| ELECTRICAL-Final | 10/5/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| Gas Test | 10/5/2022 | Approved | ALEJANDRO DE ARTOLA |
| HVAC-Final | 10/5/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| PLUMBING-Final | 10/5/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| SGSOV-Seismic Gas S/O Valve | 10/5/2022 | SGSOV Not Ready | ALEJANDRO DE ARTOLA |
| Smoke Detectors | 10/5/2022 | Corrections Issued | ALEJANDRO DE ARTOLA |
| BUILDING-Rough-Frame | 10/28/2022 | Not Ready for Inspection | ANTHONY EGSON |
| ELECTRICAL-Final | 10/28/2022 | Corrections Issued | ANTHONY EGSON |
| Final | 10/28/2022 | Corrections Issued | ANTHONY EGSON |
| Green Building Final | 10/28/2022 | Approved | ANTHONY EGSON |
| HVAC-Final | 10/28/2022 | Corrections Issued | ANTHONY EGSON |
| PLUMBING-Final | 10/28/2022 | Approved | ANTHONY EGSON |
| SGSOV-Seismic Gas S/O Valve | 10/28/2022 | SGSOV Approved | ANTHONY EGSON |
| Service/Power Release | 10/28/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Smoke Detectors | 10/28/2022 | Approved | ANTHONY EGSON |
| Verify Sprinkler Sign Off | 10/28/2022 | Not Ready for Inspection | ANTHONY EGSON |
| Final | 11/4/2022 | Partial Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 11/17/2022 | No Access for Inspection | ENRIQUE MIRELES |
| Final | 11/17/2022 | No Access for Inspection | ENRIQUE MIRELES |
| Service/Power Release | 11/17/2022 | No Access for Inspection | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 11/17/2022 | No Access for Inspection | ENRIQUE MIRELES |
| BUILDING-Rough-Frame | 1/9/2023 | Approved | ENRIQUE MIRELES |
| Final | 1/9/2023 | OK to Issue CofO | ENRIQUE MIRELES |
| Service/Power Release | 1/9/2023 | Approved | ENRIQUE MIRELES |
| Verify Sprinkler Sign Off | 1/9/2023 | Approved | ENRIQUE MIRELES |